22 U.S.C. § 306 (2026)
Contracting methods in capital construction
Edition and currency
Other sources
Unless the Secretary of State notifies the appropriate congressional committees that the use of the design-build project delivery method would not be appropriate, the Secretary shall make use of such method at United States diplomatic posts that have not yet received design or capital construction contracts as of
Before executing a contract for a delivery method other than design-build in accordance with subsection (a), the Secretary of State shall notify the appropriate congressional committees in writing of the decision, including the reasons therefor. The notification required by this subsection may be included in any other report regarding a new United States diplomatic post that is required to be submitted to the appropriate congressional committees.
Not later than 180 days after
Section was enacted as part of the Department of State Authorization Act of 2021 and also as part of the National Defense Authorization Act for Fiscal Year 2022, and not as part of the Foreign Service Buildings Act, 1926, which comprises this chapter.
For definitions of “appropriate congressional committees” and “Department” as used in this section, see section 5002 of Pub. L. 117–81, set out as a note under section 263c of this title.
Pub. L. 117–81, div. E, title LII, § 5214,