Skip to main content
U.S. CodeTitle 16Chapter 12— Federal Regulation and Development of PowerSubchapter II— Regulation of Electric Utility Companies Engaged in Interstate Commerce

16 U.S.C. § 824a (2026)

Interconnection and coordination of facilities; emergencies; transmission to foreign countries

Edition and currency
U.S. Code current through Pub. L. 119-102 (OLRC release point). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTU.S. Code current through Pub. L. 119-102 (OLRC release point) cited 1950–2026 115citing cases
At a glance

Courts have cited this section in 115 opinions since 1950, 13 of them in the last five years. The most litigated part is subsection (a) (27 cases).

(a) Regional districts; establishment; notice to State commissions

For the purpose of assuring an abundant supply of electric energy throughout the United States with the greatest possible economy and with regard to the proper utilization and conservation of natural resources, the Commission is empowered and directed to divide the country into regional districts for the voluntary interconnection and coordination of facilities for the generation, transmission, and sale of electric energy, and it may at any time thereafter, upon its own motion or upon application, make such modifications thereof as in its judgment will promote the public interest. Each such district shall embrace an area which, in the judgment of the Commission, can economically be served by such interconnection and coordinated electric facilities. It shall be the duty of the Commission to promote and encourage such interconnection and coordination within each such district and between such districts. Before establishing any such district and fixing or modifying the boundaries thereof the Commission shall give notice to the State commission of each State situated wholly or in part within such district, and shall afford each such State commission reasonable opportunity to present its views and recommendations, and shall receive and consider such views and recommendations.

(b) Sale or exchange of energy; establishing physical connections

Whenever the Commission, upon application of any State commission or of any person engaged in the transmission or sale of electric energy, and after notice to each State commission and public utility affected and after opportunity for hearing, finds such action necessary or appropriate in the public interest it may by order direct a public utility (if the Commission finds that no undue burden will be placed upon such public utility thereby) to establish physical connection of its transmission facilities with the facilities of one or more other persons engaged in the transmission or sale of electric energy, to sell energy to or exchange energy with such persons: Provided, That the Commission shall have no authority to compel the enlargement of generating facilities for such purposes, nor to compel such public utility to sell or exchange energy when to do so would impair its ability to render adequate service to its customers. The Commission may prescribe the terms and conditions of the arrangement to be made between the persons affected by any such order, including the apportionment of cost between them and the compensation or reimbursement reasonably due to any of them.

(c) Temporary connection and exchange of facilities during emergency(1) During the continuance of any war in which the United States is engaged, or whenever the Commission determines that an emergency exists by reason of a sudden increase in the demand for electric energy, or a shortage of electric energy or of facilities for the generation or transmission of electric energy, or of fuel or water for generating facilities, or other causes, the Commission shall have authority, either upon its own motion or upon complaint, with or without notice, hearing, or report, to require by order such temporary connections of facilities and such generation, delivery, interchange, or transmission of electric energy as in its judgment will best meet the emergency and serve the public interest. If the parties affected by such order fail to agree upon the terms of any arrangement between them in carrying out such order, the Commission, after hearing held either before or after such order takes effect, may prescribe by supplemental order such terms as it finds to be just and reasonable, including the compensation or reimbursement which should be paid to or by any such party.(2) With respect to an order issued under this subsection that may result in a conflict with a requirement of any Federal, State, or local environmental law or regulation, the Commission shall ensure that such order requires generation, delivery, interchange, or transmission of electric energy only during hours necessary to meet the emergency and serve the public interest, and, to the maximum extent practicable, is consistent with any applicable Federal, State, or local environmental law or regulation and minimizes any adverse environmental impacts.(3) To the extent any omission or action taken by a party, that is necessary to comply with an order issued under this subsection, including any omission or action taken to voluntarily comply with such order, results in noncompliance with, or causes such party to not comply with, any Federal, State, or local environmental law or regulation, such omission or action shall not be considered a violation of such environmental law or regulation, or subject such party to any requirement, civil or criminal liability, or a citizen suit under such environmental law or regulation.(4)(A) An order issued under this subsection that may result in a conflict with a requirement of any Federal, State, or local environmental law or regulation shall expire not later than 90 days after it is issued. The Commission may renew or reissue such order pursuant to paragraphs (1) and (2) for subsequent periods, not to exceed 90 days for each period, as the Commission determines necessary to meet the emergency and serve the public interest.(B) In renewing or reissuing an order under subparagraph (A), the Commission shall consult with the primary Federal agency with expertise in the environmental interest protected by such law or regulation, and shall include in any such renewed or reissued order such conditions as such Federal agency determines necessary to minimize any adverse environmental impacts to the extent practicable. The conditions, if any, submitted by such Federal agency shall be made available to the public. The Commission may exclude such a condition from the renewed or reissued order if it determines that such condition would prevent the order from adequately addressing the emergency necessitating such order and provides in the order, or otherwise makes publicly available, an explanation of such determination.(5) If an order issued under this subsection is subsequently stayed, modified, or set aside by a court pursuant to section 825l of this title or any other provision of law, any omission or action previously taken by a party that was necessary to comply with the order while the order was in effect, including any omission or action taken to voluntarily comply with the order, shall remain subject to paragraph (3).(d) Temporary connection during emergency by persons without jurisdiction of Commission

