16 U.S.C. § 825g (2026)
Hearings; rules of procedure
Edition and currency
Other sources
Courts have cited this section in 24 opinions since 1938, 1 of them in the last five years. The most litigated part is subsection (a) (12 cases).
- Where it cites § 825g
- “16 U.S.C. § 825g(a) (emphasis added). Pursuant to this statutory authority, the Commission has promulgated Rule 214, which governs what persons may intervene and thereby become parties in Commission proceedings.”
- The case’s holding
- An agency possesses broad discretion to deny late intervention under its rules and is not required to weigh every factor to find a lack of good cause.
- Later courts cite it for
- “normally 25 will be granted in the absence of bad faith on the part of the party seeking relief or prejudice to 26 the adverse party.” · 6 citing courts
- Where it cites § 825g
- “The first, raised by American Electric Power Service Corporation and the Public Utilities Commission of Ohio (participation by state commissions in rate proceedings before FERC is authorized by 16 U.S.C. § 825g(a); see also § 825 l (a)), involves the pricing of electricity…”
- The case’s holding
- A regulatory agency may not approve a pricing scheme requiring utilities to pay for facilities from which they derive no benefits or only trivial benefits relative to the costs.
- Later courts cite it for
- “ferc is not authorized to approve a pricing scheme that requires a group of utilities to pay for facilities from which its members derive no benefits, or benefits that are trivial in relation to the costs sought to be shifted to its members.” · 4 citing courts
- Where it cites § 825g
- “See also 16 U.S.C. § 825g(a) (1982) (giving Commission broad authority to admit as a party in any proceeding before it any interested state or local government entity, competitors, representatives of consumers or security holders, "or any other person whose participation in the…”
- The case’s holding
- A party denied statutory written notice of a permit application is considered a party for the limited purpose of reviewing the agency's basis for denying party status.
- Later courts cite it for
- “considered a party for the limited purpose of reviewing the agency's basis for denying party status.” · 2 citing courts
- Where it cites § 825g
- “§ 825g(a) (“In any proceeding before it, the Commission, in accordance with such rules and regulations as it may prescribe, may admit as a party any interested State, State commission, municipality, or any representative of interested consumers or security holders, or any…”
- Later courts cite it for
- “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” · 4 citing courts
- Where it cites § 825g
- “In Greene County, the Federal Power Commission was required to hold hearings on the application in question, pursuant to an existing agency review process, mandated by § 308 of the Federal Power Act, 16 U.S.C. § 825g. Therefore, the question before the Court was not one of…”
- The case’s holding
- The National Environmental Policy Act does not mandate public hearings in every instance nor require agencies to delay impact statements until all relevant environmental data is available.
- Later courts cite it for
- “if we were to impose a requirement that an impact statement can never be prepared until all relevant environmental effects were known, it is doubtful that any project could ever be initiated.” · 7 citing courts
- Where it cites § 825g
- “Schmidt and the Fallons were permitted to intervene in the licensing proceedings, pursuant to 16 U.S.C. § 825g(a). 1 *85 Neither Greene County, nor its county administrator, attempted to intervene in the proceedings, and they did not participate.”
- The case’s holding
- A waterway is navigable if it is used or suitable for interstate commerce, regardless of natural obstructions or periods of commercial disuse.
- Later courts cite it for
- “it is settled that historical works generally considered authentic are admissible in evidence, especially in cases such as this one which must delve into the relatively ancient and obscure origins of commerce on the nation's rivers.” · 1 citing court
- Where it cites § 825g
- “In stating that the “technical Rules of Evidence .”
- Later courts cite it for
- “when the administrative board has reached a decision and promulgated an order without considering all the evidence presented at the hearing, the 'decision and order' is arbitrary and should be reversed.” · 1 citing court
- Where it cites § 825g
- “Since there must be some rules to govern admission of evidence in proceedings before the county valuation protests boards, these rules must be found in the body of administrative law that has grown up in the courts. In stating that the "technical Rules of Evidence .”
- The case’s holding
- At county valuation protest hearings, taxpayers may take discovery and must have relevant evidence admitted, and boards must hear claims of unconstitutional assessment discrimination.
