Skip to main content
U.S. CodeTitle 42Chapter 23— Development and Control of Atomic EnergyDivision A— Atomic EnergySubchapter XIII— General Authority of Commission

42 U.S.C. § 2214 (2026)

Repealed. Pub. L. 115–439, title I, § 101(b), Jan. 14, 2019, 132 Stat. 5568

Edition and currency
U.S. Code current through Pub. L. 119-102 (OLRC release point). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTU.S. Code current through Pub. L. 119-102 (OLRC release point) cited 1993–2019 18citing cases
At a glance

Courts have cited this section in 18 opinions since 1993.

[repealed]

The 18 cases that cite 42 U.S.C. § 2214 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 2214 2×cited by 24 cases
Where it cites § 2214
“See 42 U.S.C. § 2214 . 6 The NRC recovers the *1337 costs of its site-specific activities by charging licensees site-specific fees under 10 C.”
The case’s holding
A plaintiff must demonstrate causation by establishing what costs would have been incurred in a hypothetical non-breach world to recover damages for breach of contract.
Later courts cite it for
“insufficient as a matter of law to demonstrate that the new nrc rules were the result of the government breach.” · 3 citing courts
2
GREENConsol. Edison Co. of New York v. United States, 92 Fed. Cl. 466 (Fed. Cl. 2010).
cites § 2214 2×cited by 17 cases
The case’s holding
A partial breach of contract occurs when a government agency changes a fee structure in violation of existing agreements (finding that the change in the Part 171 fee structure was caused by the DOE’s partial breach).
Later courts cite it for
“these comments confirm the existence of a direct link between doe's breach and the nrc's 1999 fee change.” · 2 citing courts
3
GREENAlabama Power Co. v. United States, 119 Fed. Cl. 615 (Fed. Cl. 2014).
cites § 2214 2×cited by 15 cases
Where it cites § 2214
“2012) (citing 42 U.S.C. § 2214 ). It does so by levying a variety of annual fees — some are site-specific, and others are generic and industry-wide.”
The case’s holding
A plaintiff seeking contract damages must prove the government's breach substantially caused the claimed costs, and insufficient evidence of causation bars recovery of fee increases not shown to result from the breach.
Later courts cite it for
“the central issue here is whether plaintiffs can prove that the government's breach caused the increase in fees.” · 2 citing courts
4
GREENBoston Edison Co. v. United States, 658 F.3d 1361 (Fed. Cir. 2011).
cites § 2214 1×cited by 39 cases
Where it cites § 2214
“See 42 U.S.C. § 2214 (c)(2)(B). However, that "fee relief” is not relevant to Entergy’s damages award because it affected only the "surcharges” paid by operating facilities.”
The case’s holding
A non-breaching party cannot recover prospective damages for anticipated future nonperformance in a partial breach case until those costs are actually incurred.
Later courts cite it for
“a non-breaching plaintiff bears the burden of persuasion to establish both the costs that it incurred and the costs that it avoided as a result of a breach of contract.” · 5 citing courts
5
GREENWisconsin Elec. Power Co. v. United States, 90 Fed. Cl. 714 (Fed. Cl. 2009).
cites § 2214 1×cited by 24 cases
Where it cites § 2214
“42 U.S.C. § 2214 (c)(3). In the non-breach world, dry storage fees would have remained specific to those utilities with dry storage which would not have included WE.”
The case’s holding
A party may recover reasonable mitigation costs incurred to limit damages from a partial breach, where those costs were reasonably foreseeable, substantially caused by the breach, and proven with reasonable certainty.
Later courts cite it for
“would have occurred in 1999 even if doe had begun performance in 1998.” · 5 citing courts
6
GREENCano v. Everest Minerals Corp., 362 F. Supp. 2d 814 (W.D. Tex. 2005).
cites § 2214 1×cited by 18 cases
Where it cites § 2214
“42 U.S.C. § 2214 (hh). The Plaintiffs’ burden under Texas law is to prove to a reasonable degree of medical certainty, based on a reasonable medical probability and scientifically reliable evidence, that their exposure to ionizing radiation from the natural uranium ore and its…”
Later courts cite it for
“although the differential diagnosis technique is well accepted ... , a finding that all possible causes are causes does not appear to have gained general acceptance in the medical and scientific communities.” · 3 citing courts
7
GREENBoston Edison Co. v. United States, 93 Fed. Cl. 105 (Fed. Cl. 2010).
cites § 2214 1×cited by 14 cases
Where it cites § 2214