During the continuance of any emergency requiring immediate action, any person or municipality engaged in the transmission or sale of electric energy and not otherwise subject to the jurisdiction of the Commission may make such temporary connections with any public utility subject to the jurisdiction of the Commission or may construct such temporary facilities for the transmission of electric energy in interstate commerce as may be necessary or appropriate to meet such emergency, and shall not become subject to the jurisdiction of the Commission by reason of such temporary connection or temporary construction: Provided, That such temporary connection shall be discontinued or such temporary construction removed or otherwise disposed of upon the termination of such emergency: Provided further, That upon approval of the Commission permanent connections for emergency use only may be made hereunder.

(e) Transmission of electric energy to foreign country

After six months from August 26, 1935, no person shall transmit any electric energy from the United States to a foreign country without first having secured an order of the Commission authorizing it to do so. The Commission shall issue such order upon application unless, after opportunity for hearing, it finds that the proposed transmission would impair the sufficiency of electric supply within the United States or would impede or tend to impede the coordination in the public interest of facilities subject to the jurisdiction of the Commission. The Commission may by its order grant such application in whole or in part, with such modifications and upon such terms and conditions as the Commission may find necessary or appropriate, and may from time to time, after opportunity for hearing and for good cause shown, make such supplemental orders in the premises as it may find necessary or appropriate.

(f) Transmission or sale at wholesale of electric energy; regulation

The ownership or operation of facilities for the transmission or sale at wholesale of electric energy which is (a) generated within a State and transmitted from the State across an international boundary and not thereafter transmitted into any other State, or (b) generated in a foreign country and transmitted across an international boundary into a State and not thereafter transmitted into any other State, shall not make a person a public utility subject to regulation as such under other provisions of this subchapter. The State within which any such facilities are located may regulate any such transaction insofar as such State regulation does not conflict with the exercise of the Commission’s powers under or relating to subsection (e).

(g) Continuance of serviceIn order to insure continuity of service to customers of public utilities, the Commission shall require, by rule, each public utility to—(1) report promptly to the Commission and any appropriate State regulatory authorities any anticipated shortage of electric energy or capacity which would affect such utility’s capability of serving its wholesale customers,(2) submit to the Commission, and to any appropriate State regulatory authority, and periodically revise, contingency plans respecting—(A) shortages of electric energy or capacity, and(B) circumstances which may result in such shortages, and(3) accommodate any such shortages or circumstances in a manner which shall—(A) give due consideration to the public health, safety, and welfare, and(B) provide that all persons served directly or indirectly by such public utility will be treated, without undue prejudice or disadvantage.(June 10, 1920, ch. 285, pt. II, § 202, as added Aug. 26, 1935, ch. 687, title II, § 213, 49 Stat. 848; amended Aug. 7, 1953, ch. 343, 67 Stat. 461; Pub. L. 95–617, title II, § 206(a), Nov. 9, 1978, 92 Stat. 3141; Pub. L. 114–94, div. F, § 61002, Dec. 4, 2015, 129 Stat. 1772.)Editorial NotesAmendments

2015—Subsec. (c). Pub. L. 114–94, § 61002(a), designated existing provisions as par. (1) and added pars. (2) to (5).

