Maurice W. Lichtman v. Off. of Pers. Mgmt., 835 F.2d 1427 (Fed. Cir. 1988). · Go Syfert
Maurice W. Lichtman v. Off. of Pers. Mgmt., 835 F.2d 1427 (Fed. Cir. 1988). Cases Citing This Book View Copy Cite
8 citation events (7 in the last 25 years) across 4 distinct courts.
Cited for
At page 1428 Determining statutory basis for awarding interest on delayed payments7 citing cases“such arguments have been unsuccessfully advanced many times before.”2 citing courts quote it
  • Manuel Lampon-Paz v. Off. of Pers. Mgmt., No. 17-2519 (3d Cir. Apr. 30, 2018).unpublished
    (holding that “there is no provision in law for accrual of interest when payment of annuity benefits is delayed)
  • Don J. Permoda v. Off. of Pers. Mgmt. (MSPB 2017).unpublished
    (denying a request for interest on a lump sum provided by OPM after the court found him entitled to annuity benefits OPM previously had denied because no provision of law permitted such interest)
  • Don J. Permoda v. Off. of Pers. Mgmt. (MSPB 2017).unpublished
    (denying a request for interest on a lump sum provided by OPM after the court found him entitled to annuity benefits OPM previously had denied because no provision of law permitted such interest)
  • Petersen v. Off. of Pers. Mgmt., 180 F. App'x 153 (Fed. Cir. 2006).unpublished
    “[i]n the absence of express congressional consent to the award of interest separate from a general waiver of immunity to suit, the United States is immune from an interest award”
  • Dist. of Columbia v. United States, 67 Fed. Cl. 292 (Fed. Cl. 2005).published 2 cites
    (finding that a statute discussing the functions of the OPM director to include the securing of “justice” did not allow for the payment of interest by OPM for delayed annuity payments because there was no express statuto…)
  • Hanna v. Off. of Pers. Mgmt., 53 F. App'x 103 (Fed. Cir. 2002).unpublished
    Mgmt., 835 F.2d 1427, 1428 (Fed.Cir.1988).
  • Grumman Data Sys. Corp. v. United States, 28 Fed. Cl. 803 (Fed. Cl. 1993).published
    While allowing recovery of protest costs may provide claimants additional stimulus to challenge improper contract awards, however, sovereign immunity “is not to be waived by policy arguments.” Lichtman v. Office of Personnel Management, 83…
Retrieving the full opinion text from the archive…
Maurice W. LICHTMAN, Petitioner,
v.
OFFICE OF PERSONNEL MANAGEMENT, Respondent
87-3433.
Court of Appeals for the Federal Circuit.
Jan 4, 1988.
Published opinion
835 F.2d 1427
1988 U.S. App. LEXIS 239
1988 WL 74
August G. Carloni, Los Angeles, Cal., for petitioner., Martha H. Degraff, Dept, of Justice, Washington, D.C., for respondent. With her on the brief were Richard K. Willard, Asst. Atty. Gen., David M. Cohen, Director, Robert A. Reutershan, Asst. Director, and Sheryl L. Floyd. Of counsel was Earl A. Sanders, Office of the General Counsel, Office of Personnel Management, Washington, D.C.
Davis, Bennett, Mayer.
Cited by 7 opinions  |  Published
BENNETT, Senior Circuit Judge.

DECISION

Maurice W. Lichtman appeals the decision of the Merit Systems Protection Board, 33 M.S.P.R. 580 (1987), affirming the denial by the Office of Personnel Management (OPM) of Mr. Lichtman’s claim for 8 percent compounded interest on the amount of the lump-sum settlement received by Mr. Lichtman following this court’s decision in Lichtman v. Office of Personnel Management, 785 F.2d 299 (Fed.Cir.1986) (Lichtman I), which held him to be entitled to annuity benefits previously denied by the OPM. We affirm.

[*1428] OPINION

This court’s previous decision expressly declined to decide whether interest could be recovered on the amount ultimately found to be due Mr. Lichtman because the issue “ha[d] not been adequately argued” in the prior appeal. Lichtman I, 785 F.2d at 303 n. 10. Thus, our silence on the issue should not and cannot be construed as then mandating anything with respect to interest. On remand following Lichtman I, the interest issue was decided in the negative by the OPM and the MSPB and has become the sole issue argued in this appeal.

As the OPM’s initial rejection of petitioner’s claim for interest points out, “[t]here is no provision in law for accrual of interest when payment of annuity benefits is delayed.” Nevertheless, petitioner asserts that this court’s language in Lichtman I that “[o]ur effort is to put Lichtman in the same position now as if he had received the lump-sum computation settlement plus the annuity payments, as he should have, in 1972” provides adequate basis upon which to base an award of interest. The petitioner also asserts that “basic fairness” and “equity” requires that payments delayed over 10 years should rightly be made with interest in order to compensate for the loss of the money that should have been received in 1972.

However, such arguments have been unsuccessfully advanced many times before. “In the absence of express congressional consent to the award of interest separate from a general waiver of immunity to suit, the United States is immune from an interest award.” Library of Congress v. Shaw, 478 U.S. 310, 106 S.Ct. 2957, 2961, 92 L.Ed.2d 250 (1986). As was stated by the Supreme Court in United States v. N.Y. Rayon Importing Co., 329 U.S. 654, 663, 67 S.Ct. 601, 606, 91 L.Ed. 577 (1947)—

[T]he immunity of the United States from liability for interest is not to be waived by policy arguments.... Courts lack the power to award interest against the United States on the basis of what they think is or is not sound policy. We reiterate that only express language in a statute or contract can justify the imposition of such interest.

See also Zumerling v. Marsh, 783 F.2d 1032, 1034 (Fed.Cir.1986); Fidelity Construction Co. v. United States, 700 F.2d 1379 (Fed.Cir.), cert. denied, 464 U.S. 826, 104 S.Ct. 97, 78 L.Ed.2d 103 (1983); United States v. Mescalero Apache Tribe, 518 F.2d 1309, 207 Ct.Cl. 369 (1975), cert. denied, 425 U.S. 911, 96 S.Ct. 1506, 47 L.Ed.2d 761 (1976); cf. Gevyn Construction Corp. v. United States, 827 F.2d 752 (Fed.Cir.1987).

At oral argument, counsel for petitioner attempted to find support for payment of prejudgment interest by the United States in the language of 5 U.S.C. Section 1103(a) where it is stated that the functions of the Director of the OPM include “securing ... justice in the functions of the Office.” We do not find the mention of “securing justice” to be express language allowing the payment of interest by OPM for delayed annuity payments. See United States v. Thayer-West Point Hotel Co., 329 U.S. 585, 589, 67 S.Ct. 398, 400, 91 L.Ed. 521 (1947) (the term “just compensation” does not constitute an express provision for interest). In fact, petitioner’s brief concedes that he “cannot expressly point to any applicable statute in which interest is specifically provided for” in the circumstances of this case. We agree. Therefore, the board was correct.

AFFIRMED.