42 U.S.C. § 10222 (2026)
Nuclear Waste Fund
Edition and currency
Other sources
Courts have cited this section in 118 opinions since 1984, 4 of them in the last five years. The most litigated part is subsection (a)(1) (1 case).
Subsection (c), referred to in subsec. (a)(3), was in the original “subsection (c) 126(b)” and was translated as subsection (c) as the probable intent of Congress in view of the establishment of the Nuclear Waste Fund by subsec. (c) of this section and the absence of a section 126 in Pub. L. 97–425.
This subchapter, referred to in subsecs. (a)(5)(B), (d), and (e)(5), was in the original “this subtitle”, and was translated as this subchapter to reflect the probable intent of Congress because title III of Pub. L. 97–425, which enacted this subchapter, does not contain subtitles.
Such Act, referred to in subsec. (e)(5), probably means chapter 31 of Title 31, Money and Finance.
For termination, effective
- Where it cites § 10222
- “” 42 U.S.C. § 10222 (a)(5)(B). It failed to do so.”
- The case’s holding
- The Department of Energy lacks authority to use Nuclear Waste Fund monies to pay for interim storage costs resulting from its breach of contract.
- Later courts cite it for
- “in either circumstance ... be forced to pay for the damages ...” · 1 citing court
- Where it cites § 10222
- “Because the Nuclear Waste Policy Act (NWPA), 42 U.S.C. § 10222 , allows such assignments, we affirm the court's holding on this issue.”
- Later courts cite it for
- “a party to a standard contract cannot transfer its rights and duties to another party without also transferring title to the snf.” · 1 citing court
- Where it cites § 10222
- “” 42 U.S.C. § 10222 (a)(5)(A). In order to accomplish the goals of the nuclear waste disposal program, the NWPA authorized the Secretary of Energy “to enter into contracts with any person who generates or holds title to [HLW], or [SNF], of domestic origin for the acceptance of…”
- The case’s holding
- A court may not speculate on whether deferred costs will increase or decrease by the time a breaching party eventually performs a contract.
- Later courts cite it for
- “plaintiffs loading costs have been deferred rather than avoided, and the court declines to engage in a guessing game as to whether such deferred costs will have increased or decreased by the time (if ever) defendant performs.” · 2 citing courts
- Where it cites § 10222
- “The sales contract included an assignment of the Standard Contract for disposal of SNF and HLW, as authorized by Section 302 of the NWPA, as amended, 42 U.S.C. § 10222 . 1 As the parties have construed the assignment, it permitted Boston Edison to retain claims for damages…”
- The case’s holding
- Section 119 of the Nuclear Waste Policy Act does not displace the jurisdiction of the Court of Federal Claims over breach of contract claims arising under Title III.
- Later courts cite it for
- “because the motion to strike raises a threshold issue, that motion is addressed initially.” · 2 citing courts
- Where it cites § 10222
- “at 165 (citing 42 U.S.C. § 10222 (a)(1)). The NWPA provides that contracts were to be entered requiring the contracting utilities to pay a one-time fee for the electricity generated and sold prior to April 7, 1983, and a continuing fee based on the amount of electricity…”
- The case’s holding
- The government must demonstrate with reasonable certainty that claimed benefits exist to offset costs, as speculative claims are insufficient (establishing the standard for offsetting benefits).
- Later courts cite it for
- “any 'benefits' the government seeks to offset must be shown to a reasonable certainty, or they must be denied as too speculative to meet the standards set forth by the federal circuit in indiana michigan.” · 2 citing courts
- Where it cites § 10222
- “See 42 U.S.C. § 10222 (a)(1). The NWPA required that all contracts “shall provide that” the Department will dispose of the waste “beginning not later than January 31, 1998,” id.”
- The case’s holding
- The concept of a taking has limited application when the parties' rights are voluntarily created by contract and interference with those rights generally gives rise to a breach of contract claim.
- Later courts cite it for
- “although plaintiff may have real property interests that are separate from its interests under the standard contract, plaintiff does not have a takings claim absent the rights and obligations granted to the parties by the standard contract.” · 2 citing courts
- Where it cites § 10222
- “7, 1983) (codified at 42 U.S.C. § 10222 (2000)), Congress directed DOE to “enter into [Standard Contracts with all entities that] generate[ ] or hold[] title to high-level radioactive waste, or spent nuclear fuel, of domestic origin for the acceptance of title, subsequent…”
- The case’s holding
- Damages for breach of contract are recoverable only if they were reasonably foreseeable, caused by the breach, and shown with reasonable certainty.
- Later courts cite it for
- “the remedy for breach of contract is damages sufficient to place the injured party in as good a position as it would have been had the breaching party fully performed.” · 54 citing courts
- Where it cites § 10222
- “7, 1983) (codified as amended at 42 U.S.C. § 10222 ). Under the NWPA and the Standard Contract, DOE was to begin collecting SNF no later than January 31, 1998.”
- The case’s holding
- The NRC minimum decommissioning fund formula excludes costs for dismantling non-radiological structures and managing or storing spent fuel until transfer to the government.
- Later courts cite it for
- “the nrc formulas and the calculated fund amounts herein exclude the cost of dismantling or demolishing non-radiological systems and structures as well as costs to manage and store spent fuel until transfer to doe.” · 1 citing court
- Where it cites § 10222
- “7, 1983) (codified at 42 U.S.C. § 10222 ), authorizing DOE “to enter into contracts with any person who generates or holds title to high-level radioactive waste [‘HLW’], or spent nuclear fuel, of domestic origin for the acceptance of title, subsequent transportation, and…”
- The case’s holding
- A government agency breaches the implied covenant of good faith and fair dealing by failing to act on contractually mandated schedules, allowing for recovery of mitigation costs.