Subsec. (d). Pub. L. 114–94, § 61002(b), inserted “or municipality” before “engaged in the transmission or sale of electric energy”.

1978—Subsec. (g). Pub. L. 95–617 added subsec. (g).

1953—Subsec. (f). Act Aug. 7, 1953, added subsec. (f).

Statutory Notes and Related SubsidiariesEffective Date of 1978 Amendment

Pub. L. 95–617, title II, § 206(b), Nov. 9, 1978, 92 Stat. 3142, provided that: “The amendment made by subsection (a) [adding subsec. (g) of this section] shall not affect any proceeding of the Commission [Federal Energy Regulatory Commission] pending on the date of the enactment of this Act [Nov. 9, 1978] or any case pending on such date respecting a proceeding of the Commission.”

Executive DocumentsDelegation of Functions

Functions of President respecting certain facilities constructed and maintained on United States borders delegated to Secretary of State, see Ex. Ord. No. 11423, Aug. 16, 1968. 33 F.R. 11741, set out as a note under section 301 of Title 3, The President.

Performance of Functions Respecting Electric Power and Natural Gas Facilities Located on United States Borders

For provisions relating to performance of functions by Secretary of Energy respecting electric power and natural gas facilities located on United States borders, see Ex. Ord. No. 10485, Sept. 8, 1953, 18 F.R. 5397, as amended by Ex. Ord. No. 12038, Feb. 3, 1978, 43 F.R. 4957, set out as a note under section 717b of Title 15, Commerce and Trade.

