California Codes homeSearch California
Cal. CodesEducation CodeTitle 1. General Education Code ProvisionsDivision 1. General Education Code ProvisionsPart 10.5. School Facilities

Cal. Education Code § 17406 (2026)

Edition and currency
leginfo export of Sept. 26, 2026 (applied Oct. 1, 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
VersionsThe text below is in force today and remains in effect only until July 1, 2027.
CURRENTleginfo export of Sept. 26, 2026 (applied Oct. 1, 2026) cited 2014–2023 13citing cases
At a glance

Courts have cited this section in 13 opinions since 2014, 1 of them in the last five years.

(a)(1)Notwithstanding Section 17417, the governing board of a school district may let, for a minimum rental of one dollar ($1) a year, to a person, firm, or corporation real property that belongs to the school district if the instrument by which this property is let requires the lessee therein to construct on the demised premises, or provide for the construction thereon of, a building or buildings for the use of the school district during the term of the lease, and provides that title to that building shall vest in the school district at the expiration of that term. The instrument may provide for the means or methods by which that title shall vest in the school district before the expiration of that term, and shall contain other terms and conditions as the governing board of the school district may deem to be in the best interest of the school district.

(2)An instrument created pursuant to paragraph (1) shall be awarded based on a competitive solicitation process to the proposer providing the best value to the school district, taking into consideration the proposer’s demonstrated competence and professional qualifications necessary for the satisfactory performance of the services required. Before awarding an instrument pursuant to this section, the governing board of the school district shall adopt and publish required procedures and guidelines for evaluating the qualifications of proposers that ensure the best value selections by the school district are conducted in a fair and impartial manner. These procedures and guidelines shall be mandatory for the school district when awarding an instrument pursuant to this section. The required procedures shall include, at a minimum, the following:

(A)The school district shall prepare a request for sealed proposals from qualified proposers. The school district shall include in the request for sealed proposals an estimate of price of the project, a clear, precise description of any preconstruction services that may be required and the facilities to be constructed, the key elements of the instrument to be awarded, a description of the format that proposals shall follow and the elements they shall contain, the standards the school district will use in evaluating proposals, the date on which proposals are due, and the timetable the school district will follow in reviewing and evaluating proposals.

(B)The school district shall give notice of the request for sealed proposals in the manner of notice provided in Section 20112 of the Public Contract Code and in a trade paper of general circulation published in the county where the project is located, with the latest notice published at least 10 days before the date for receipt of the proposals.

(C)A proposer shall be prequalified in accordance with subdivisions (b) to (m), inclusive, of Section 20111.6 of the Public Contract Code in order to submit a proposal. If used, electrical, mechanical, and plumbing subcontractors shall be subject to the same prequalification requirements for prospective bidders described in subdivisions (b) to (m), inclusive, of Section 20111.6 of the Public Contract Code, including the requirement for the completion and submission of a standardized prequalification questionnaire and financial statement that is verified under oath and is not a public record. These prequalification requirements shall be included in an instrument created pursuant to paragraph (1).

(D)The request for sealed proposals shall identify all criteria that the school district will consider in evaluating the proposals and qualifications of the proposers, including relevant experience, safety record, price proposal, and other factors specified by the school district. The price proposal shall include, at the school district’s discretion, either a lump-sum price for the instrument to be awarded or the proposer’s proposed fee to perform the services requested, including the proposer’s proposed fee to perform preconstruction services or any other work related to the facilities to be constructed, as requested by the school district. The request for proposals shall specify whether each criterion will be evaluated pass-fail or will be scored as part of the best value score, and whether proposers must achieve any minimum qualification score for award of the instrument under this section.

(E)For each scored criterion, the school district shall identify the methodology and rating or weighting system that will be used by the school district in evaluating the criterion, including the weight assigned to the criterion and any minimum acceptable score.

(F)Proposals shall be evaluated and the instrument awarded under this section in the following manner:

(i)All proposals received shall be reviewed to determine those that meet the format requirements and the standards specified in the request for sealed proposals.