- Later courts cite it for
- “doe's failure to perform under the standard contract thus has led to the very thing the nwpa and the standard contract were designed to forestall, i.e., the construction of dry storage facilities for spent nuclear fuel at nuclear power electricity generating plants throughout the united states.” · 2 citing courts
- Where it cites § 10222
- “See 42 U.S.C. § 10222 (b)(2) (“No [SNF or HLW] may be disposed of by the Secretary .”
- The case’s holding
- Mitigation of damages requires the deduction of any achieved savings from the total recoverable amount rather than requiring the plaintiff to mitigate at the least cost to the defendant.
- Later courts cite it for
- “to accept smud's position, the court would need to speculate about whether smud would have been successful in trading smud's acceptance priority with another utility or convincing doe to accept smud's snf early.” · 5 citing courts
- Where it cites § 10222
- “42 U.S.C. § 10222 (b). 4 Ind. *725 Mich. II, 422 F.”
- The case’s holding
- A party may recover reasonable mitigation costs incurred to limit damages from a partial breach, where those costs were reasonably foreseeable, substantially caused by the breach, and proven with reasonable certainty.
- Later courts cite it for
- “would have occurred in 1999 even if doe had begun performance in 1998.” · 5 citing courts
- Where it cites § 10222
- “2005) (citing 42 U.S.C. § 10222 (a)(1)); Maine Yankee, 225 F.”
- The case’s holding
- Mitigation costs for additional at-reactor storage are recoverable if the need for such expenditures was reasonably foreseeable to the breaching party at the time of contracting.
- Later courts cite it for
- “foreseeable to doe at the time of contracting.” · 2 citing courts
- Where it cites § 10222
- “” 42 U.S.C. § 10222 (a)(1). 5 The Department drafted a Standard Contract for use with participants in the program and published it for comment.”
- Where it cites § 10222
- “See 42 U.S.C. § 10222 (b)(2) (“No [SNF or HLW] may be disposed of by the Secretary .”
- Where it cites § 10222
- “” 42 U.S.C. § 10222 (a)(5)(B) (1994). Petitioners are utilities and state commissions who paid fees to the Secretary under the statute.”
- The case’s holding
- The Nuclear Waste Policy Act imposes an unconditional obligation on the Department of Energy to begin disposing of spent nuclear fuel by the statutorily mandated deadline.
- Later courts cite it for
- “without qualification or condition.” · 4 citing courts
- Where it cites § 10222
- “3d at 1372 (citing 42 U.S.C. § 10222 (2000)). The Act required that the contracts provide that: (A) following commencement of operation of a repository, the Secretary shall take title to high-level radioactive waste or spent nuclear fuel involved as expeditiously as practicable…”
- The case’s holding
- Mitigation costs are recoverable if the general response to a breach is foreseeable, even if the specific implementation of the mitigating decision is not.
- Later courts cite it for
- “while the general response to a breach must be foreseen, the particular way that a mitigating decision is implemented need not.” · 7 citing courts
- Where it cites § 10222
- “42 U.S.C. § 10222 (a)(1). Congress left open many of the terms of the contracts, but specifically dictated, inter alia, the deadline by which DOE must begin disposing of the SNF.”
- The case’s holding
- A statutory mandate to begin nuclear waste disposal creates a clear duty to act that cannot be excused by the absence of a permanent repository or interim storage program.
- Later courts cite it for
- “provides a potentially adequate remedy if doe fails to fulfill its obligations by the deadline.” · 6 citing courts
- Where it cites § 10222
- “42 U.S.C. § 10222 (a)(1). Section 302(a)(5) sets forth certain contractual obligations which DOE must assume: (5) Contracts entered into under this section shall provide that— (A) following commencement of operations of a repository, the Secretary shall take title to the [SNF]…”
- Later courts cite it for
- “gave doe the right to unilaterally postpone its unconditional obligations under article ii . . . even though it is cognizable as an avoidable delay and may, in some cases, be redressable under article ix.b.” · 2 citing courts
- Where it cites § 10222
- “42 U.S.C. § 10222 . Congress expressly mandated that, under the terms of the con- tracts, DOE accept SNF and HLW “beginning not later than January 31, 1998.”
- The case’s holding
- A plaintiff must prove that the type of damages is foreseeable as well as the fact of damage to recover consequential damages for breach of contract.
- Later courts cite it for
- “a plaintiff must show that the type of damages are foreseeable as well as the fact of damage.” · 3 citing courts
- Where it cites § 10222
- “42 U.S.C. § 10222 (a)(1). The Standard Con- tract required the owners of SNF and HLW to pay fees into the Nuclear Waste Fund, in exchange for which the DOE would begin to dispose of the SNF and HLW “not later than January 31, 1998.”
- The case’s holding
- Benefits resulting directly from mitigation efforts reduce contract damages and internal accounting complying with FERC regulations sufficiently demonstrates overhead costs with reasonable certainty.
- Later courts cite it for
- “by enhancing the racks to accommodate high-enrichment fuel assemblies, the plaintiffs mitigated the government's breach in a way that produced a benefit.” · 2 citing courts
Show all 118 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 16 cases in 2005. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
The 8 courts with the most citing cases, of 13 courts in all.
(a)(1)1 case
(a)(5)1 case
Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.