The 20 cases that cite 16 U.S.C. § 824a most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENOtter Tail Power Co. v. United States, 410 U.S. 366 (1973).
cites § 824a 16×subsections: (b) 2× (c)cited by 579 cases
Where it cites § 824a
“848 , 16 U. S. C. § 824a (b), to require Otter Tail to interconnect with the town and sell it power at wholesale.”
The case’s holding
A regulated utility violates antitrust laws by refusing to sell electricity at wholesale or denying competitors use of its distribution lines to foreclose competition.
Later courts cite it for
“when these relationships are governed in the first instance by business judgment and not regulatory coercion, courts must be hesitant to conclude that congress intended to override the fundamental national policies embodied in the antitrust laws.” · 18 citing courts
cites § 824a 3×subsections: (b) 3×cited by 390 cases
Where it cites § 824a
“16 U.S.C. § 824a(b); .18 C.F.R. pt. 32. In addition, FERC may not compel the enlargement of generating facilities for such purposes, and it may not compel a public utility to sell or exchange energy when to do so would impair the utility’s ability to render adequate service to…”
The case’s holding
A supplier cannot establish antitrust injury by alleging that a purchaser's refusal to buy products prevents competition in a market where the supplier is contractually or legally prohibited from competing.
Later courts cite it for
“unsupported conclusions and unwarranted inferences,” · 31 citing courts
cites § 824a 3×subsections: (g) 2× (c)cited by 58 cases
Where it cites § 824a
“, 16 U.S.C. § 824a(c) (permitting FERC to require from public utilities, whenever it determines an emergency exists, “such generation, delivery, interchange, or transmission of electric energy as in its judgment will best meet the emergency and serve the public interest”); 16 U.”
The case’s holding
A bankruptcy court may authorize the rejection of an executory power contract because such rejection only has an indirect effect upon the filed rate.
Later courts cite it for
“would only have an indirect effect upon the filed rate,” · 2 citing courts
cites § 824a 4×cited by 166 cases
Where it cites § 824a
“It is said that allegations of anticompetitive conduct properly may be raised and fully considered in other proceedings related to interconnections under § 202 of the Act, 16 U. S. C. § 824a, to dispositions and mergers under § 203, 16 U.”
The case’s holding
The Federal Power Commission interprets the public interest standard under the Federal Power Act (construing public interest standard under Federal Power Act).
Later courts cite it for
“to provide effective federal regulation of the expanding business of transmitting and selling electric power in interstate commerce.” · 9 citing courts
cites § 824a 4×cited by 163 cases
Where it cites § 824a
“Unless it is done voluntarily, as was true here, the Commission by virtue of § 202 (b) of the Federal Power Act can act only [1] "upon application of any State commission or of any person engaged in the transmission or sale of electric energy.”
The case’s holding
Courts must defer to an administrative agency's factual findings on technical or scientific matters if those findings are supported by substantial evidence.
Later courts cite it for
“particularly when we consider a purely factual question within the area of competence of an administrative agency created by congress, and when resolution of that question depends on 'engineering and scientific' considerations, we recognize the relevant agency's technical expertise and experience, and defer to its analysis unless it is without substantial basis in fact.” · 8 citing courts
cites § 824a 2×subsections: (a) 2×cited by 69 cases
Where it cites § 824a
“” FPA § 202(a), 16 U.S.C. § 824a(a). Such public utilities, in turn, were required to file new rates for Commission approval, and Congress directed that “[a]ll rates and charges made, demanded, or received by any public utility for or in connection with the [jurisdictional]…”
The case’s holding
A regulatory order based on market competition theory is reasonable if it determines that rights of first refusal would lead to unjust or unreasonable practices (Order 1000).
Later courts cite it for
“opportunities for nonincumbents, such developers must still comply with state law.” · 2 citing courts
cites § 824a 1×cited by 236 cases
Where it cites § 824a
