Revised Code of Washington homeSearch Washington
Wash. Rev. CodeTitle 39Chapter 39.08

Wash. Rev. Code § 39.08.065 (2025)

Notice to contractor condition to suit on bond when supplies are furnished to subcontractor

Edition and currency
laws through the 2025 session: 2026 session laws are not yet included. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2025 session: 2026 session laws are not yet included cited 1965–2013 13citing cases
At a glance

Courts have cited this section in 13 opinions since 1965.

The 13 cases that cite Wash. Rev. Code § 39.08.065 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENLRS Elec. Controls, Inc. v. Hamre Const., Inc., 107 P.3d 721 (Wash. 2005).
cites § 39.08.065 25×cited by 11 cases
Where it cites § 39.08.065
“¶ 1 The central question presented is whether preclaim notice requirements, generally necessary to recover on a materials claim against either a contractor's bond (RCW 39.08.065) or a retained percentage (RCW 60.”
2
GREENLRS Elec. Controls, Inc. v. Hamre Constr. Inc., 153 Wash. 2d 731 (2005).
cites § 39.08.065 25×cited by 12 cases
Where it cites § 39.08.065
“*734 ¶1 The central question presented is whether preclaim notice requirements, generally necessary to recover on a materials claim against either a contractor’s bond (RCW 39.08.065) or a retained percentage (RCW 60.”
3
REDLRS Elec. Controls, Inc. v. Hamre Constr., Inc., 82 P.3d 248 (Wash. Ct. App. 2004).
cites § 39.08.065 8×cited by 3 cases
Reversed by LRS Electric Controls, Inc. v. Hamre Const., Inc. (2005): the Washington Supreme Court's own opinion in this case.
Where it cites § 39.08.065
“It argued that RCW 39.08.065 1 and RCW 60.28.015 2 required Tyko to give notice of its intent to claim a material lien.”
Later courts cite it for
“but again, the language of the statute suggests to us that the materials, of concern, are those coming from some third party.” · 2 citing courts
4
GREENAustin v. C. v. Wilder & Co., 397 P.2d 1019 (Wash. 1965).
cites § 39.08.065 4×cited by 9 cases
Where it cites § 39.08.065
“This appeal brings into sharp focus the application of RCW 39.08.065 to the facts. RCW 39.08.065, omitting provisions not material here, provides: “Every person [Plaintiff Austin] .”
Later courts cite it for
“the prime contractor is protected against a suit by a materialman of a subcontractor unless the prime contractor has waived his rights under the statute, or, by his action, misled the materialman.” · 2 citing courts
5
GREENNat'l Concrete Cutting, Inc. v. Nw. GM Contractors, Inc., 107 Wash. App. 657 (Wash. Ct. App. 2001).
cites § 39.08.065 2×cited by 5 cases
Where it cites § 39.08.065
“Lumpkin asserted that National Concrete should be considered a supplier of materials required to file a preclaim notice under RCW 39.08.065. That provision states: Notice to contractor condition to suit on bond when supplies are furnished to subcontractor.”
6
GREENKeller Supply Co. v. Lydig Constr. Co., 789 P.2d 788 (Wash. Ct. App. 1990).
cites § 39.08.065 2×cited by 9 cases
Where it cites § 39.08.065
“) RCW 39.08.065. Recovery from retained percentage—Written notice to contractor of materials furnished.”
7
GREENBetter Fin. Solutions, Inc. v. Transtech Elec., Inc., 112 Wash. App. 697 (Wash. Ct. App. 2002).
cites § 39.08.065 1×cited by 12 cases
Where it cites § 39.08.065
“Northwest GM Contractors, 24 the issue presented was whether National Concrete was a supplier of materials to a public works project and therefore required to file a preclaim notice under RCW 39.08.065 or whether it was a supplier of labor and therefore not required to file such…”
Later courts cite it for
“bfs agrees to supply personnel to work under the client's supervision and control.” · 2 citing courts
8
GREENNat. Concrete Cutting v. Nw Gm Contractors, 27 P.3d 1239 (Wash. Ct. App. 2001).
cites § 39.08.065 2×cited by 4 cases
Where it cites § 39.08.065
“Lumpkin asserted that National Concrete should be considered a supplier of materials required to file a pre-claim notice under RCW 39.08.065. That provision states: Notice to contractor condition to suit on bond when supplies are furnished to subcontractor.”
Later courts cite it for
“including such articles which either actually have been incorporated into and become part of the building or have been delivered on the site for incorporation into the finished structure.” · 2 citing courts
9
NEUTRALCampbell Crane & Rigging Servs., Inc. v. Dynamic Int'l AK, Inc., 186 P.3d 1193 (Wash. Ct. App. 2008).
cites § 39.08.065 4×cited by 3 cases
Where it cites § 39.08.065
“No “Materials” for Incorporation into Project ¶14 BP argues that Campbell Crane’s role as a second-tier subcontractor supplying both materials and labor required Campbell Crane to give prelien notice.”
Later courts cite it for
“in an action brought against a performance bond where the surety contests a right to recover, denies the allegations in a complaint, and seeks dismissal of an action.” · 2 citing courts
10
GREENBetter Fin. Solutions, Inc. v. Transtech Elec., Inc., 51 P.3d 108 (Wash. Ct. App. 2002).
cites § 39.08.065 1×cited by 11 cases
Where it cites § 39.08.065
“Northwest GM Contractors, [24] the issue presented was whether National Concrete was a supplier of materials to a public works project and therefore required to file a pre-claim notice under RCW 39.08.065 or whether it was a supplier of labor and therefore not required to file…”
11
NEUTRALApex Glass & Sash, Inc. v. City of Seattle, 490 P.2d 885 (Wash. Ct. App. 1971).
cites § 39.08.065 2×cited by 3 cases
Where it cites § 39.08.065
“if the contract requires delivery at destination, title passes on tender there.”
12
REDLRS Elec. Controls, Inc. v. HAMRE CONST., INC., 82 P.3d 248 (Wash. Ct. App. 2004).
cites § 39.08.065 9×cited by 0 cases
Reversed by LRS Electric Controls, Inc. v. Hamre Const., Inc. (2005): the Washington Supreme Court's own opinion in this case.
Where it cites § 39.08.065
“Tyko then claimed against both the payment bond and the county's retainage for the balance due, $9,500, and ultimately sued on the claim.”
13
NO FLAGBncc, Inc. v. Access Elec. Supply, Inc., No. 68738-7 (Wash. Ct. App. June 17, 2013).
cites § 39.08.065 2×cited by 0 casesunpublished
Where it cites § 39.08.065
“BNCC filed a motion for summary judgment dismissal of all Access's claims against BNCC, arguing that Access had no privity of contract with BNCC and failed to provide preclaim notice as required by RCW 39.08.065. At a hearing on BNCC's motion for summary judgment, Access argued…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
196519892013

One bar per year. Tallest: 2 cases in 2001. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Wash. Ct. App.10Wash.3
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2025 session: 2026 session laws are not yet included. Syfert holds no earlier or later version of this section.

Revised Code of Washington Home  |  Search Washington  |  Search cases for this section  |  syfert.com