Tex. Prop. Code § 53.056 (2026)
Derivative Claimant: Notice To Owner And Original Contractor
Edition and currency
Other sources
Courts have cited this section in 40 opinions since 1986, 6 of them in the last five years. The most litigated part is subsection (b) (12 cases).
Sec. 53.056. DERIVATIVE CLAIMANT: NOTICE TO OWNER AND ORIGINAL CONTRACTOR. (a) Except as provided by Section 53.057, a claimant other than an original contractor must give the notice prescribed by Subsections (a-1) and (a-2) for the lien to be valid.
(a-1) For all unpaid labor or materials provided, the claimant must send a notice of claim for unpaid labor or materials to the owner or reputed owner and the original contractor. The notice must be sent:
(1) for projects other than residential construction projects, not later than the 15th day of the third month after the month during which:
(A) the labor or materials were provided; or
(B) the undelivered specially fabricated materials would normally have been delivered; or
(2) for residential construction projects, not later than the 15th day of the second month after the month during which:
(A) the labor or materials were provided; or
(B) the undelivered specially fabricated materials would normally have been delivered.
(a-2) The notice must be in substantially the following form:
"NOTICE OF CLAIM FOR UNPAID LABOR OR MATERIALS
"WARNING: This notice is provided to preserve lien rights.
"Owner's property may be subject to a lien if sufficient funds are not withheld from future payments to the original contractor to cover this debt.
"Date:_______________
"Project description and/or address: _______________
"Claimant's name: _______________
"Type of labor or materials provided: _______________
"Original contractor's name: _______________
"Party with whom claimant contracted if different from original contractor: _______________
"Claim amount: _______________
"_______________ (Claimant's contact person)
"_______________ (Claimant's address)"
(a-3) The notice may include an invoice or billing statement.
(a-4) A claimant may give to the original contractor a written notice of an unpaid labor or materials invoice that is past due. A notice under this subsection is not required for a lien to be valid.
(b) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
(c) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
(d) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
(e) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
(f) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
Acts 1983, 68th Leg., p. 3540, ch. 576, Sec. 1, eff. Jan. 1, 1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 8, eff. Sept. 1, 1989; Acts 1997, 75th Leg., ch. 526, Sec. 8, eff. Sept. 1, 1997.
Amended by:
Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 10, eff. January 1, 2022.
Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 11, eff. January 1, 2022.
Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
- Where it cites § 53.056
- “Laws 4693 , 4696 (amended 1997) (current version at Tex. Prop.Code Ann. § 53.056 (West Supp.2002)).”
- The case’s holding
- A property owner cannot recover from a subcontractor for breach of contract or implied warranty in the absence of privity of contract or third-party beneficiary status.
- Where it cites § 53.056
- “” Tex. Prop.Code Ann. § 53.056(a) (West 2002).”
- The case’s holding
- A materialman's lien is invalid if the required notice is mailed without sufficient postage because such a mailing fails to satisfy statutory notice requirements.
- Later courts cite it for
- “liberal interpretation of a statute does not permit doing violence to the language in the statute.” · 3 citing courts
- Where it cites § 53.056
- “, Tex. Prop.Code § 53.056 (notice requirements for derivative claimant to original contractor or owner); § 53.057 (derivative claimant's notice for contractual retainage lien); § 53.024 (limitation on subcontractor's lien).”
- The case’s holding
- Work under a construction contract is complete, starting the thirty-day lien affidavit period, when that contract is terminated or abandoned, not when replacement contractors finish the project.
- Later courts cite it for
- “work must be defined in relation to a particular contract.” · 3 citing courts
- Where it cites § 53.056
- “Tex. PROP.Code Ann. § 53.056. But the ability to “trap” funds is extinguished if the “claim is otherwise paid or settled.”
- The case’s holding
- A subcontractor's settlement and release of its underlying claim against the general contractor extinguishes derivative trapping and retainage claims against the owner, and the owner is not liable.