“742, 751 (1982); see 16 U. S. C. § 824a—3(a). Over a decade later, Congress enacted the Energy Policy Act of 1992 (EPAct), 106 Stat.”
The case’s holding
The Federal Power Act grants an agency jurisdiction over interstate electric energy transmission regardless of whether the transmission is associated with a wholesale or retail transaction.
Later courts cite it for
“the sale of electric energy at wholesale in interstate commerce.” · 13 citing courts
8
GREENYounger v. Jensen, 26 Cal. 3d 397 (1980).
cites § 824a 2×subsections: (c) 2×cited by 82 cases
Where it cites § 824a
“1022 ] (FPC authority to order electric utility interconnections (16 U.S.C. § 824a(c); cf. Natural Gas Act, 15 U.”
The case’s holding
Federal antitrust enforcement overlaps with state antitrust laws that prohibit substantially the same conduct.
Later courts cite it for
“a federal judgment has the same effect in the courts of this state as it would have in a 28 federal court.” · 6 citing courts
9
GREENCity of Cleveland v. Fed. Power Comm'n, 525 F.2d 845 (D.C. Cir. 1976).
cites § 824a 2×subsections: (b) (c)cited by 77 cases
Where it cites § 824a
“See Federal Power Act § 202(b), 16 U.S.C. § 824a(b) (1970). 17 . See Federal Power Act § 202(c), 16 U.”
The case’s holding
The Commission must adjust a filed rate if it deviates from the actual agreement of the parties regardless of whether the thirty-day filing period has expired.
Later courts cite it for
“preservation of the agency's primary jurisdiction over reasonableness of rates and the need to insure that regulated companies charge only those rates of which the agency has been made cognizant.” · 9 citing courts
10
GREENAtl. City Elec. Co. v. Fed. Energy Regulatory Comm'n, 295 F.3d 1 (D.C. Cir. 2002).
cites § 824a 1×subsections: (a)cited by 106 cases
Where it cites § 824a
“See 16 U.S.C. § 824a(a). Section 202 provides that “the Commission is empowered and directed to divide the country into regional districts for the voluntary interconnection and coordination of facilities for the generation, transmission, and sale of electric energy.”
The case’s holding
An agency lacks authority to act in the absence of specific statutory authorization and cannot compel utilities to cede their statutory rate-filing rights.
Later courts cite it for
“assuming that there was no reason to question what transpired at the contract formation stage” · 3 citing courts
11
GREENDuke Power Co. v. Fed. Power Comm'n, 401 F.2d 930 (D.C. Cir. 1968).
cites § 824a 6×subsections: (a)cited by 17 cases
Where it cites § 824a
“Section 203 was likewise added with full awareness that this was not a provision needed to close a constitutional gap, and that the states had jurisdiction to accomplish this regulation. Hearings on H.R. 5423 Before the House Committee on Interstate and Foreign Commerce.”
Later courts cite it for
“the act's major emphasis is upon federal regulation of those aspects of the industry which- - for reasons either legal or practical - are beyond the pale of effective state supervision.” · 3 citing courts
cites § 824a 1×subsections: (b)cited by 227 cases
Where it cites § 824a
“Prior to their enactment, the Commission’s authority to order interconnections was limited, under § 202(b) of the FPA, 16 U. S. C. § 824a(b), to utilities over which it had regulatory jurisdiction and, except in emergencies, to situations in which a “person engaged in the .”
The case’s holding
A court will uphold an agency decision even if it is not the only reasonable outcome (explaining that the agency's decision need not be the only reasonable one).
Later courts cite it for
“a qualifying facility and a utility may negotiate a contract setting a price that is lower than a full avoided cost rate.” · 3 citing courts
13
GREENLSP Transmission Holdings, LLC v. Katie Sieben, 954 F.3d 1018 (8th Cir. 2020).
cites § 824a 1×subsections: (a)cited by 22 cases
Where it cites § 824a
“(quoting 16 U.S.C. § 824a(a)). “Regionally, FERC-approved nongovernmental agencies, independent system operators (‘ISO’s), oversee the operation and expansion of electric transmission grids.”
The case’s holding
A state law that does not discriminate against interstate commerce and whose burdens on commerce are not clearly excessive relative to local benefits does not violate the dormant Commerce Clause.
Later courts cite it for
“preference is for electric transmission owners who have existing facilities, and its law applies evenhandedly to all entities, regardless of whether they are minnesota-based entities or based elsewhere.” · 3 citing courts