- Where it cites § 825g
- “84 16 U.S.C. § 825g(b) (2012). PSMF ¶ 8; DRPSMF ¶ 8.”
- Later courts cite it for
- “any off-the-record communications between (i) commissioners and the staff that may advise them (decisional staff) and (ii) enforcement prosecutorial staff involved in the investigation or show cause proceeding.” · 2 citing courts
- Where it cites § 825g
- “That federal agencies possess such discretionary authority has been recognized by the Comptroller General since the Greene County I panel decision, and in the case of the FPC would be based on two statutes that were not considered by that panel, § 308 of the Federal Power Act,…”
- Later courts cite it for
- “none of the intervenors deserved such compensation in any event since they had only been 'protecting their own interests.” · 2 citing courts
- Where it cites § 825g
- “After the Commission’s order approving the merger was entered, the petitioners (intervenors) filed a petition for rehearing with the Commission.”
- Where it cites § 825g
- “In any case, the Federal Power Act creates no absolute right of intervention; § 308(a), 16 U.S.C. § 825g(a), reads: “In any proceeding before it, the Commission, in accordance with such rules and regulations as it may prescribe, may admit as a party any interested State, State…”
- The case’s holding
- An administrative agency has an affirmative duty to inquire into and consider all relevant facts and feasible alternatives when making licensing decisions.
- Later courts cite it for
- “in order to insure that the federal power commission will adequately protect the public interest in the aesthetic, conservational, and recreational aspects of power development, those who by their activities and conduct have exhibited a special interest in such areas, must be held to be included in the class of 'aggrieved' parties.” · 8 citing courts
- Where it cites § 825g
- “” 16 U.S.C. § 825g(b) describes the procedural rules to be applied to all Federal Power Act hearings, including ratemaking: “All hearings, investigations, and proceedings under this chapter shall be governed by the rules of practice and procedure to be adopted by the Commission.”
- The case’s holding
- Federal Power Act procedural requirements regarding ex parte communications and case-in-chief filings apply to nonregional rate proceedings.
- Later courts cite it for
- “usually implement existing law, imposing general, extrastatutory obligations pursuant to authority properly delegated by congress.” · 3 citing courts
- Where it cites § 825g
- “” 23 *422 There can be no question that the hearings on PASNY’s application, ordered pursuant to Section 308 of the Federal Power Act, 16 U.S.C. § 825g, and Section 1.20 of the Commission’s rules, 18 C.”
- The case’s holding
- A federal agency bears the primary and nondelegable responsibility to consider environmental values at every stage of its process and cannot substitute an applicant's submission for its own statement.
- Later courts cite it for
- “to consider environmental values 'at every distinctive and comprehensive stage of the (agency's) process.' the primary and nondelegable responsibility for fulfilling that function lies with the commission.” · 4 citing courts
- Where it cites § 825g
- “Trial-type hearing Under 16 U.S.C. § 825g (Federal Power Act) in conjunction with 5 U.”
- Later courts cite it for
- “carefully considered the in-tervenor's written submissions and responded to each of its comments.” · 2 citing courts
- Where it cites § 825g
- “” 8 Under § 308 of the Federal Power Act, Title 16 U.S.C.A. § 825g, the order granting the license was a matter “required by statute to be determined on the record after opportunity for an agency hearing” within the meaning of § 1004 of Title 5 U.”
- Where it cites § 825g
- “The Commission, pursuant to section 308 of the act, 16 U.S.C.A. § 825g, heretofore referred to, prescribes its own rules of procedure and must itself pass upon the propriety of the evidence offered and its admissibility.”
- Where it cites § 825g
- “” 16 U.S.C. § 825g(b); see also id. § 825h (authorizing FERC to make “such orders, rules, and regulations as it may find necessary or appropriate to carry out the provisions of” the Federal Power Act).”
- Where it cites § 825g
- “Since, however, the Commission’s dismissal of petitioner’s application was without prejudice, this holding does not foreclose petitioner from using the proffered evidence in another context.”
Show all 24 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per 2 years. Tallest: 5 cases in 2008–2009. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
(a)12 cases
(b)8 cases
Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.