42 U.S.C. § 6804 (2026)

Funding, administrative, and judicial authorities of Secretary

Edition and currency
U.S. Code current through Pub. L. 119-102 (OLRC release point). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTU.S. Code current through Pub. L. 119-102 (OLRC release point)
The Secretary may—(1) fund (A) demonstration projects to improve electric utility load management procedures and (B) regulatory rate reform initiatives,(2) on request of a State, a utility regulatory commission, or of any participant in any proceeding before a State utility regulatory commission which relates to electric utility rates or rate design, intervene and participate in such proceeding, and(3) on request of any State, utility regulatory commission, or party to any action to obtain judicial review of an administrative proceeding in which the Secretary intervened or participated under paragraph (2), intervene and participate in such action.(Pub. L. 94–385, title II, § 204, Aug. 14, 1976, 90 Stat. 1143; Pub. L. 95–617, title I, § 143, Nov. 9, 1978, 92 Stat. 3134.)Editorial NotesAmendments

1978—Pub. L. 95–617 substituted “Secretary” for “Administrator”, meaning Administrator of the Federal Energy Administration in two places.

Enactment and amendments
(Pub. L. 94–385, title II, § 204, Aug. 14, 1976, 90 Stat. 1143; Pub. L. 95–617, title I, § 143, Nov. 9, 1978, 92 Stat. 3134.)
Amendment years (notes): 1978
Versions

Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.