“1388 -298 to -299 (1990) (codified as amended at 42 U.S.C. § 2214 ). 23 In response, the NRC modified its fee recovery structure for both Part 170 specific-services fees and Part 171 generic fees to enable it to “more completely recover costs incurred by the Commission.”
Later courts cite it for
“by regulation, decommissioning funds may not be used for non-decommissioning related expenses, such as spent nuclear fuel storage.” · 1 citing court
8
GREENEntergy Gulf States, Inc. v. United States, 125 Fed. Cl. 678 (Fed. Cl. 2016).
cites § 2214 1×cited by 6 cases
Where it cites § 2214
“; 42 U.S.C. § 2214 (c)(3) (2012). In 1999, the NRC established a new fee under Part 171, the Spent Fuel Storage/Reactor Decommissioning Fee (“SFS/RD fee”).”
9
GREENAllied-Signal, Inc. v. U.S. Nuclear Regulatory Comm'n, 988 F.2d 146 (D.C. Cir. 1993).
cites § 2214 5×cited by 19 cases
Where it cites § 2214
“101-508, § 6101 (codified at 42 U.S.C. § 2214 ), and told the Commission to promulgate a rule apportioning the generic fees “fairly and equitably” among licensees.”
The case’s holding
An inadequately supported agency rule need not be vacated if the agency can reasonably justify its choice on remand and vacatur would cause disruptive consequences.
Later courts cite it for
“the decision whether to vacate depends on 'the seriousness of the order's deficiencies (and thus the extent of doubt whether the agency chose correctly) and the disruptive consequences of an interim change that may itself be changed.” · 98 citing courts
10
GREENSys. Fuels, Inc. v. United States, 125 Fed. Cl. 331 (Fed. Cl. 2016).
cites § 2214 1×cited by 3 cases
Where it cites § 2214
“; 42 U.S.C. § 2214 (c)(3) (2012). Prior to 1999, the NRC recovered its generic costs associated with spent fuel stored outside a spent fuel pool through an annual fee assessed under Part 171, but only on licensees that held a Part 72 license to store spent fuel outside of the…”
11
GREENElec. Welfare Trust Fund v. United States, 907 F.3d 165 (4th Cir. 2018).
cites § 2214 1×cited by 3 cases
Where it cites § 2214
“§ 136a(a) (authorizing the Secretary of Agriculture to prescribe fees to defray quarantine and inspection costs); 42 U.S.C. § 2214 (authorizing the Nuclear Regulatory Commission to assess and collect charges and fees); 31 U.”
12
GREENVelazquez v. UPMC Bedford Mem'l Hosp., 338 F. Supp. 2d 609 (W.D. Pa. 2004).
cites § 2214 1×cited by 6 cases
Later courts cite it for
“is not a proper basis for reconsideration.” · 4 citing courts
13
GREENEnergy Nw. v. United States, 115 Fed. Cl. 69 (Fed. Cl. 2014).
cites § 2214 1×cited by 6 cases
Where it cites § 2214
“See 42 U.S.C. § 2214 . To fulfill this requirement, the NRC collects fees from its licensees, including those described in Part 171.”
14
GREENEntergy Nuclear Indian Point 2, LLC v. United States, 121 Fed. Cl. 667 (Fed. Cl. 2015).
cites § 2214 1×cited by 5 cases
Where it cites § 2214
“The NRC modified its 10 C.F.R. Part 171 fee structure in 1999 to recover costs relating to its spent fuel storage and reactor decommissioning generic activities.”
Later courts cite it for
“the federal circuit did not hold that nrc fees may not be recovered, only that in each case the evidence must be evaluated to determine whether the plaintiff met its burden of proof.” · 2 citing courts
15
GREENJordan v. Erschen, 45 V.I. 247 (V.I. 2003).
cites § 2214 1×cited by 2 cases
Where it cites § 2214
“” 42 U.S.C. § 2214 (note). The court determined that because the legislature unambiguously declared retroactivity, the amendment applies.”
16
NO FLAGHoneywell Int'l Inc. v. United States, No. 18-249 (Fed. Cl. Feb. 25, 2019).
cites § 2214 4×
Where it cites § 2214
“2012) (citing 42 U.S.C. § 2214 ). It does so primarily through two types of fee assessments.”
17
NO FLAGEntergy Nuclear Generation Co. v. United States, No. 14-1248 (Fed. Cl. June 19, 2018).
cites § 2214 1×
Where it cites § 2214
“” 42 U.S.C. § 2214 (c)(2). The amount of those fees is set by the NRC via regulation.”
18
NO FLAGBoston Edison Co. v. United States, No. 2010-5136 (Fed. Cir. Sept. 28, 2011).
cites § 2214 1×
Where it cites § 2214
“See 42 U.S.C. § 2214 (c)(2)(B). However, that “fee relief” is not relevant to Entergy’s damages award because it affected only the “surcharges” paid by operating facilities.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199320062019

One bar per year. Tallest: 2 cases in 2010. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.10Fed. Cir.34th Cir.1D.C. Cir.1W.D. Pa.1W.D. Tex.1V.I.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments
Repealed. Pub. L. 115–439, title I, § 101(b), Jan. 14, 2019, 132 Stat. 5568
Versions

Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.