U.S. CodeTitle 16Chapter 12H— Pacific Northwest Electric Power Planning and Conservation

16 U.S.C. § 839 (2026)

Congressional declaration of purpose

Edition and currency
U.S. Code current through Pub. L. 119-102 (OLRC release point). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTU.S. Code current through Pub. L. 119-102 (OLRC release point) cited 1982–2025 95citing cases
At a glance

Courts have cited this section in 95 opinions since 1982, 3 of them in the last five years. The most litigated part is subsection (5) (1 case).

The purposes of this chapter, together with the provisions of other laws applicable to the Federal Columbia River Power System, are all intended to be construed in a consistent manner. Such purposes are also intended to be construed in a manner consistent with applicable environmental laws. Such purposes are:(1) to encourage, through the unique opportunity provided by the Federal Columbia River Power System—(A) conservation and efficiency in the use of electric power, and(B) the development of renewable resources within the Pacific Northwest;(2) to assure the Pacific Northwest of an adequate, efficient, economical, and reliable power supply;(3) to provide for the participation and consultation of the Pacific Northwest States, local governments, consumers, customers, users of the Columbia River System (including Federal and State fish and wildlife agencies and appropriate Indian tribes), and the public at large within the region in—(A) the development of regional plans and programs related to energy conservation, renewable resources, other resources, and protecting, mitigating and enhancing fish and wildlife resources,(B) facilitating the orderly planning of the region’s power system, and(C) providing environmental quality;(4) to provide that the customers of the Bonneville Power Administration and their consumers continue to pay all costs necessary to produce, transmit, and conserve resources to meet the region’s electric power requirements, including the amortization on a current basis of the Federal investment in the Federal Columbia River Power System;(5) to insure, subject to the provisions of this chapter—(A) that the authorities and responsibilities of State and local governments, electric utility systems, water management agencies, and other non-Federal entities for the regulation, planning, conservation, supply, distribution, and use of electric power shall be construed to be maintained, and(B) that Congress intends that this chapter not be construed to limit or restrict the ability of customers to take actions in accordance with other applicable provisions of Federal or State law, including, but not limited to, actions to plan, develop, and operate resources and to achieve conservation, without regard to this chapter; and(6) to protect, mitigate and enhance the fish and wildlife, including related spawning grounds and habitat, of the Columbia River and its tributaries, particularly anadromous fish which are of significant importance to the social and economic well-being of the Pacific Northwest and the Nation and which are dependent on suitable environmental conditions substantially obtainable from the management and operation of the Federal Columbia River Power System and other power generating facilities on the Columbia River and its tributaries.(Pub. L. 96–501, § 2, Dec. 5, 1980, 94 Stat. 2697.)Editorial NotesReferences in Text

This chapter, referred to in provision preceding par. (1) and in par. (5), was in the original “this Act”, meaning Pub. L. 96–501, Dec. 5, 1980, 94 Stat. 2697, known as the Pacific Northwest Electric Power Planning and Conservation Act, which enacted this chapter, amended sections 837, 838i, and 838k of this title, and enacted provisions set out as notes under this section. For complete classification of this Act to the Code, see Short Title note set out below and Tables.

Statutory Notes and Related SubsidiariesEffective Date

Pub. L. 96–501, § 11, Dec. 5, 1980, 94 Stat. 2735, provided that: “This Act [enacting this chapter, amending sections 837, 838i, and 838k of this title, and enacting provisions set out as notes under this section] shall be effective on the date of enactment [Dec. 5, 1980], or October 1, 1980, whichever is later. For purposes of this Act, the term ‘date of the enactment of this Act’ means such date of enactment [Dec. 5, 1980] or October 1, 1980, whichever is later.”

Short Title

Pub. L. 96–501, § 1, Dec. 5, 1980, 94 Stat. 2697, provided in part that: “This Act [enacting this chapter, amending sections 837, 838i, and 838k of this title, and enacting provisions set out as notes under this section] may be cited as the ‘Pacific Northwest Electric Power Planning and Conservation Act’.”

