Texas Codes homeSearch Texas
Tex. CodesProperty CodeTitle 5. Exempt Property and LiensSubtitle B. LiensChapter 53. Mechanic'S, Contractor'S, Or Materialman'S Lien

Tex. Prop. Code § 53.101 (2026)

Funds Required To Be Reserved

Edition and currency
laws through the 89th Legislature (2025). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 89th Legislature (2025) cited 1991–2025 34citing cases
At a glance

Courts have cited this section in 34 opinions since 1991, 3 of them in the last five years. The most litigated part is subsection (a) (3 cases).

Sec. 53.101. FUNDS REQUIRED TO BE RESERVED. (a) During the progress of work under an original contract for which a mechanic's lien may be claimed and for 30 days after the work under the contract is completed, the owner shall reserve:

(1) 10 percent of the contract price of the work to the owner; or

(2) 10 percent of the value of the work, measured by the proportion that the work done bears to the work to be done, using the contract price or, if there is no contract price, using the reasonable value of the completed work.

(b) In this section, "owner" includes the owner's agent, trustee, or receiver.

Acts 1983, 68th Leg., p. 3545, ch. 576, Sec. 1, eff. Jan. 1, 1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 15, eff. Sept. 1, 1989.

Amended by:

Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 18, eff. January 1, 2022.

The 20 cases that cite Tex. Prop. Code § 53.101 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENPage v. Structural Wood Components, Inc., 102 S.W.3d 720 (Tex. 2003).
cites § 53.101 8×cited by 25 cases
Where it cites § 53.101
“A subcontractor or other claimant who wants to make a claim on that retainage must properly give notice and file "an affidavit claiming a lien not later than the 30th day after the work is completed.”
The case’s holding
Work under a construction contract is complete, starting the thirty-day lien affidavit period, when that contract is terminated or abandoned, not when replacement contractors finish the project.
Later courts cite it for
“work must be defined in relation to a particular contract.” · 3 citing courts
cites § 53.101 4×cited by 43 cases
Where it cites § 53.101
“Tex. Prop.Code Ann. § 53.101. The subcontractors concede that Agape, as the owner of the project, would ordinarily be responsible for retaining funds in the construction account pursuant to the statute.”
The case’s holding
Freedom of contract is strongly favored by public policy (explaining that freedom of contract is strongly favored public policy).
Later courts cite it for
“to recognize a new common-law duty that has no existence in established law” · 6 citing courts
3
GREENGreen Int'l, Inc. v. Solis, 951 S.W.2d 384 (Tex. 1997).
cites § 53.101 2×cited by 859 cases
Where it cites § 53.101
“See TEX. PROP.CODE § 53.101. Thus, the Subcontracts contemplated that Solis would execute the waiver of lien releases before receiving one hundred percent of his compensation due.”
The case’s holding
A party must prevail on a cause of action and recover damages to be entitled to attorney's fees under section 38.001.
Later courts cite it for
“prevail on a cause of action for which attorney's fees are recoverable.” · 86 citing courts
cites § 53.101 1×cited by 111 cases
Where it cites § 53.101
“Tex. Prop.Code § 53.101. This retainage secures the payment of any contractor or subcontractor who may assert a lien on the property in the event that the general fails to pay them.”
The case’s holding
A contract provision is construed as a covenant rather than a condition precedent if it lacks conditional language and another reasonable interpretation is possible.
Later courts cite it for
“a covenant, as distinguished from a condition precedent, is an agreement to act or refrain from acting in a certain way.” · 11 citing courts
5
GREENBond v. Kagan-Edelman Enter., 985 S.W.2d 253 (Tex. App.—Houston [1st Dist.] 1999).
cites § 53.101 5×subsections: (a)(1) 2×cited by 9 cases
Where it cites § 53.101
“Tex. Prop. Code § 53.101. The retained funds secure the payment of those who furnish material and labor for any contractor or subcontractor in the performance of the work.”
6
GREENSan Antonio Credit Union v. O'CONNOR, 115 S.W.3d 82 (Tex. App.—San Antonio 2003).
cites § 53.101 1×cited by 62 cases
Where it cites § 53.101
“Tex. PROP.Code Ann. § 53.101 (Vernon 1995).”
The case’s holding
Acting in concert to withhold funds does not establish the specific intent required to prove a civil conspiracy claim.
Later courts cite it for
“a judicial proceeding would only be 'proposed' when the investigating body found enough information either to present that information to a grand jury or to file a misdemeanor complaint.” · 2 citing courts
7
GREENPage v. Marton Roofing, Inc., 102 S.W.3d 750 (Tex. App.—Houston [1st Dist.] 2002).
cites § 53.101 3×cited by 5 cases
Where it cites § 53.101
“Tex. Prop.Code Ann. §§ 53.101, 53.103 (Vernon 1995) (emphasis added).”
8
GREENPage v. Marton Roofing, Inc., 102 S.W.3d 733 (Tex. 2003).
cites § 53.101 2×cited by 8 cases
Where it cites § 53.101
“; Tex. Prop.Code § 53.101. Here, Marton Roofing filed its affidavit two months after the original contract was terminated, and consequently failed to perfect a lien on the statutory retainage.”
9
GREENHadnot v. Wenco Distributors, 961 S.W.2d 232 (Tex. App.—Houston [1st Dist.] 1997).
cites § 53.101 2×cited by 16 cases
Where it cites § 53.101
“1983); see Tex. PROP.Code Ann. § 53.101 et seq (Vernon 1995); Tex.”
10
GREENStolz v. Honeycutt, 42 S.W.3d 305 (Tex. App.—Houston [14th Dist.] 2001).
cites § 53.101 1×subsections: (a)cited by 23 cases
Where it cites § 53.101
“Tex. Prop.Code Ann. § 53.101(a). A claimant may then secure a lien on the retained funds if he provides the owner with proper notice under the statute and files an affidavit claiming a lien no later than the 30th day after the work was completed.”
The case’s holding
A subcontractor's settlement and release of its underlying claim against the general contractor extinguishes derivative trapping and retainage claims against the owner, and the owner is not liable.
Later courts cite it for
“the amount trapped under the trapping statute (as big as the claim is big) may be more than the required retainage under the retainage statute (a flat ten percent of contract price or value).” · 2 citing courts
11
GREENAiken v. State, 36 S.W.3d 131 (Tex. App.—Austin 2000).
cites § 53.101 1×cited by 41 cases
Where it cites § 53.101
“The Property Code requires an owner, under an original contract for which a mechanic’s lien may be claimed, to retain ten percent of the contract price of the work or ten percent of the value of the work during the progress of the work and for thirty days after the work is…”
The case’s holding
Retainage funds held under the Property Code belong to the contractor subject to subcontractor claims, so nonpayment of those claims does not create substantial risk of loss to owners.
12
GREENRonk v. State, 250 S.W.3d 467 (Tex. App.—Waco 2008).
cites § 53.101 2×cited by 5 cases
Where it cites § 53.101
“See TEX. PROP.CODE ANN. § 53.101 (Vernon 2007) (requiring retainage of funds under construction contract to pay subcontractors).”
13
GREENMorrell Masonry Supply, Inc. v. Lupe's Shenandoah Reserve, LLC, 363 S.W.3d 901 (Tex. App.—Beaumont 2012).
cites § 53.101 1×cited by 8 cases
Where it cites § 53.101
“See Tex. Prop.Code Ann. § 53.101 (West 2007).”
14
GREENDorsett Bros. Concrete Supply v. Safeco Title Ins. Co., 880 S.W.2d 417 (Tex. App.—Houston [14th Dist.] 1993).
cites § 53.101 1×cited by 15 cases
Where it cites § 53.101
“See Tex. Prop.Code Ann. § 53.101 (Vernon Supp.”
15
GREENRough Creek Lodge Operating, L.P. v. Double K Homes, Inc., 278 S.W.3d 501 (Tex. App.—Eastland 2009).
cites § 53.101 1×cited by 7 cases
Where it cites § 53.101
“See Tex. Prop.Code Ann. § 53.101 (Vernon 2007).”
16
GREENTDIndustries, Inc. v. NCNB Texas Nat'l Bank, 837 S.W.2d 270 (Tex. App.—Eastland 1992).
cites § 53.101 1×cited by 11 cases
Where it cites § 53.101
“The controlling issue in this case is the date the work was “completed” on a construction contract under TEX.PROP.CODE ANN. § 53.101 (Vernon Supp.”
17
GREENJewelry Mfr.'s Exch., Inc. v. Tafoya, 374 S.W.3d 639 (Tex. App.—Dallas 2012).
cites § 53.101 2×cited by 2 cases
Where it cites § 53.101
“Tex. Prop.Code Ann. § 53.101 (West 2007).”
18
GREENMorrell Masonry Supply, Inc. v. Loeb, 349 S.W.3d 664 (Tex. App.—Houston [14th Dist.] 2011).
cites § 53.101 1×cited by 4 cases
Where it cites § 53.101
“*671 III In its third issue, Morrell argues the trial court erred in concluding Morrell never gave timely notice nor perfected a claim to the statutory ten-percent retain-age fund the Loebs were required to maintain.”
19
GREENEmployers Mut. Cas. Co. v. Walker, 811 S.W.2d 270 (Tex. App. 1991).
cites § 53.101 1×cited by 3 cases
Where it cites § 53.101
“Employers’ inaccurately characterizes appellee’s contract as a retainage contract such as those covered by Tex.Prop.Code Ann. § 53.101 -105 (Vernon 1984 & Supp.”
20
NO FLAGJP Morgan Chase Bank, N.A. v. Texas Contract Carpet, Inc., No. 03-05-00629-CV (Tex. App.—Austin Dec. 11, 2009).
cites § 53.101 5×cited by 0 cases
Where it cites § 53.101
“See Tex. Prop. Code Ann. § 53.101 (West 2007) (imposing duty to retain funds on owner of project or owner's agent, trustee, or receiver).”

