U.S.C. homeSearch U.S. Code
U.S. CodeTitle 41Subtitle I— Federal Procurement PolicyDivision B— Office of Federal Procurement PolicyChapter 15— Cost Accounting Standards

41 U.S.C. § 1503 (2026)

Contract price adjustment

Edition and currency
U.S. Code current through Pub. L. 119-102 (OLRC release point). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTU.S. Code current through Pub. L. 119-102 (OLRC release point) cited 2012–2024 8citing cases
At a glance

Courts have cited this section in 8 opinions since 2012, 2 of them in the last five years.

(a)Disagreement Constitutes a Dispute.—If the Federal Government and a contractor or subcontractor fail to agree on a contract price adjustment, including whether the contractor or subcontractor has complied with the applicable cost accounting standards, the disagreement will constitute a dispute under chapter 71 of this title.(b)Amount of Adjustment.—A contract price adjustment undertaken under section 1502(f)(2) of this title shall be made, where applicable, on relevant contracts that are subject to the cost accounting standards so as to protect the Federal Government from payment, in the aggregate, of increased costs, as defined by the Cost Accounting Standards Board and in accordance with the following requirements:(1) The Federal Government may not recover costs greater than the aggregate increased cost to the Federal Government, as defined by the Board, on the relevant contracts subject to the price adjustment unless the contractor or subcontractor made a change in its cost accounting practices of which the contractor or subcontractor was aware or should have been aware at the time of the price negotiation and which contractor or subcontractor failed to disclose to the Federal Government.(2) For such changes in cost accounting practices—(A) costs recovered by the Federal Government shall exclude any contract or subcontract (or any portion of such contract or subcontract) that is firm, fixed-price, or that is not price-redeterminable based on costs; and(B) for a fiscal year, for any contract or subcontract (or any portion of such contract or subcontract) that is not a firm, fixed-price contract or subcontract the costs recovered by the Federal Government shall not exceed the net increased costs, if any, paid to the contractor or subcontractor for all changes in cost accounting practices implemented within the same fiscal year.(c)Interest.—The interest rate applicable to a contract price adjustment is the annual rate of interest established under section 6621 of the Internal Revenue Code of 1986 (26 U.S.C. 6621) for the period. Interest accrues from the time payments of the increased costs were made to the contractor or subcontractor to the time the Federal Government receives full compensation for the price adjustment.(Pub. L. 111–350, § 3, Jan. 4, 2011, 124 Stat. 3699; Pub. L. 119–60, div. A, title XVIII, § 1806(f)(1), Dec. 18, 2025, 139 Stat. 1240.)

Historical and Revision Notes

Revised

Section

Source (U.S. Code)

Source (Statutes at Large)

1503(a)

41:422(h)(2).

Pub. L. 93–400, § 26(h)(2)–(4), as added Pub. L. 100–679, § 5(a), Nov. 17, 1988, 102 Stat. 4062.

1503(b)

41:422(h)(3).

1503(c)

41:422(h)(4).

Editorial NotesAmendments

2025—Subsec. (b). Pub. L. 119–60 amended subsec. (b) generally. Prior to amendment, text read as follows: “A contract price adjustment undertaken under section 1502(f)(2) of this title shall be made, where applicable, on relevant contracts between the Federal Government and the contractor that are subject to the cost accounting standards so as to protect the Federal Government from payment, in the aggregate, of increased costs, as defined by the Cost Accounting Standards Board. The Federal Government may not recover costs greater than the aggregate increased cost to the Federal Government, as defined by the Board, on the relevant contracts subject to the price adjustment unless the contractor made a change in its cost accounting practices of which it was aware or should have been aware at the time of the price negotiation and which it failed to disclose to the Federal Government.”

Statutory Notes and Related SubsidiariesRegulations

Pub. L. 119–60, div. A, title XVIII, § 1806(f)(2), Dec. 18, 2025, 139 Stat. 1240, provided that: “Not later than 180 days after the date of the enactment of this Act [Dec. 18, 2025], the Administrator for Federal Procurement Policy shall issue such regulations as are necessary to implement the amendments made by this subsection [amending this section].”