The 20 cases that cite 16 U.S.C. § 839 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENAlcoa, Inc. v. Bonneville Power Admin., 698 F.3d 774 (9th Cir. 2012).
cites § 839 4×cited by 48 cases
Where it cites § 839
“Finally, BPA is charged with “assur[ing] the timely implementation of [ 16 U.S.C. §§ 839 -839h] in a sound and businesslike manner.”
The case’s holding
A federal agency is not required to maximize profits but must act in a manner consistent with its public mission and statutory mandates.
Later courts cite it for
“claims that are based solely on harms stemming from events that have not yet occurred, and may never occur,” · 3 citing courts
2
GREENCity of Tacoma v. Taxpayers of City of Tacoma, 743 P.2d 793 (Wash. 1987).
cites § 839 4×cited by 139 cases
Where it cites § 839
“2697 (1980) (codified at 16 U.S.C. § 839 ). Both the Pacific Northwest Electric Power and Conservation Planning Council (Regional Council) and the BPA consider conservation a resource of electrical energy equivalent to a generating plant.”
The case’s holding
A municipal utility program providing electricity through conservation measures is constitutional if the utility receives sufficient bargained for consideration in the form of a public benefit.
Later courts cite it for
“bears a sufficiently close nexus to the purpose and object the legislature intended to serve in granting the power to operate an electric utility.” · 6 citing courts
3
GREENNat'l Wildlife Fed'n v. Nat'l Marine Fisheries Serv., 524 F.3d 917 (9th Cir. 2008).
cites § 839 2×cited by 159 cases
Where it cites § 839
“Although we acknowledge that the existence of the dams must be included in the environmental baseline, *931 the operation of the dams is within the federal agencies’ discretion under both the ESA and the Northwest Power Act, 16 U.S.C. § 839 . Any proposed agency action must be…”
The case’s holding
An agency must evaluate jeopardy by considering both the survival and recovery of a species within the context of the existing environmental baseline.
Later courts cite it for
“jeopardize the continued existence of' means "to engage in an action that reasonably would be expected, directly or indirectly, to reduce appreciably the likelihood of both the survival and recovery of a listed species in the wild by reducing the reproduction, numbers, or distribution of that species.” · 11 citing courts
cites § 839 3×cited by 35 cases
Where it cites § 839
“with a view to encouraging the widest possible diversified use of electric power at the lowest possible rates to consumers consistent with sound business principles” (emphasis added)); § 839a(5) (defining “consumer” as “any end user of electric power”).”
The case’s holding
A petitioner's legally protected interest need not be statutorily created; economic injury from utility price increases passed through customer contracts can establish concrete, particularized Article III standing.
Later courts cite it for
“a petitioner's 'legally protected interest' need not be a statutorily created interest,” · 4 citing courts
5
GREENPortland Gen. Elec. Co. v. Bonneville Power Admin., 501 F.3d 1009 (9th Cir. 2007).
cites § 839 2×cited by 62 cases
Where it cites § 839
“In order to avoid an energy crisis and to redress BPA’s diminishing ability to satisfy the region’s power demands, Congress enacted the Pacific Northwest Electric Power Planning and Conservation Act of 1980, 16 U.S.C. §§ 839 -839h (2000) (“Northwest Power Act” or “NWPA”).”
The case’s holding
An agency's general authority to enter into settlement agreements is limited by its specific statutory obligations and requirements governing the subject matter of the settlement.
Later courts cite it for
“as a general rule, we will not review challenges to agency action raised for the first time on appeal.” · 4 citing courts
cites § 839 2×cited by 148 cases
Where it cites § 839
“2697 , 16 U. S. C. § 839 et seq. (Regional Act).”
The case’s holding
An agency administrator's interpretation of its governing statute is entitled to great weight (reasoning that the interpretation is to be given great weight).
Later courts cite it for
“because the exchange program essentially requires bpa to trade its cheap power for more expensive power, it is obviously a money-losing pro- gram for bpa.” · 4 citing courts
7
GREENS. California Edison v. United States, 58 Fed. Cl. 313 (Fed. Cl. 2003).
cites § 839 2×cited by 39 cases
Where it cites § 839
“§§ 838 -838Í; and the Pacific Northwest Electric Power Planning and Conservation Act of 1980, as amended (“Northwest Power Planning Act”), 16 U.S.C. §§ 839 -839h. The contract itself makes no reference to these statutes, and the parties have given them short shrift in their…”
The case’s holding
Contract interpretation is a question of law that a court may resolve on a motion to dismiss, beginning with the written agreement's language and giving plain meaning to clear terms.
Later courts cite it for
