Revised Code of Washington
Wash. Rev. Code § 80.52.040 (2026)
Election approval required before issuance of bonds
✓ current as of May 2026
Find cases:
SyfertCases citing this section
WA-LEGapp.leg.wa.gov
JustiaTitle on Justia
CornellLII Search
CasesGoogle Scholar
No public agency or assignee of a public agency may issue or sell bonds to finance the cost of construction or the cost of acquisition of a major public energy project, or any portion thereof, unless it has first obtained authority for the expenditure of the funds to be raised by the sale of such bonds for that project at an election conducted in the manner provided in this chapter.
[ 1981 2nd ex.s. c 6 s 4 (Initiative Measure No. 394, approved November 3, 1981).]
Notes of Decisions
Cited in 3
cases, 1998–2015 · leading case: Concerned Ratepayers Ass'n v. Pub. Util. Dist. No. 1, 983 P.2d 635 (Wash. 1999).
Concerned Ratepayers Ass'n v. Pub. Util. Dist. No. 1, 983 P.2d 635 (Wash. 1999). “Smith and Wachter wanted to review the technical specifications in the IPS 10380 in order to determine whether the proposed power plant would be capable of generating more than 250-megawatts of power, thus necessitating a public vote under RCW 80.52.040. The main concern for the…”
Concerned Ratepayers Ass'n v. Pub. Util. Dist. No. 1, 968 P.2d 6 (Wash. Ct. App. 1998). “Because RCW 80.52.040 1 requires voter approval before a public agency may sell bonds to finance the construction of a public *222 energy project capable of generating more than 250 megawatts of electricity, CRA sought information that might show the project turbine’s generating…”
Cedar Grove Composting Inc., / X-app. v. City Of Marysville, / X-res. (Wash. Ct. App. 2015). “The citizens who formed the Concerned Ratepayers Ass'n sought to determine if the proposed power plant would be capable of generating more than 250 megawatts of power, thus necessitating a public vote under RCW 80.52.040. 59 Concerned Ratepayers. 138 Wn.”
Annotations are extracted automatically from the opinions in the
Syfert caselaw corpus and ranked by authority, recency, and
treatment. Dots show Syfertize treatment of the citing case itself.