Or. Rev. Stat. § 537.410 (2026)

Failure to commence or complete work, or to properly apply water, as grounds for cancellation of permit; irrigation districts, municipalities and public utilities excepted

Edition and currency
laws through the 2025 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2025 session (checked Sept. 2026) cited 1969–2013 3citing cases
At a glance

Courts have cited this section in 3 opinions since 1969. The most litigated part is subsection (1) (1 case).

      537.410 Failure to commence or complete work, or to properly apply water, as grounds for cancellation of permit; irrigation districts, municipalities and public utilities excepted. (1) Whenever the owner of a permit to appropriate the public waters of Oregon fails to commence actual construction work within the time required by law, or having commenced construction work as required by law, fails or neglects to prosecute the construction work with reasonable diligence, or fails to complete the construction work within the time required by law, or as fixed in the permit, or within such further time as may be allowed under ORS 537.230, or having completed construction work, fails or neglects to apply the water to beneficial use within the time fixed in the permit, the Water Resources Commission may cancel the permit on the records in the Water Resources Department as provided in ORS 537.410 to 537.450.

      (2) However, permits issued by the commission to irrigation districts for reclamation purposes under the irrigation district laws of this state, to municipal corporations for municipal uses or purposes or to public utilities complying with subsection (3) of this section for an energy facility granted a site certificate by the Energy Facility Siting Council, are not subject to cancellation under the provisions of ORS 537.410 to 537.450.

      (3) For a public utility to qualify under subsection (2) of this section:

      (a) The energy facility of the public utility must not be a facility required to be licensed under ORS chapter 543; and

      (b) The public utility must supply information every two years that demonstrates to the satisfaction of the commission that the conditions in the site certificate issued by the Energy Facility Siting Council contemplate the future use of the remaining portion of the water applied for in the original permit application. [Amended by 1985 c.673 §41; 1995 c.372 §1]

The 3 cases that cite Or. Rev. Stat. § 537.410 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 537.410 1×subsections: (1)cited by 24 cases
Where it cites § 537.410
“ORS 537.410(1). If the department determines that “an appropriation has been perfected in accordance with the provisions of the Water Rights Act,” however, the department issues a certificate to the applicant/ permittee.”
The case’s holding
The holder of a water use subject to transfer is the party with an ownership interest in the certificated water right rather than the user of the water.
Later courts cite it for
“holders of any water use subject to transfer.” · 3 citing courts
2
GREENWaterwatch of Oregon, Inc. v. Water Resources Dep't, 316 P.3d 330 (Or. Ct. App. 2013).
cites § 537.410 1×cited by 5 cases
Where it cites § 537.410
“260(4) (providing that a municipality may partially perfect not less than 25 percent of the water authorized by its permit; in that case, the department shall issue a certificate only for the amount perfected); ORS 537.410 - 537.450 (providing process for cancellation of…”
3
GREENGreen v. Wheeler, 458 P.2d 938 (Or. 1969).
cites § 537.410 1×cited by 10 cases
Where it cites § 537.410
“The cancellation shall have the same force and effect as cancellation of a permit in the proceedings provided for in ORS 537.410 and 537.450.” *430 Plaintiffs argue that ORS 537.260 (1) is applicable only to a case where a permit is issued but no' beneficial use of the water has yet been made under the permit; at this stage the right is inchoate only.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
196919912013

One bar per year. Tallest: 1 case in 1969. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Or.2Or. Ct. App.1
By subsection
(1)1 case
Fort Vannoy Irrigation Dist. v. Water Resources Comm'n, 188 P.3d 277 (Or. 2008).“ORS 537.410(1). If the department determines that “an appropriation has been perfected in accordance with the provisions of the Water Rights Act,” however, the department issues a certificate to the applicant/ permittee.”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2025 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.