Revised Code of Washington

Wash. Rev. Code § 60.28.051 (2026)

Duties of disbursing officer upon completion of contract

✓ current as of May 2026
Find cases: SyfertCases citing this section WA-LEGapp.leg.wa.gov JustiaTitle on Justia CornellLII Search CasesGoogle Scholar
Upon completion of a contract, the state, county, or other municipal officer charged with the duty of disbursing or authorizing disbursement or payment of such contracts shall forthwith notify the department of revenue, the employment security department, and the department of labor and industries of the completion of contracts over thirty-five thousand dollars. Such officer shall not make any payment from the retained percentage fund or release any retained percentage escrow account to any person, until he or she has received from the department of revenue, the employment security department, and the department of labor and industries certificates that all taxes, increases, and penalties due from the contractor, and all taxes due and to become due with respect to such contract have been paid in full or that they are, in each department's opinion, readily collectible without recourse to the state's lien on the retained percentage.
[ 2009 c 432 s 8; 2007 c 210 s 2; 1992 c 223 s 4.]

Notes:

Report2009 c 432: See RCW 18.27.800.
Effective date1992 c 223: See note following RCW 39.76.011.
Waiver of rights, constructionApplication1992 c 223: See RCW 39.04.900 and 39.04.901.
Notes of Decisions
Cited in 3 cases, 2006–2020 · leading case: Evans & Son, Inc. v. City of Yakima, 136 Wash. App. 471 (Wash. Ct. App. 2006).
Evans & Son, Inc. v. City of Yakima, 136 Wash. App. 471 (Wash. Ct. App. 2006). “See RCW 60.28.051; RCW 39.12.040; RCW 60.28.010.”
Evans & Son, Inc. v. City of Yakima, 149 P.3d 691 (Wash. Ct. App. 2006). “See RCW 60.28.051; RCW 39.12.040; RCW 60.28.010.”
State Constr. Inc v. Hartford Fire Ins. Co. (Wash. Ct. App. 2020). · cites it 4× “” One of the key steps to closing out a public works contract, it maintains, is the filing of a “Notice of Completion of Public Works Contract” with the State, as required by RCW 60.28.051 ~ State Construction argues the City filed this notice on April 13, 2017, and that the…”