14
GREENResource Tech. Corp. v. Illinois Com. Comm'n, 822 N.E.2d 50 (Ill. App. Ct. 1st Dist. 2004).
cites § 824a 3×cited by 8 cases
Where it cites § 824a
“1(b) (West 2000)), is preempted by the Public Utility Regulatory Policies Act of 1978 (PURPA) (16 U.S.C. § 824a—3 (2000)); (2) a facility’s status as a QSWEF under state law is automatically established when the facility files a Federal Energy Regulatory Commission (FERC)…”
Later courts cite it for
“so dominant that it displaces state regulation on the same subject” · 2 citing courts
cites § 824a 1×cited by 1,293 cases
Where it cites § 824a
“§§ 221 (a), 222 (c) (1) (1952); Federal Power Act, 16 U. S. C. § 824a (b) (1952); Interstate Commerce Act, 49 U.”
The case’s holding
Monopoly power is the power to control prices or exclude competition, and the relevant product market includes commodities reasonably interchangeable by consumers for the same purposes.
Later courts cite it for
“the power to control prices or exclude competition.” · 139 citing courts
16
GREENPower Resource Grp., Inc. v. Pub. Util. Comm'n, 422 F.3d 231 (5th Cir. 2005).
cites § 824a 2×cited by 12 cases
Where it cites § 824a
“PRG then petitioned FERC pursuant to 16 U.S.C. § 824a~3(h)(2)(B), requesting that FERC undertake an enforcement action against the PUC for its failure to implement PURPA’s regulatory scheme.”
The case’s holding
States possess broad discretion to determine the specific parameters for when a legally enforceable obligation arises under federal regulations.
Later courts cite it for
“a legally enforceable obligation arises only when a qualified facility can deliver power within 90 days.” · 1 citing court
17
GREENNextEra v. Lake, 48 F.4th 306 (5th Cir. 2022).
cites § 824a 1×subsections: (a)cited by 15 cases
Where it cites § 824a
“; see also 16 U.S.C. § 824a(a) (“direct[ing] [FERC] to divide the county into regional districts for the voluntary interconnection and coordination of facilities for the .”
The case’s holding
A dismissal of a dormant commerce clause claim is reversed when the underlying legal sufficiency is established (reversing dismissal of dormant commerce clause claim).
Later courts cite it for
“limiting competition based on the existence or extent of a business's local foothold,” · 8 citing courts
18
GREENMid-Texas Commc'ns Sys., Inc. v. Am. Tel. & Tel. Co., 615 F.2d 1372 (5th Cir. 1980).
cites § 824a 1×subsections: (b)cited by 109 cases
Where it cites § 824a
“” 16 U.S.C. § 824a(b). The Supreme Court rejected the argument on the ground that the statutory provision was designed to foster voluntary interconnection.”
The case’s holding
Federal and state regulations must be considered when analyzing monopoly power and the reasonableness of a refusal to deal in antitrust litigation.
Later courts cite it for
“antitrust laws are not so inflexible as to deny consideration of governmental regulation.” · 2 citing courts
19
GREENExelon Wind 1, L.L.C. v. Donna Nelson, 766 F.3d 380 (5th Cir. 2014).
cites § 824a 1×cited by 37 cases
Where it cites § 824a
“” 16 U.S.C. § 824a- 3(a). The statute did not do any more to describe the regulatory scheme that 2 As one scholar recently observed, “State implementation of federal law is commonplace, but has been largely ignored by the interpretive doctrines of legislation and administrative…”
The case’s holding
An agency is not entitled to deference when it offers an interpretation of a regulation that is unambiguously foreclosed by the regulatory text.
Later courts cite it for
“an agency is not entitled to deference when it offers up an interpretation of the regulation that we have already said to be unambiguously foreclosed by the regulatory text.” · 2 citing courts
20
GREENNaacp v. FPC, 425 U.S. 662 (1976).
cites § 824a 1×cited by 98 cases
Where it cites § 824a
“[5] 16 U. S. C. § 824a (a) (The purpose of the Power Act is to "assur[e] an abundant supply of electric energy throughout the United States with the greatest possible economy"); Pennsylvania Power Co.”
The case’s holding
A regulatory commission has the authority to promulgate regulations concerning employment discrimination by its regulatees and to exclude costs resulting from discriminatory practices from rates.
Later courts cite it for
“take meaning from the purposes of the regulatory legislation.” · 10 citing courts

