Skip to main content
C.F.R.Title 10Chapter I—Nuclear Regulatory CommissionPart 52—Licenses, Certifications, And Approvals for Nuclear Power PlantsSubpart C—Combined Licenses

10 C.F.R. § 52.103 (2026)

Operation under a combined license

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1990–2013 3citing cases
At a glance

Courts have cited this section in 3 opinions since 1990.

(a) The licensee shall notify the NRC of its scheduled date for initial loading of fuel no later than 270 days before the scheduled date and shall notify the NRC of updates to its schedule every 30 days thereafter. Not less than 180 days before the date scheduled for initial loading of fuel into a plant by a licensee that has been issued a combined license under this part, the Commission shall publish notice of intended operation in the Federal Register. The notice must provide that any person whose interest may be affected by operation of the plant may, within 60 days, request that the Commission hold a hearing on whether the facility as constructed complies, or on completion will comply, with the acceptance criteria in the combined license, except that a hearing shall not be granted for those ITAAC which the Commission found were met under § 52.97(a)(2).

(b) A request for hearing under paragraph (a) of this section must show, prima facie, that—

(1) One or more of the acceptance criteria of the ITAAC in the combined license have not been, or will not be, met; and

(2) The specific operational consequences of nonconformance would be contrary to providing reasonable assurance of adequate protection of the public health and safety.

(c) The Commission, acting as the presiding officer, shall determine whether to grant or deny the request for hearing in accordance with the applicable requirements of 10 CFR 2.309. If the Commission grants the request, the Commission, acting as the presiding officer, shall determine whether during a period of interim operation there will be reasonable assurance of adequate protection to the public health and safety. The Commission's determination must consider the petitioner's prima facie showing and any answers thereto. If the Commission determines there is such reasonable assurance, it shall allow operation during an interim period under the combined license.

(d) The Commission, in its discretion, shall determine appropriate hearing procedures, whether informal or formal adjudicatory, for any hearing under paragraph (a) of this section, and shall state its reasons therefore.

(e) The Commission shall, to the maximum possible extent, render a decision on issues raised by the hearing request within 180 days of the publication of the notice provided by paragraph (a) of this section or by the anticipated date for initial loading of fuel into the reactor, whichever is later.

(f) A petition to modify the terms and conditions of the combined license will be processed as a request for action in accordance with 10 CFR 2.206. The petitioner shall file the petition with the Secretary of the Commission. Before the licensed activity allegedly affected by the petition (fuel loading, low power testing, etc.) commences, the Commission shall determine whether any immediate action is required. If the petition is granted, then an appropriate order will be issued. Fuel loading and operation under the combined license will not be affected by the granting of the petition unless the order is made immediately effective.

(g) The licensee shall not operate the facility until the Commission makes a finding that the acceptance criteria in the combined license are met, except for those acceptance criteria that the Commission found were met under § 52.97(a)(2). If the combined license is for a modular design, each reactor module may require a separate finding as construction proceeds.

(h) After the Commission has made the finding in paragraph (g) of this section, the ITAAC do not, by virtue of their inclusion in the combined license, constitute regulatory requirements either for licensees or for renewal of the license; except for the specific ITAAC for which the Commission has granted a hearing under paragraph (a) of this section, all ITAAC expire upon final Commission action in the proceeding. However, subsequent changes to the facility or procedures described in the final safety analysis report (as updated) must comply with the requirements in § 52.98(e) or (f), as applicable.

[72 FR 49517, Aug. 28, 2007, as amended at 89 FR 57721, July 16, 2024]
The 3 cases that cite 10 C.F.R. § 52.103 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 52.103 1×cited by 8 cases
Where it cites § 52.103
“ovide a concise statement of the alleged facts or expert opinions which support the requestor’s/petitioner’s position on the issue and on which the petition intends to rely at hearing, together with references to the specific sources and documents on which the request-…”
Later courts cite it for
“arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” · 2 citing courts
cites § 52.103 8×cited by 1 case
Superseded by Nuclear Information Resource Service v. Nuclear Regulatory Commission (1991): the Court of Appeals for the D.C. Circuit's own en banc opinion in this case.
Where it cites § 52.103
“We thus vacate 10 C.F.R. § 52.103 (b) and 10 C.F.R. § 52.103 (c); wé uphold the remainder of the regulations against petitioners’ various challenges.”
3
NEUTRALNuclear Info. Resource Serv. v. Nuclear Regulatory Comm'n, 928 F.2d 465 (D.C. Cir. 1991).
cites § 52.103 2×cited by 1 case
Where it cites § 52.103
“(2) Whether it is necessary or appropriate for us to reexamine our pre-Chevron holding in Union of Concerned Scientists v.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199020012013

One bar per year. Tallest: 1 case in 1990. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.C. Cir.21st Cir.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.