“contract interpretation is a matter of law and thus may be addressed by the court in resolving a motion to dismiss.” · 8 citing courts
8
GREENPacificorp v. Bonneville Power Admin., 856 F.2d 94 (9th Cir. 1988).
cites § 839 5×subsections: (5)cited by 15 cases
Where it cites § 839
“See Pacific Northwest Electric Power Planning and Conservation Act (Planning Act), 16 U.S.C. § 839 et seq. (1982). SVEC is an electrical cooperative organized under the Rural Electrification Administration, and, as such, it receives BPA power at the priority firm rate.”
9
GREENGolden Nw. Aluminum, Inc. v. Bonneville Power Admin., 501 F.3d 1037 (9th Cir. 2007).
cites § 839 2×cited by 19 cases
Where it cites § 839
“Section 7 requires, among other things, that BPA charge rates sufficient to cover its costs, “including the amortization of the Federal investment in the Federal Columbia River Power System.”
The case’s holding
An agency rate case is not the proper forum for deciding which specific fish and wildlife alternatives to implement.
Later courts cite it for
“chronicle the history of bpa and describe the tangle of statutes that govern its operations.” · 3 citing courts
cites § 839 2×cited by 38 cases
Where it cites § 839
“Recognizing these common themes, we find that the IAP is consistent with BPA statutory authority and is not an arbitrary and capricious exercise of its discretion. Accordingly, we uphold the validity of the Near Term Intertie Access Policy.”
The case’s holding
An agency's interpretation of its enabling statutes is valid if it is reasonable, even if it is not the only possible interpretation.
Later courts cite it for
“bpa is required to allocate use of federally-owned transmission facilities in a manner which accords preference first to transmission of federal power and then to transmission of other northwest-generated power.” · 2 citing courts
11
GREENPuget Sound Power & Light Co. v. United States, 23 Cl. Ct. 46 (Ct. Cl. 1991).
cites § 839 3×cited by 16 cases
Where it cites § 839
“In 1980, in order to avoid years of litigation and what the Governor of Washington described as a “regional civil war” over low-cost power, Congress enacted the Pacific Northwest Electric Power Planning and Conservation Act, 16 U.S.C. §§ 839 -839h (hereinafter the Northwest…”
Later courts cite it for
“thereby waiving the government's traditional immunity, must be explicit and strictly construed.” · 3 citing courts
12
GREENNat'l Wildlife Fed'n v. Fed. Energy Regulatory Comm'n, 801 F.2d 1505 (9th Cir. 1986).
cites § 839 2×cited by 30 cases
Where it cites § 839
“§§ 4321 -4370a (1982), and the Pacific Northwest Electric Power Planning and Conservation Act (“Northwest Power Act”), 16 U.S.C. §§ 839 -39h (1982). The Nez Perce Tribe argues that the Commission has breached its obligations under the Nez Perce Treaty, 12 Stat.”
The case’s holding
A federal agency licensing hydroelectric projects must consider each project within the entire river basin, and a comprehensive basin plan must be available before licensing, absent record-supported reasons.
Later courts cite it for
“each particular dam project should be given consideration not only with a view to the locality where constructed but with reference to the entire water system of which it constituted a part.” · 2 citing courts
13
GREENBonneville Power Admin. v. Mirant Corp., 440 F.3d 238 (5th Cir. 2006).
cites § 839 1×cited by 49 cases
Where it cites § 839
“Originally, BPA marketed the energy produced for the benefit of the public, particularly domestic and rural customers, giving preference and priority to public bodies and cooperatives. See § 832c(a). For some time, surplus in energy production meant BPA could market freely to…”
The case’s holding
The bankruptcy code exception to ipso facto clauses requires an actual inquiry into applicable law rather than a hypothetical one.
Later courts cite it for
“flexibility to the bankruptcy courts.” · 5 citing courts
14
GREENNat'l Wildlife Fed'n v. Fed. Energy Regulatory Comm'n, 870 F.2d 542 (9th Cir. 1989).
cites § 839 2×cited by 28 cases
Where it cites § 839
“On review in this court, the Federations challenged the Commission’s decision on five theories: (1) the Commission’s refusal to adopt a comprehensive plan and to fashion a coordinated study process for the Salmon River Basin violated the FPA; (2) the Commission violated the…”
Later courts cite it for
“significant issue in litigation which achieved some of the benefit they sought in bringing suit.” · 2 citing courts
15
GREENPortland Gen. Elec. Co. v. Peter Johnson, 754 F.2d 1475 (9th Cir. 1985).
cites § 839 2×cited by 24 cases
Where it cites § 839
“1 Petitioner alleges that BPA failed to follow ratemaking procedures mandated by the Pacific Northwest Electric Power Planning and Conservation Act, 16 U.S.C. §§ 839 -839h (1982). We find that petitioner had standing to bring this action, that the action is timely, and that the…”
Later courts cite it for