- Later courts cite it for
- “the amount trapped under the trapping statute (as big as the claim is big) may be more than the required retainage under the retainage statute (a flat ten percent of contract price or value).” · 2 citing courts
- Where it cites § 53.056
- “Tex. PROp.Code Ann. §§ 53.056(b), .206(a).”
- Later courts cite it for
- “we are to interpret a contract in such a manner that none of its provisions will be rendered meaningless.” · 3 citing courts
- Where it cites § 53.056
- “Tex. Prop.Code Ann. § 53.056(b). The person claiming the lien must then file an affidavit with the county clerk not later than the fifteenth day of the fourth month after the day on which the indebtedness accrued.”
- Where it cites § 53.056
- “Tex. Prop. Code Ann. § 53.056 (b) (Vernon 1995).”
- Where it cites § 53.056
- “See TEX.PROP. CODE ANN. § 53.056(b) (Vernon 1984).”
- The case’s holding
- Attorney fees may include compensation for a legal assistant if the assistant performs work traditionally performed by an attorney.
- Later courts cite it for
- “if a legal assistant performs work that has traditionally been done by any attorney.” · 1 citing court
- Where it cites § 53.056
- “, TEX. PROP. CODE ANN. § 53.056(b) (West 2014) (providing, among other things, that any notice *646 must be submitted no later than 15th day of third month after claimant's labor or materials were furnished).”
- Where it cites § 53.056
- “See Tex. Prop.Code Ann. § 53.056 (requiring pre-hen notice to owner or general contractor).”
- Later courts cite it for
- “in general, courts that have addressed substantial-compliance issues have distinguished between mere technical defects, which can be excused, and those defects that are more substantive in nature and, if overlooked, would read a provision out of the statute or prejudice another party.” · 3 citing courts
- Where it cites § 53.056
- “2003); Tex. Prop.Code Ann. § 53.056 (Vernon 1997).”
- Where it cites § 53.056
- “Tex.Prop.Code Ann. § 53.056(b) (Vernons 1984).”
- Where it cites § 53.056
- “Appellee sued for the removal of the lien, based upon appellant’s alleged failure to give it notice of the unpaid debt as required by Tex.Prop.Code Ann. § 53.056 (Vernon 1985).”
- Where it cites § 53.056
- “This section provides that if the lien claim arises, as here, from a debt incurred by a subcontractor, the claimant must give-the original contractor 5 written notice of the unpaid balance not later than the fifteenth day of the second month following each month in which all or…”
- Where it cites § 53.056
- “TEX.PROP.CODE ANN. § 53.056. On September 11, 1985, the Schneiders received the appellant’s timely notice of claim stating that Kitchen Designers, Inc.”
- Later courts cite it for
- “the purpose of 53.055 is to ensure that the owner receives actual notice that an affidavit has been filed against the property so that he will be able to take steps to protect himself.” · 5 citing courts
- Where it cites § 53.056
- “This notice must inform the owner that if the bills remain unpaid, the owner may be personally liable and the owner’s property subjected to a lien unless the owner withholds payment from the contractor to pay the subcontractor’s bill or the bill is otherwise paid or settled.”
- Where it cites § 53.056
- “See Tex.Prop.Code § 53.056(b) (1984) (amended 1989).”
- Where it cites § 53.056
- “See Tex. PROP. Code, §§ 53.056(d), 53.081(a).”
- Where it cites § 53.056
- “1 Article 5453 is now codified in Tex.Prop.Code Ann. § 53.056 (Vernon 1984), and describes what steps are necessary for a subcontractor to perfect a statutory lien.”
- Where it cites § 53.056
- “Following repeated fruitless requests for payment, appellee followed Tex.Prop.Code Ann. § 53.056 (Vernon 1984 & Supp.”
Show all 40 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 4 cases in 1988. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
(a)3 cases
(b)12 cases
(c)4 cases
(d)4 cases
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: laws through the 89th Legislature (2025). Syfert holds no earlier or later version of this section.