Show all 34 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199120082025

One bar per year. Tallest: 5 cases in 2009. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Tex. App.30Tex.4
By subsection
(a)3 cases
Stolz v. Honeycutt, 42 S.W.3d 305 (Tex. App.—Houston [14th Dist.] 2001).“Tex. Prop.Code Ann. § 53.101(a). A claimant may then secure a lien on the retained funds if he provides the owner with proper notice under the statute and files an affidavit claiming a lien no later than the 30th day after the work was completed.”
Astra Ventures, LLC v. Serv. Steel Warehouse Co., L.P., No. 01-23-00825-CV (Tex. App.—Houston [1st Dist.] Aug. 28, 2025).
Ajas, Inc. v. Idaho Pac. Lumber Co., No. 13-12-00763-CV (Tex. App.—Corpus Christi May 14, 2015).
(a)(1)1 case
Bond v. Kagan-Edelman Enter., 985 S.W.2d 253 (Tex. App.—Houston [1st Dist.] 1999).“Tex. Prop. Code § 53.101. The retained funds secure the payment of those who furnish material and labor for any contractor or subcontractor in the performance of the work.”

Show all 34 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 89th Legislature (2025). Syfert holds no earlier or later version of this section.

Texas Codes Home  |  Search Texas  |  Search cases for this section  |  syfert.com