(ii)The school district shall evaluate the qualifications of the proposers based solely upon the criteria and evaluation methodology set forth in the request for sealed proposals, and shall assign a best value score to each proposal. Once the evaluation is complete, all responsive proposals shall be ranked from the highest best value to the lowest best value to the school district.

(iii)The award of the instrument shall be made by the governing board of the school district to the responsive proposer whose proposal is determined, in writing by the governing board of the school district, to be the best value to the school district.

(iv)If the selected proposer refuses or fails to execute the tendered instrument, the governing board of the school district may award the instrument to the proposer with the second highest best value score if the governing board of the school district deems it to be for the best interest of the school district. If the second selected proposer refuses or fails to execute the tendered instrument, the governing board of the school district may award the instrument to the proposer with the third highest best value score if the governing board of the school district deems it to be for the best interest of the school district.

(v)Notwithstanding any other law, upon issuance of a contract award, the school district shall publicly announce its award, identifying the entity to which the award is made, along with a statement regarding the basis of the award. The statement regarding the school district’s contract award and the contract file shall provide sufficient information to satisfy an external audit.

(G)The governing board of the school district, at its discretion, may reject all proposals and request new proposals.

(3)Following the award of an instrument created pursuant to paragraph (1), and if the price proposal is not a lump sum for the instrument awarded, the successful proposer shall provide the school district with objectively verifiable information of its costs to perform the services requested under the instrument and shall select subcontractors as set forth in paragraph (4). Once any preconstruction services are completed and subcontractors are selected, and upon approval of the plans and specifications for work on the site by the Department of General Services’ Division of the State Architect, if required, the successful proposer and the school district shall finalize the price for the services to be provided under the instrument. The successful proposer shall provide the school district with written rationale for the price, and the school district shall approve or reject the final price at a public meeting before the successful proposer may proceed with any further work under the instrument. The contract file shall include documentation sufficient to support the final price determination.

(4)(A)The school district, in the request for sealed proposals, may identify specific types of subcontractors that must be included in the proposal. All subcontractors that are identified in the proposal shall be afforded the protections of the Subletting and Subcontracting Fair Practices Act (Chapter 4 (commencing with Section 4100) of Part 1 of Division 2 of the Public Contract Code).

(B)Following the award of an instrument created pursuant to paragraph (1) and for subcontractors not identified in the proposal, the successful proposer shall proceed as follows in awarding construction subcontracts with a value exceeding one-half of 1 percent of the price allocable to construction work:

(i)Provide public notice of availability of work to be subcontracted in accordance with the publication requirements applicable to the competitive bidding process of the school district, including a fixed date and time on which qualifications statements, bids, or proposals will be due.

(ii)Establish reasonable qualification criteria and standards.

(iii)Award the subcontract either on a best value basis or to the lowest responsible bidder. The process may include prequalification or short-listing. The process shall not apply to subcontractors listed in the original proposal. Subcontractors awarded construction subcontracts under this subdivision shall be afforded all the protections of the Subletting and Subcontracting Fair Practices Act (Chapter 4 (commencing with Section 4100) of Part 1 of Division 2 of the Public Contract Code).

(5)Paragraph (2) shall not preclude a school district from segregating the request for proposals into a request for qualifications, followed by a request for proposals with price information from the proposers deemed most qualified by the school district, provided that the procedures specified in paragraphs (2), (3), and (4) are otherwise followed.

(b)(1)Notwithstanding Sections 17297 and 17402, for purposes of using preconstruction services, a school district may enter into an instrument created pursuant to paragraph (1) of subdivision (a) before written approval by the Department of General Services’ Division of the State Architect only if the instrument provides that no work for which a contractor is required to be licensed in accordance with Article 5 (commencing with Section 7065) of Chapter 9 of Division 3 of the Business and Professions Code and for which Division of the State Architect approval is required can be performed before receipt of the required Division of the State Architect approval.

(2)This subdivision does not waive the requirements of Section 17072.30 or Section 17074.16, or any other applicable requirements of Chapter 12.5 (commencing with Section 17070.10) of Part 10.

(c)A rental of property that complies with subdivision (a) as it reads on the day that the lease is entered into shall be deemed to have thereby required the payment of adequate consideration for purposes of Section 6 of Article XVI of the California Constitution.