The 8 cases that cite 41 U.S.C. § 1503 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENBoeing Co. v. United States, 968 F.3d 1371 (Fed. Cir. 2020).
cites § 1503 4×cited by 36 cases
Where it cites § 1503
“606 undisputedly required the Defense Department to act as it did, that regulation is unlawful— principally because it is contrary to 41 U.S.C. § 1503 (b) (and also for procedural reasons).”
The case’s holding
Allegations of subject matter jurisdiction must satisfy a relatively low standard, but essentially fictitious or obviously frivolous claims fall outside the jurisdiction of the Court of Federal Claims.
Later courts cite it for
“allegations of subject matter jurisdiction, to suffice, must satisfy a relatively low standard-must exceed a threshold that 'has been equated with such concepts as "essentially fictitious," "wholly insubstantial," "obviously frivolous," and "obviously without merit.” · 5 citing courts
2
GREENBoeing Co. v. United States, 119 F.4th 17 (Fed. Cir. 2024).
cites § 1503 3×cited by 9 cases
Where it cites § 1503
“” 41 U.S.C. § 1503 (b). Further, Case: 23-1018 Document: 41 Page: 4 Filed: 10/04/2024 4 BOEING COMPANY v.”
Later courts cite it for
“pursuant to 1491(a)(1) of the tucker act, the court of federal claims also has jurisdiction to entertain monetary claims against the united states based on contracts with the united states, the constitution, or other money mandating statutes or regulation. 28 u.s.c. 1491 (a)(1).” · 2 citing courts
3
GREENDirectv Grp., Inc. v. United States, 670 F.3d 1370 (Fed. Cir. 2012).
cites § 1503 2×cited by 19 cases
Where it cites § 1503
“§ 422 (h)(3) was recodified at 41 U.S.C. § 1503 (b). [3] § 15 was recodified at the same time as § 422 at 41 U.”
Later courts cite it for
“as a matter of elementary grammar, the statute's 27 use of 'such' is a demonstrative adjective, and it must refer to a clear antecedent.” · 2 citing courts
4
NO FLAGBoeing Co. v. United States, No. 17-1969 (Fed. Cl. May 29, 2019).
cites § 1503 7×cited by 0 cases
Where it cites § 1503
“606 was applied to Boeing’s contract, in violation of 41 U.S.C. § 1503 (b). Id. at 34-35 . When only the representative contract is considered, Boeing asserts that the government’s claim for $1,064,773 is invalid, and that damages for the payments paid by Boeing on the…”
5
NO FLAGBoeing Co. v. United States, No. 17-1969 (Fed. Cl. Sept. 21, 2022).
cites § 1503 3×cited by 0 cases
Where it cites § 1503
“) Cost Accounting Standards ) Statute; 41 U.S.C. § 1503 ; THE UNITED STATES, ) Illegal Exaction; Exclusive ) Remedy.”
6
NO FLAGGulley v. United States, No. 19-1816 (Fed. Cl. Oct. 19, 2020).
cites § 1503 2×cited by 0 cases
Where it cites § 1503
“- 15 - In Boeing, plaintiff, The Boeing Company, alleged that the government forced it to pay $1,064,773 to cover various increased costs caused by changes “in direct violation of 41 U.S.C. § 1503 (b), which requires that the Government may not recover costs greater than the…”
7
NO FLAGPerry v. United States, No. 19-1797 (Fed. Cl. June 17, 2020).
cites § 1503 1×cited by 0 cases
Where it cites § 1503
“26 See also Boeing Co. v. United States, 143 Fed. Cl.”
8
NO FLAGJohnson Lasky Kindelin Architects, Inc v. United States, No. 19-1419 (Fed. Cl. Dec. 23, 2020).
cites § 1503 1×cited by 0 cases
Where it cites § 1503
“41 U.S.C. § 1503 (b) (“Contract price adjustment”) (providing for CDA jurisdiction for cost accounting disputes involving “relevant contracts between the Federal Government and the contractor” (emphasis added)).”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
201220182024

One bar per year. Tallest: 4 cases in 2020. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.5Fed. Cir.3
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments
(Pub. L. 111–350, § 3, Jan. 4, 2011, 124 Stat. 3699; Pub. L. 119–60, div. A, title XVIII, § 1806(f)(1), Dec. 18, 2025, 139 Stat. 1240.)
Amendment years (notes): 2025
Versions

Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.

U.S.C. Home  |  Search U.S. Code  |  Search cases for this section  |  syfert.com