Oregon Revised Statutes

Or. Rev. Stat. § 543A.100 (2026)

Final application for water right; application for water quality certification

✓ current as of May 2026
Find cases: SyfertCases citing this section ORSoregonlegislature.gov JustiaChapter on Justia CornellLII Search CasesGoogle Scholar

      543A.100 Final application for water right; application for water quality certification. Not less than two years before the expiration of the federal license for the project, the applicant shall submit the final application to reauthorize the water right and a request for certification under ORS 468B.040 and 33 U.S.C. 1341. The application submitted under this section shall be the same as the final application submitted to the Federal Energy Regulatory Commission for the new federal license for the project. [1997 c.449 §20]