(d)(1)This subdivision shall apply to a project for the construction, alteration, repair, or improvement of any structure, building, or other improvement of any kind that was leased through an instrument pursuant to this section before July 1, 2015. If at any time the instrument is determined to be invalid by a court of competent jurisdiction because it fails to fall within the competitive bidding exception pursuant to paragraph (1) of subdivision (a), as it read on December 31, 2016, the contractor who entered into the instrument with the school district may be paid the reasonable cost, specifically excluding profit, of the labor, equipment, materials, and services furnished by the contractor before the date of the determination that the instrument is invalid if all of the following conditions, as determined by the court, are met:

(A)The contractor proceeded with construction, alteration, repair, or improvement based upon a good faith belief that the instrument was valid.

(B)The school district has reasonably determined that the work performed is satisfactory.

(C)Contractor fraud did not occur in the obtaining or performance of the instrument.

(D)The instrument does not otherwise violate state law related to the construction or leasing of public works of improvement.

(2)In no event shall payment to the contractor pursuant to this section exceed either of the following:

(A)The contractor’s costs as included in the instrument plus the cost of any approved change orders.

(B)The lease payments made, less profit, at the point in time the instrument is determined to be invalid by a court of competent jurisdiction.

(3)Notwithstanding paragraph (1), this subdivision shall not affect any protest and legal proceedings, whether contractual, administrative, or judicial, to challenge the award of the public works contract, nor affect any rights under Section 337.1 or 337.15 of the Code of Civil Procedure.

(e)This section shall become inoperative on July 1, 2027, and, as of January 1, 2028, is repealed, unless a later enacted statute, that becomes operative on or before January 1, 2028, deletes or extends the dates on which it becomes inoperative and is repealed.