“when bpa offers to sell power to a class of customers at a rate unavailable to that class under the established rate structure, it has modified the rate structure and generally must follow the statutorily-prescribed ratemaking procedures.” · 2 citing courts
16
GREENHarriet F. Laflamme v. Fed. Energy Regulatory Comm'n, 852 F.2d 389 (9th Cir. 1988).
cites § 839 1×cited by 82 cases
Where it cites § 839
“In Forelaws the Bonneville Power Administration (BPA) argued that it did not prepare an Environmental Impact Statement (EIS) prior to offering long term contracts for power delivery pursuant to the Pacific Northwest Electric Power Planning & Conservation Act (Regional Act), 16…”
The case’s holding
An environmental impact statement must be prepared if a plaintiff raises substantial questions regarding whether a project may have a significant effect on the environment.
Later courts cite it for
“the plaintiff need not show that significant effects will in fact occur, but if the plaintiff raises substantial questions whether a project may have a significant effect, an eis must be prepared.” · 3 citing courts
17
GREENPac. Nw. Generating Coop. v. Brown, 822 F. Supp. 1479 (D. Or. 1993).
cites § 839 2×cited by 18 cases
Where it cites § 839
“The BPA does not, however, participate in such programs of its own initiative, but is required to do so through the Pacific Northwest Electric Power and Conservation Planning Council under the Northwest Power Act (NWPA), 16 U.S.C. § 839 (6), 839b(a)(2), (e)(1) & (h).”
The case’s holding
Generalized claims of agency failure within the habitat sector are not ripe for adjudication when unparticularized allegations make it impossible to determine the duration of the alleged injury.
Later courts cite it for
“because these plaintiffs have relied upon generalized claims of esa violations by defendants within the habitat sector, it is impossible at this time to tell if the generalized failures are of such a short duration that they may evade review.” · 4 citing courts
18
GREENForelaws on Bd. v. Johnson, 743 F.2d 677 (9th Cir. 1984).
cites § 839 5×cited by 41 cases
Where it cites § 839
“This is a challenge to the Bonneville Power Administration’s offers of long term contracts for power delivery pursuant to the Pacific Northwest Electric Power Planning and Conservation Act (Regional Act), 16 U.S.C. § 839 -839h (1982), without compliance with the requirements of…”
The case’s holding
An agency violates the National Environmental Policy Act by failing to prepare an environmental impact statement despite statutory deadlines that appear to conflict with the requirement.
Later courts cite it for
“clear tension between nepa's charge to the agency to evaluate the effects of action upon the environment and the command of the regional act that the contracts be in place within 21 months of its passage.” · 3 citing courts
19
GREENPseg Nuclear v. United States, 465 F.3d 1343 (Fed. Cir. 2006).
cites § 839 1×cited by 23 cases
Where it cites § 839
“There, we considered the scope of the judicial review provision contained in the Pacific Northwest Electric Power Planning and Conservation Act of 1980, 16 U.S.C. §§ 839 -839h (“NPA”). The NPA permitted the BPA to enter into contracts which included some statutorily mandated…”
The case’s holding
The Nuclear Waste Policy Act does not strip the Court of Federal Claims of Tucker Act jurisdiction over claims for breach of contract and resulting damages.
Later courts cite it for
“issues of whether the doe breached its contractual obligations, and if so, to what damages, if any, pseg is entitled for the breach.” · 1 citing court
20
GREENIn re Consol. Salmonid Cases, 791 F. Supp. 2d 802 (E.D. Cal. 2011).
cites § 839 2×cited by 7 cases
Where it cites § 839
“See Northwest Power Act, 16 U.S.C. § 839 (providing for purposes of 1980 Pacific Northwest Electric Power Planning and Conservation Act "to be construed in a manner consistent with applicable environmental laws"); ALCOA, 175 F.”
The case’s holding
Under the ESA and APA, an agency biological opinion must rest on the best available science and a rational explanation, and courts defer to agency expertise but not without limit.

Show all 95 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198220032025

One bar per year. Tallest: 7 cases in 1984. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
9th Cir.63D. Or.9Fed. Cl.7E.D. Cal.35th Cir.2Ct. Cl.2E.D. Wash.2D. Ariz.1

The 8 courts with the most citing cases, of 14 courts in all.

By subsection
(5)1 case
Pacificorp v. Bonneville Power Admin., 856 F.2d 94 (9th Cir. 1988).“See Pacific Northwest Electric Power Planning and Conservation Act (Planning Act), 16 U.S.C. § 839 et seq. (1982). SVEC is an electrical cooperative organized under the Rural Electrification Administration, and, as such, it receives BPA power at the priority firm rate.”

Show all 95 citing cases (list view) →

Enactment and amendments
(Pub. L. 96–501, § 2, Dec. 5, 1980, 94 Stat. 2697.)
Versions

Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.