Mont. Code Ann. § 71-3-902 (2026)

How Lien Obtained

✓ laws through the 2025 session (checked July 2026)
Find cases: SyfertCases citing this section MT-LEGleg.mt.gov JustiaTitle on Justia CornellLII Search CasesGoogle Scholar

TITLE 71. MORTGAGES, PLEDGES, AND LIENS

CHAPTER 3. LIENS

Part 9. Fertilizer and Pesticide Liens

How Lien Obtained

71-3-902. How lien obtained. (1) A person, firm, corporation, or partnership that is entitled to a lien under this part shall, within 90 days after the last labor or service was performed or material furnished in crop dusting or spraying grains or crops, file in the office of the secretary of state a statement of agricultural lien as provided in 71-3-125.

(2) A person, firm, corporation, or partnership that is entitled to a lien and that intends to file a lien under this part shall give notice, by certified mail, of intent to file to the person, firm, corporation, or partnership for which labor or service was performed or materials furnished.

History: En. Sec. 2, Ch. 205, L. 1953; amd. Sec. 1, Ch. 65, L. 1955; R.C.M. 1947, 45-1402; amd. Sec. 11, Ch. 295, L. 1987; amd. Sec. 7, Ch. 529, L. 1989; amd. Sec. 1, Ch. 56, L. 1995; amd. Sec. 1, Ch. 152, L. 1999.

Notes of Decisions
Cited in 2 cases, 2008–2009 · leading case: Stockman Bank of Montana v. Mon-Kota, Inc., 2008 MT 74, 180 P.3d 1125.
Stockman Bank of Montana v. Mon-Kota, Inc., 2008 MT 74, 180 P.3d 1125. · cites it 33× “” ¶15 Section 71-3-902, MCA, provides: (1) A person, firm, corporation, or partnership that is entitled *123 to a lien under this part shall, within 90 days after the last labor or service was performed or material furnished in crop dusting or spraying grains or crops, file in…”
In Re Aznoe Agribiz, Inc., 416 B.R. 755 (Bankr. D. Mont. 2009). · cites it 4× “The requirements for obtaining an agricultural lien are provided at § 71-3-902: 71-3-902. How lien obtained. (1) A person, firm, corporation, or partnership that is entitled to a lien under this part shall, within 90 days after the last labor or service was performed or material…”
Mont. Code Ann. § 71-3-902(1): 1 case
Stockman Bank of Montana v. Mon-Kota, Inc., 2008 MT 74, 180 P.3d 1125. “” ¶15 Section 71-3-902, MCA, provides: (1) A person, firm, corporation, or partnership that is entitled *123 to a lien under this part shall, within 90 days after the last labor or service was performed or material furnished in crop dusting or spraying grains or crops, file in…”
Mont. Code Ann. § 71-3-902(2): 1 case
Stockman Bank of Montana v. Mon-Kota, Inc., 2008 MT 74, 180 P.3d 1125. “” ¶15 Section 71-3-902, MCA, provides: (1) A person, firm, corporation, or partnership that is entitled *123 to a lien under this part shall, within 90 days after the last labor or service was performed or material furnished in crop dusting or spraying grains or crops, file in…”