The 13 cases that cite Cal. Education Code § 17406 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENLos Alamitos Unified Sch. Dist. v. Howard Contracting, Inc., 229 Cal. App. 4th 1222 (Ct. App. 2014).
cites § 17406 12×cited by 10 casesunpublished
Where it cites § 17406
“Introduction The primary issue presented by this appeal is a legal one: Does Education Code section 17406 exempt school districts from obtaining competitive bids when entering into what are known as “lease-leaseback” agreements to improve school property? We conclude the answer…”
Holding on this section
A school district may enter a lease-leaseback agreement for construction projects without competitive bidding under Education Code section 17406.
Later courts cite it for
“it owns the land to be leased; byrom-davey, the contractor for the project, agreed to construct the project for a guaranteed maximum price; and title to the site and all improvements made by the project will vest in the district at the end of the lease term.” · 3 citing courts
2
GREENCal. Taxpayers Action Network v. Taber Constr., Inc., 12 Cal. App. 5th 115 (Ct. App. 2017).
cites § 17406 2×cited by 19 cases
Where it cites § 17406
“First, "[t]he Attorney General interpreted an earlier version of Education Code section 17406 and concluded it exempted school district lease-leaseback arrangements from the competitive bidding process.”
3
GREENMcGee v. Balfour Beatty Constr., 247 Cal. App. 4th 235 (Ct. App. 2016).
cites § 17406 1×cited by 13 casesunpublished
Where it cites § 17406
“This case concerns the application of Education Code section 17406 (section 17406) which governs lease-leaseback construction agreements.”
Holding on this section
Lease-leaseback construction agreements are exempt from competitive bidding requirements under Education Code section 17406, but independent contractors may be subject to conflict of interest claims under Government Code section 1090.
Later courts cite it for
“the legislative history provided to us does not suggest the legislature intended to modify the statute to overrule the analysis in hub city , which was decided prior to the proposed amendment.” · 2 citing courts
4
GREENDavis v. Fresno Unified Sch. Dist., 237 Cal. App. 4th 261 (Ct. App. 2015).
cites § 17406 1×cited by 32 cases
Where it cites § 17406
“The construction was completed in 2014 pursuant to a lease-leaseback arrangement that Fresno Unified and Contractor contend is exempt from competitive bidding under Education Code section 17406.”
The case’s holding
A lease-leaseback arrangement qualifies for the competitive bidding exception only if it is a genuine lease including a financing component and provides for the district's use of the facilities.
Later courts cite it for
“apportioning money from a state fund and determining which schools are eligible to receive funding.” · 2 citing courts
5
NEUTRALDavis v. Fresno Unified Sch. Dist., 57 Cal. App. 5th 911 (Ct. App. 2020).
cites § 17406 23×cited by 0 cases
Where it cites § 17406
“On page 34, the following text is added to the end of footnote 15: The statutory interpretation of Education Code section 17406 adopted in Davis I is now law of the case, and we decline the invitation in Fresno Unified’s petition for rehearing to conclude that interpretation was…”
6
NEUTRALDavis v. Fresno Unified Sch. Dist., 57 Cal. App. 5th 911 (Ct. App. 2020).
cites § 17406 19×cited by 0 cases
Where it cites § 17406
“7 million contract for the construction of a middle school in violation of California’s competitive bidding requirements, the statutory and common law rules governing conflicts of interest, and Education Code sections 17406 and 17417.”
7
GREENMcGee v. Torrance Unified Sch. Dist., 49 Cal. App. 5th 814 (Ct. App. 2020).
cites § 17406 3×cited by 0 cases
Where it cites § 17406
“) Authorized by Education Code section 17406, lease-leaseback agreements are used to “contract[] for construction or improvement of school facilities.”
Later courts cite it for
“section 526a taxpayer claims alleging violations of government code section 1090 may still fall within the validation statutes.” · 2 citing courts
8
GREENLos Alamitos Unified etc. v. Howard Contracting, No. G049194 (Cal. Ct. App. Sept. 18, 2014).
cites § 17406 12×cited by 0 cases
Where it cites § 17406
“* * * INTRODUCTION The primary issue presented by this appeal is a legal one: Does Education Code section 17406 exempt school districts from obtaining competitive bids when entering into what are known as “lease-leaseback” agreements to improve school property? We conclude the…”
9
GREENDavis v. Fresno Unified Sch. Dist., 14 Cal. 5th 671 (2023).
cites § 17406 2×cited by 0 cases
Where it cites § 17406
“The deal was structured as a lease-leaseback arrangement under Education Code section 17406.”
Later courts cite it for
“an action under the validation statutes permits a public agency to obtain a judgment upholding its handling of an agency matter.” · 2 citing courts
10
GREENCal. Taxpayers Action Network v. Taber Constr., No. A145078 (Cal. Ct. App. May 31, 2017).
cites § 17406 5×cited by 0 cases
Where it cites § 17406
“Education Code section 17406 authorizes school districts to use lease-leaseback agreements in contracting for construction or improvement of school facilities.”
11
GREENMcGee v. Balfour Beatty Constr., No. B262850 (Cal. Ct. App. May 4, 2016).
cites § 17406 1×cited by 0 cases
Where it cites § 17406
“This is an appeal from the judgment of dismissal following the trial court’s order sustaining defendants’ demurrers without leave to amend.”
12
NEUTRALCal. Taxpayers Action Network v. Taber Constr., Inc., 42 Cal. App. 5th 824 (Ct. App. 2019).
cites § 17406 1×cited by 0 cases
Where it cites § 17406
“2 Education Code section 17406 authorizes school districts to use lease-leaseback agreements in contracting for construction or improvement of school facilities.”
13
NO FLAGMcGee v. Torrance U. Sch. Dist., No. B252570 (Cal. Ct. App. Jan. 23, 2015).
cites § 17406 1×cited by 0 casesunpublished
Where it cites § 17406
“) The court also rejected the argument that ―because a more specific statute must take precedence over a general statute, Education Code section 17417 takes precedence over Education Code section 17406.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
201420182023

One bar per year. Tallest: 3 cases in 2020. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Cal. Ct. App.12Cal.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: leginfo export of Sept. 26, 2026 (applied Oct. 1, 2026). Another version of this section is on file: see the note under the citation at the top of the page.

California Codes Home  |  Search California  |  Search cases for this section  |  syfert.com