“Completion of the work of improvement” defined

✓ current as of July 2026
Find cases: SyfertCases citing this section NRSleg.state.nv.us (official) Justiaon Justia CornellLII Search CasesGoogle Scholar
NRS 108.22116  “Completion of the work of improvement” defined.  “Completion of the work of improvement” means:

      1.  The occupation or use by the owner, an agent of the owner or a representative of the owner of the work of improvement, accompanied by the cessation of all work on the work of improvement;

      2.  The acceptance by the owner, an agent of the owner or a representative of the owner of the work of improvement, accompanied by the cessation of all work on the work of improvement; or

      3.  The cessation of all work on a work of improvement for 30 consecutive days, provided a notice of completion is timely recorded and served and the work is not resumed under the same contract.

      (Added to NRS by 2003, 2587)

     

Notes of Decisions
Cited in 2 cases, 2016–2016 · leading case: Dykema Vs. Del Webb Communities, Inc., 2016 NV 82 (Nev. 2016).
Dykema Vs. Del Webb Communities, Inc., 2016 NV 82 (Nev. 2016). · cites it 2× “NRS 108.22116(3) explicitly defines "[c]ompletion of the work of improvement" as including "Wile cessation of all work on a work of improvement for 30 consecutive days, provided a notice of completion is timely recorded and served and the work is not resumed under the same…”
Dykema Vs. Del Webb Communities, Inc., 2016 NV 82 (Nev. 2016). “NRS 108.22116(3) explicitly defines "[c]ompletion of the work of improvement" as including "Wile cessation of all work on a work of improvement for 30 consecutive days, provided a notice of completion is timely recorded and served and the work is not resumed under the same…”
— Nev. Rev. Stat. § 108.22116(3) — 2 cases
Dykema Vs. Del Webb Communities, Inc., 2016 NV 82 (Nev. 2016). “NRS 108.22116(3) explicitly defines "[c]ompletion of the work of improvement" as including "Wile cessation of all work on a work of improvement for 30 consecutive days, provided a notice of completion is timely recorded and served and the work is not resumed under the same…”
Dykema Vs. Del Webb Communities, Inc., 2016 NV 82 (Nev. 2016). “NRS 108.22116(3) explicitly defines "[c]ompletion of the work of improvement" as including "Wile cessation of all work on a work of improvement for 30 consecutive days, provided a notice of completion is timely recorded and served and the work is not resumed under the same…”