§ 126. The decision. 1. The commission shall render a decision upon the record either granting or denying the application as filed or granting it upon such terms, conditions, limitations or modifications of the construction or operation of the facility as the commission may deem appropriate. If the commission denies the application, it shall file, with its order, an opinion stating in full its reasons for the denial. Except as provided in subdivision two of this section, the commission may not grant a certificate for the construction or operation of a major utility transmission facility, either as proposed or as modified by the commission, unless it shall find and determine: (a) the basis of the need for the facility; (b) the nature of the probable environmental impact; * (c) that the facility avoids or minimizes to the extent practicable any significant adverse environmental impact, considering the state of available technology and the nature and economics of the various alternatives, and other pertinent considerations including but not limited to, the effect on agricultural lands, wetlands, parklands and river corridors traversed; * NB Effective until December 31, 2030 * (c) that the facility represents the minimum adverse environmental impact, considering the state of available technology and the nature and economics of the various alternatives, and other pertinent considerations including but not limited to, the effect on agricultural lands, wetlands, parklands and river corridors traversed; * NB Effective December 31, 2030 * (d) that the facility avoids or minimizes to the extent practicable any significant adverse impact on active farming operations that produce crops, livestock and livestock products, as defined in section three hundred one of the agriculture and markets law, considering the state of available technology and the nature and economics of various alternatives, and the ownership and easement rights of the impacted property; * NB Effective until December 31, 2030 * (d) that the facility represents a minimum adverse impact on active farming operations that produce crops, livestock and livestock products, as defined in section three hundred one of the agriculture and markets law, considering the state of available technology and the nature and economics of various alternatives, and the ownership and easement rights of the impacted property; * NB Effective December 31, 2030 (e) in the case of an electric transmission line, (1) what part, if any, of the line shall be located underground; (2) that such facility conforms to a long-range plan for expansion of the electric power grid of the electric systems serving this state and interconnected utility systems, which will serve the interests of electric system economy and reliability; (f) in the case of a gas transmission line, that the location of the line will not pose an undue hazard to persons or property along the area traversed by the line; (g) that the location of the facility as proposed conforms to applicable state and local laws and regulations issued thereunder, all of which shall be binding upon the commission, except that the commission may refuse to apply any local ordinance, law, resolution or other action or any regulation issued thereunder or any local standard or requirement which would be otherwise applicable if it finds that as applied to the proposed facility such is unreasonably restrictive in view of the existing technology, or of factors of cost or economics, or of the needs of consumers whether located inside or outside of such municipality; (h) that the facility will serve the public interest, convenience, and necessity, provided, however, that a determination of necessity made by the power authority of the state of New York pursuant to section ten hundred five of the public authorities law for a major utility transmission facility for which an application has been filed prior to July first, nineteen hundred seventy-eight pursuant to section one hundred twenty-two of this chapter, shall be conclusive on the commission. 2. In the case of an electric transmission line to be constructed by the power authority of the state of New York and located in part under the waters of Long Island Sound and for the remaining part underground, the commission shall make only the findings and determinations required by paragraphs (b), (c) and (f) of subdivision one of this section and, on the basis of such findings and determinations, shall grant, grant in part, or deny the certificate. 3. If the commission determines that the location of all or a part of the proposed facility should be modified, it may condition its certificate upon such modification, provided that the municipalities and persons residing in such municipalities affected by the modification shall have had notice of the application as provided in subdivision two of section one hundred twenty-two. 4. A copy of the order and any opinion issued therewith pursuant to section one hundred twenty-seven shall be served upon each party.
Notes of Decisions
Cited in 10
cases (1 in the last 5 years), 1986–2023 · leading case: Niagara Mohawk Power Corp. v. Pub. Serv. Comm'n, 164 A.D.2d 502 (N.Y. App. Div. 3d Dep't 1990).
Niagara Mohawk Power Corp. v. Pub. Serv. Comm'n, 164 A.D.2d 502 (N.Y. App. Div. 3d Dep't 1990). “Petitioner first contends that the PSC misapplied the "public interest” requirement of Public Service Law § 126 (1) (g) by failing to make a comparative evaluation of the competing proposals and determining only that Selkirk’s proposal is in the public interest.”
Matter of Citizens for the Preserv. of Wainscott, Inc. v. New York State Pub. Serv. Commn., 216 A.D.3d 769 (N.Y. App. Div. 2d Dep't 2023). “ropriate mitigation, considered and thoroughly mitigated the SFEC project's construction impacts, carefully considered all proposed routes and rationally concluded that the Beach Lane route minimized adverse impacts to the greatest practicable extent, and rationally determined…”
CNG Transmission Corp. v. New York State Pub. Serv. Comm'n, 185 A.D.2d 671 (N.Y. App. Div. 4th Dep't 1992). “the future; that the pipeline would introduce competition into a monopolistic marketplace and thus lower prices to consumers; that Empire’s pipeline would enhance access to diverse markets of natural gas and would improve the availability and reliability of services; that…”
Skyview Acres Coop., Inc. v. Pub. Serv. Comm'n, 163 A.D.2d 600 (N.Y. App. Div. 2d Dep't 1990). “Additionally, pursuant to Public Service Law § 126 (1) (i), the PSC waived compliance with applicable provisions of the zoning ordinance of the Town of Clarkstown, which would not have permitted construction of the M&R facility at the Buena Vista Road site.”
Vill. of Tuckahoe v. Pub. Serv. Comm'n, 150 A.D.2d 466 (N.Y. App. Div. 2d Dep't 1989). “e Legislature determined that a new underground electric transmission line was necessary to supply Long Island with electricity from upstate sources, and it amended Public Service Law article VII to foreclose, as unnecessary, consideration by the Public Service Commission of the…”
MatterofEntergyNuclearPowerMarketing,LLCvNewYorkStatePublicServiceCommission, No. 517776 (N.Y. App. Div. 3d Dep't Nov. 13, 2014). “Ultimately, the Commission concluded that the applicants' proposal met the required statutory findings of Public Service Law § 126 and granted the EC&PN on April 18, 2013.”
Entergy Nuclear Power Mktg., LLC v. New York State Pub. Serv. Comm'n, 122 A.D.3d 1024 (N.Y. App. Div. 3d Dep't 2014). “Ultimately, the Commission concluded that the applicants’ proposal met the required statutory findings of Public Service Law § 126 and granted the EC&PN on April 18, 2013.”
Entergy Nuclear Power Mktg., LLC v. New York State Pub. Serv. Comm'n, 122 A.D.3d 1024 (N.Y. App. Div. 3d Dep't 2014). “Ultimately, the Commission concluded that the applicants’ proposal met the required statutory findings of Public Service Law § 126 and granted the EC&PN on April 18, 2013.”
City of New Rochelle v. Pub. Serv. Comm'n, 150 A.D.2d 441 (N.Y. App. Div. 2d Dep't 1989). “Furthermore, we note the absence of long-term noise or visual impact, heightened engineering feasibility, and decreased costs and delays.”
Delaney v. Pub. Serv. Comm'n, 123 A.D.2d 861 (N.Y. App. Div. 2d Dep't 1986). “Based on the record, we conclude that the commission fully complied with the requirements of Public Service Law § 126 (1) in analyzing the need for the project, its probable environmental impacts, and the manner in which those impacts could be reduced.”