Show all 115 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
195019882026

One bar per 2 years. Tallest: 8 cases in 2014–2015. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.C. Cir.295th Cir.10SCOTUS92d Cir.79th Cir.53rd Cir.48th Cir.41st Cir.3

The 8 courts with the most citing cases, of 43 courts in all.

By subsection
(a)27 cases
South Carolina Pub. Serv. Auth. v. Fed. Energy Regulatory Comm'n, 762 F.3d 41 (D.C. Cir. 2014).“” FPA § 202(a), 16 U.S.C. § 824a(a). Such public utilities, in turn, were required to file new rates for Commission approval, and Congress directed that “[a]ll rates and charges made, demanded, or received by any public utility for or in connection with the [jurisdictional]…”
Atl. City Elec. Co. v. Fed. Energy Regulatory Comm'n, 295 F.3d 1 (D.C. Cir. 2002).“See 16 U.S.C. § 824a(a). Section 202 provides that “the Commission is empowered and directed to divide the country into regional districts for the voluntary interconnection and coordination of facilities for the generation, transmission, and sale of electric energy.”
LSP Transmission Holdings, LLC v. Katie Sieben, 954 F.3d 1018 (8th Cir. 2020).“(quoting 16 U.S.C. § 824a(a)). “Regionally, FERC-approved nongovernmental agencies, independent system operators (‘ISO’s), oversee the operation and expansion of electric transmission grids.”
NextEra v. Lake, 48 F.4th 306 (5th Cir. 2022).“; see also 16 U.S.C. § 824a(a) (“direct[ing] [FERC] to divide the county into regional districts for the voluntary interconnection and coordination of facilities for the .”
LSP Transmission Holdings, LLC v. Lange, 329 F. Supp. 3d 695 (D. Me. 2017).
Showing the top 5 of 27. More in the list view →
(b)21 cases
Schuylkill Energy Resources, Inc. v. Pennsylvania Power & Light Co., 113 F.3d 405 (3d Cir. 1997).“16 U.S.C. § 824a(b); .18 C.F.R. pt. 32. In addition, FERC may not compel the enlargement of generating facilities for such purposes, and it may not compel a public utility to sell or exchange energy when to do so would impair the utility’s ability to render adequate service to…”
Otter Tail Power Co. v. United States, 410 U.S. 366 (1973).“848 , 16 U. S. C. § 824a (b), to require Otter Tail to interconnect with the town and sell it power at wholesale.”
Am. Paper Inst., Inc. v. Am. Elec. Power Serv. Corp., 461 U.S. 402 (1983).“Prior to their enactment, the Commission’s authority to order interconnections was limited, under § 202(b) of the FPA, 16 U. S. C. § 824a(b), to utilities over which it had regulatory jurisdiction and, except in emergencies, to situations in which a “person engaged in the .”
Mid-Texas Commc'ns Sys., Inc. v. Am. Tel. & Tel. Co., 615 F.2d 1372 (5th Cir. 1980).“” 16 U.S.C. § 824a(b). The Supreme Court rejected the argument on the ground that the statutory provision was designed to foster voluntary interconnection.”
City of Cleveland v. Fed. Power Comm'n, 525 F.2d 845 (D.C. Cir. 1976).“See Federal Power Act § 202(b), 16 U.S.C. § 824a(b) (1970). 17 . See Federal Power Act § 202(c), 16 U.”
Showing the top 5 of 21. More in the list view →
(c)7 cases
Younger v. Jensen, 26 Cal. 3d 397 (1980).“1022 ] (FPC authority to order electric utility interconnections (16 U.S.C. § 824a(c); cf. Natural Gas Act, 15 U.”
Mirant Corp. v. Potomac Elec. Power Co. (In re Mirant Corp.), 378 F.3d 511 (5th Cir. 2004).“, 16 U.S.C. § 824a(c) (permitting FERC to require from public utilities, whenever it determines an emergency exists, “such generation, delivery, interchange, or transmission of electric energy as in its judgment will best meet the emergency and serve the public interest”); 16 U.”
City of Cleveland v. Fed. Power Comm'n, 525 F.2d 845 (D.C. Cir. 1976).
Showing the top 5 of 7. More in the list view →
(e)1 case
Greene Cnty. Plan. Bd. v. Fed. Power Comm'n, 528 F.2d 38 (2d Cir. 1975).
(f)4 cases
California ex rel. Lockyer v. Dynegy, Inc., 375 F.3d 831 (9th Cir. 2004).
Maine Pub. Serv. Co. v. Fed. Power Comm'n, 579 F.2d 659 (1st Cir. 1978).
Florida Power & Light Co. v. Fed. Power Comm'n, 430 F.2d 1377 (5th Cir. 1970).
(g)2 cases

Show all 115 citing cases (list view) →

Enactment and amendments
(June 10, 1920, ch. 285, pt. II, § 202, as added Aug. 26, 1935, ch. 687, title II, § 213, 49 Stat. 848; amended Aug. 7, 1953, ch. 343, 67 Stat. 461; Pub. L. 95–617, title II, § 206(a), Nov. 9, 1978, 92 Stat. 3141; Pub. L. 114–94, div. F, § 61002, Dec. 4, 2015, 129 Stat. 1772.)
Amendment years (notes): 2015, 1978, 1953
Versions

Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.