16 U.S.C. § 811 (2026)
Operation of navigation facilities; rules and regulations; penalties
Edition and currency
Other sources
Courts have cited this section in 13 opinions since 1939, 4 of them in the last five years.
The Commission shall require the construction, maintenance, and operation by a licensee at its own expense of such lights and signals as may be directed by the Secretary of the Department in which the Coast Guard is operating, and such fishways as may be prescribed by the Secretary of the Interior or the Secretary of Commerce, as appropriate. The license applicant and any party to the proceeding shall be entitled to a determination on the record, after opportunity for an agency trial-type hearing of no more than 90 days, on any disputed issues of material fact with respect to such fishways. All disputed issues of material fact raised by any party shall be determined in a single trial-type hearing to be conducted by the relevant resource agency in accordance with the regulations promulgated under this subsection 1
- Where it cites § 811
- “at 661 (quoting 16 U.S.C. § 811 ). In doing so, FERC declined to consider Bangor’s arguments concerning the need for the fishway, concluding that under the statute it had no choice but to require Bangor to construct it.”
- The case’s holding
- An agency required by statute to implement another department's recommendations without change is not obligated to respond to public comments regarding those specific recommendations.
- Later courts cite it for
- “an agency must ... demonstrate the rationality of its decisionmaking process by responding to those comments that are relevant and significant.” · 7 citing courts
- Where it cites § 811
- “825f (1964), for willful failure to testify or produce documents; Section 314(a), 16 U.S.C. § 825m (1964), for willful violation of the Act, rules, regulations, or orders; Section 315(a), 16 U.”
- The case’s holding
- An agency possesses implied authority to establish retroactive effective dates for licenses when a project is maintained without a license in violation of applicable law.
- Later courts cite it for
- “the breadth of agency discretion is, if anything, at zenith when the action assailed relates primarily not to the issue of ascertaining whether conduct violates the statute, or regulations, but rather to the fashioning of policies, remedies and sanctions.” · 13 citing courts
- Where it cites § 811
- “" Section 18, 16 U.S.C.A. § 811 , provides for the operation of navigation facilities constructed in connection with licensed dams.”
- Where it cites § 811
- “In the respective licenses issued in the two eases the Federal Energy Regulatory Commission (the Commission or FERC) included reopener clauses requiring the licensees to construct, operate and maintain such fishways as might in the future be prescribed by the Secretary of the…”
- Later courts cite it for
- “congress has delegated to the secretary of the interior the authority to make a determination when and if a section 18 fishway may become necessary.” · 3 citing courts
- Where it cites § 811
- “” 16 U.S.C. § 811 . Conspicuously absent from this provision is a qualifying clause, such as the one in FPA subsection 10(j)(2), which expressly enables the Commission to reject a recommendation submitted under color of section 10(j).”
- The case’s holding
- The Commission may define the no-action alternative as continued operation under existing licenses and use existing environmental conditions as the baseline for environmental impact analysis.
- Later courts cite it for
- “we are mindful that this court steadfastly abides by the principle that 'legislative history-no matter how clear-can't override statutory text.” · 5 citing courts
- Where it cites § 811
- “845 , as amended, 16 U.S.C. § 811 (1958). 25 . As added, 49 Stat.”
- Later courts cite it for
- “it is not a taking for the government to withhold a benefit it is not contractually or constitutionally obliged to confer, nor is it a taking for the government to impose financial obligations upon the recipient of a benefit if, as here, the benefit may be declined.” · 2 citing courts
- Summary
- No passage or summary on file for this case yet.
- Where it cites § 811
- “” 16 U.S.C. § 811 . Conspicuously absent from this provision is a qualifying clause, such as the one in FPA subsection 10(j)(2), which expressly enables the Commission to reject a recommendation submitted under color of section 10(j).”
- Where it cites § 811
- “In it, FERC explained that neither the Secretary of Commerce nor the Secretary of the Interior had prescribed a fishway under 16 U.S.C. § 811 . 4 It also explained that both the Department of Commerce and the Department of the Interior were parties to the Settlement Agreement in…”
- The case’s holding
- A state-law challenge to a federally licensed dam's operation raises a substantial federal question permitting removal, since federal law comprehensively governs FERC-licensed projects and review lies exclusively in the courts of appeals.
- Later courts cite it for
- “the federal removal statute provides that 'any civil action brought in a state court of which the district courts of the united states have original jurisdiction . . . may be removed by the defendant . . . to the district court of the united states.” · 4 citing courts
- Where it cites § 811
- “11 Neither the Department of the Interior nor the Department of Commerce, as authorized 12 under 16 U.S.C. §811 , prescribed as a condition of relicensing the construction of a fishway at 13 Gorge Dam (or any of the other two dams in the Project) to enable the passage of…”
- Where it cites § 811
- “” ( 16 U.S.C. § 811 .) Therefore, if FERC has licensing authority over a dam, the USFWS and NMFS have the ability to require fish passage measures as a condition of licensure.”
- Where it cites § 811
- “The United States Fish and Wildlife Service (FWS), an arm of the Department of Interior, notified FERC that it did not approve of the Bangor plan and that pursuant to § 18 of the Federal Power Act, 16 U.S.C. § 811 (1985), it would require Bangor to construct permanent upstream…”
- The case’s holding
- An agency is not required to judge the procedural or substantive validity of another agency's position, but any resulting requirement must be supported by substantial evidence in the record.
- Later courts cite it for
- “it may be dicta, but supreme court dicta tends to have somewhat greater force-particularly when expressed so unequivocally.” · 5 citing courts
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per 2 years. Tallest: 2 cases in 1998–1999. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Amendment years (notes): 2005, 1956, 1935
Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.