(a) The Commission may obtain an injunction or other court order to prevent a violation of the provisions of—

(1) The Atomic Energy Act of 1954, as amended;

(2) Title II of the Energy Reorganization Act of 1974, as amended; or

(3) A regulation or order issued pursuant to those Acts.

(b) The Commission may obtain a court order for the payment of a civil penalty imposed under Section 234 of the Atomic Energy Act:

(1) For violations of—

(i) Sections 53, 57, 62, 63, 81, 82, 101, 103, 104, 107, or 109 of the Atomic Energy Act of 1954, as amended;

(ii) Section 206 of the Energy Reorganization Act;

(iii) Any rule, regulation, or order issued pursuant to the sections specified in paragraph (b)(1)(i) of this section;

(iv) Any term, condition, or limitation of any license issued under the sections specified in paragraph (b)(1)(i) of this section.

(2) For any violation for which a license may be revoked under section 186 of the Atomic Energy Act of 1954, as amended.

[57 FR 55075, Nov. 24, 1992]
Notes of Decisions
Cited in 1 case, 1973–1973 · leading case: Laurence Gage v. United States Atomic Energy Comm'n & United States of Am. Commonwealth Edison Co., Intervenor, 479 F.2d 1214 (D.C. Cir. 1973).
Laurence Gage v. United States Atomic Energy Comm'n & United States of Am. Commonwealth Edison Co., Intervenor, 479 F.2d 1214 (D.C. Cir. 1973). “See 10 C.F.R. § 50.110 . 22 . 10 C.F.R. §§ 2.”