42 U.S.C. § 7512a
Plan submissions and requirements
No later than 2 years from
No later than 2 years after
Within 2 years after
No later than 2 years after
Immediately after
No later than
No later than 2 years after
In the case of Moderate Areas with a design value greater than 12.7 ppm at the time of classification, no later than 2 years after
Each State in which all or part of a Serious Area is located shall, with respect to the Serious Area, make the submissions (other than those required under subsection (a)(1)(B) 1
Within 2 years after
In the case of Serious Areas in which stationary sources contribute significantly to carbon monoxide levels (as determined under rules issued by the Administrator), the State shall submit a plan revision within 2 years after
The Administrator may, on a case-by-case basis, waive any requirements that pertain to transportation controls, inspection and maintenance, or oxygenated fuels where the Administrator determines by rule that mobile sources of carbon monoxide do not contribute significantly to carbon monoxide levels in the area.
Within 6 months after
By
A demonstration under this paragraph shall be submitted in such form and manner, and shall contain such information and analysis, as the Administrator shall require. The Administrator shall determine whether or not a State’s demonstration is adequate within 90 days after the Administrator’s receipt of a demonstration which contains the information and analysis required by the Administrator.
If a State fails to submit a demonstration under paragraph (1) within the required period, or if the Administrator notifies the State that the State has not met the milestone, the State shall, within 9 months after such a failure or notification, submit a plan revision to implement an economic incentive and transportation control program as described in section 7511a(g)(4) of this title. Such revision shall be sufficient to achieve the specific annual reductions in carbon monoxide emissions set forth in the plan by the attainment date.
Each State in which there is located a portion of a single nonattainment area for carbon monoxide which covers more than one State (“multi-State nonattainment area”) shall take all reasonable steps to coordinate, substantively and procedurally, the revisions and implementation of State implementation plans applicable to the nonattainment area concerned. The Administrator may not approve any revision of a State implementation plan submitted under this part for a State in which part of a multi-State nonattainment area is located if the plan revision for that State fails to comply with the requirements of this subsection.
If any State in which there is located a portion of a multi-State nonattainment area fails to provide a demonstration of attainment of the national ambient air quality standard for carbon monoxide in that portion within the period required under this part the State may petition the Administrator to make a finding that the State would have been able to make such demonstration but for the failure of one or more other States in which other portions of the area are located to commit to the implementation of all measures required under this section (relating to plan submissions for carbon monoxide nonattainment areas). If the Administrator makes such finding, in the portion of the nonattainment area within the State submitting such petition, no sanction shall be imposed under section 7509 of this title or under any other provision of this chapter, by reason of the failure to make such demonstration.
Each State containing a carbon monoxide nonattainment area reclassified under section 7512(b)(2) of this title shall meet the requirements of subsection (b) of this section, as may be applicable to the area as reclassified, according to the schedules prescribed in connection with such requirements, except that the Administrator may adjust any applicable deadlines (other than the attainment date) where such deadlines are shown to be infeasible.
If the Administrator determines under section 7512(b)(2) of this title that the national primary ambient air quality standard for carbon monoxide has not been attained in a Serious Area by the applicable attainment date, the State shall submit a plan revision for the area within 9 months after the date of such determination. The plan revision shall provide that a program of incentives and requirements as described in section 7511a(g)(4) of this title shall be applicable in the area, and such program, in combination with other elements of the revised plan, shall be adequate to reduce the total tonnage of emissions of carbon monoxide in the area by at least 5 percent per year in each year after approval of the plan revision and before attainment of the national primary ambient air quality standard for carbon monoxide.
For provisions prohibiting Administrator of Environmental Protection Agency from requiring adoption or implementation by State of test-only I/M240 enhanced vehicle inspection and maintenance program as means of compliance with this section, with further provisions relating to plan disapproval and emissions reduction credits, see section 348 of Pub. L. 104–59, set out as a note under section 7511a of this title.