C.F.R. homeSearch C.F.R.
C.F.R.Title 13Chapter I—Small Business AdministrationPart 121—Small Business Size RegulationsSubpart A—Size Eligibility Provisions and Standards

13 C.F.R. § 121.406 (2026)

How does a small business concern qualify to provide manufactured products or other supply items under a small business set-aside, service-disabled veteran-owned small business, HUBZone, WOSB or EDWOSB, or 8(a) contract?

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1994–2026 10citing cases
At a glance

Courts have cited this section in 10 opinions since 1994, 2 of them in the last five years.

(a) General. In order to qualify as a small business concern for a small business set-aside, service-disabled veteran-owned small business set-aside or sole source contract, HUBZone set-aside or sole source contract, WOSB or EDWOSB set-aside or sole source contract, 8(a) set-aside or sole source contract, partial set-aside, or set aside of an order against a multiple award contract to provide manufactured products or other supply items, an offeror must either:

(1) Be the manufacturer or producer of the end item being procured (and the end item must be manufactured or produced in the United States); or

(2) Comply with the requirements of paragraph (b), (c) or (d) of this section as a nonmanufacturer, a kit assembler or a supplier under Simplified Acquisition Procedures.

(b) Nonmanufacturers. (1) A firm may qualify as a small business concern for a requirement to provide manufactured products or other supply items as a nonmanufacturer if it:

(i) Does not exceed 500 employees (or 150 employees for the Information Technology Value Added Reseller exception to NAICS Code 541519, which is found at § 121.201, footnote 18);

(ii) Is primarily engaged in the retail or wholesale trade and normally sells the type of item being supplied;

(iii) Takes ownership or possession of the item(s) with its personnel, equipment or facilities in a manner consistent with industry practice; and

(iv) Will supply the end item of a small business manufacturer, processor or producer made in the United States, or obtains a waiver of such requirement pursuant to paragraph (b)(5) of this section.

(2) For size purposes, there can be only one manufacturer of the end item being acquired. The manufacturer is the concern which, with its own facilities, performs the primary activities in transforming inorganic or organic substances, including the assembly of parts and components, into the end item being acquired. The end item must possess characteristics which, as a result of mechanical, chemical or human action, it did not possess before the original substances, parts or components were assembled or transformed. The end item may be finished and ready for utilization or consumption, or it may be semifinished as a raw material to be used in further manufacturing. Firms which perform only minimal operations upon the item being procured do not qualify as manufacturers of the end item. Firms that add substances, parts, or components to an existing end item to modify its performance will not be considered the end item manufacturer where those identical modifications can be performed by and are available from the manufacturer of the existing end item:

(i) SBA will evaluate the following factors in determining whether a concern is the manufacturer of the end item:

(A) The proportion of total value in the end item added by the efforts of the concern, excluding costs of overhead, testing, quality control, and profit;

(B) The importance of the elements added by the concern to the function of the end item, regardless of their relative value; and

(C) The concern's technical capabilities; plant, facilities and equipment; production or assembly line processes; packaging and boxing operations; labeling of products; and product warranties.

(ii) Firms that provide computer and other information technology equipment primarily consisting of component parts (such as motherboards, video cards, network cards, memory, power supplies, storage devices, and similar items) who install components totaling less than 50% of the value of the end item are generally not considered the manufacturer of the end item.

(3) The nonmanufacturer rule applies only to procurements that have been assigned a manufacturing or supply NAICS code, or the Information Technology Value Added Resellers (ITVAR) exception to NAICS code 541519. The nonmanufacturer rule does not apply to contracts that have been assigned a service (except for the ITVAR exception to NAICS code 541519), construction, or specialty trade construction NAICS code.

(4) The nonmanufacturer rule applies only to the supply component of a requirement classified as a manufacturing, supply, or ITVAR contract. If a requirement is classified as a service contract, but also has a supply component, the nonmanufacturer rule does not apply to the supply component of the requirement. The rental of an item(s) is a service and should be treated as such in the application of the nonmanufacturer rule and the limitation on subcontracting.

Example 1 to paragraph (b)(4).A procuring agency seeks to acquire computer integration and maintenance services. Included within that requirement, the agency also seeks to acquire some computer hardware. If the procuring agency determines that the principal nature of the procurement is services and classifies the procurement as a services procurement, the nonmanufacturer rule does not apply to the computer hardware portion of the requirement. This means that while a contractor must meet the applicable performance of work requirement set forth in § 125.6 for the services portion of the contract, the contractor does not have to supply the computer hardware of a small business manufacturer.Example 2 to paragraph (b)(4).A procuring agency seeks to acquire computer hardware, as well as computer integration and maintenance services. If the procuring agency determines that the principal nature of the procurement is for supplies and classifies the procurement as a supply procurement, the nonmanufacturer rule applies to the computer hardware portion of the requirement. A firm seeking to qualify as a small business nonmanufacturer must supply the computer hardware manufactured by a small business. Because the requirement is classified as a supply contract, the contractor does not have to meet the performance of work requirement set forth in § 125.6 for the services portion of the contract.

(5) The Administrator or designee may waive the requirement set forth in paragraph (b)(1)(iv) of this section under the following two circumstances:

(i) The contracting officer has determined that no small business manufacturer or processor reasonably can be expected to offer a product meeting the specifications (including period for performance) required by a particular solicitation and SBA reviews and accepts that determination; or

(ii) SBA determines that no small business manufacturer or processor of the product or class of products is available to participate in the Federal procurement market.

(6) The two waiver possibilities identified in paragraph (b)(5) of this section are called “individual” and “class” waivers respectively, and the procedures for requesting and granting them are contained in § 121.1204.

(7) SBA's waiver of the nonmanufacturer rule means that the firm can supply the product of any size business without regard to the place of manufacture. However, SBA's waiver of the nonmanufacturer rule has no effect on requirements external to the Small Business Act which involve domestic sources of supply, such as the Buy American Act or the Trade Agreements Act.

(c) The limitations on subcontracting (performance of work) requirements, the ostensible subcontracting rule, and the nonmanufacturer rule do not apply to small business set-aside acquisitions with an estimated value between the micro-purchase threshold and the simplified acquisition threshold (as both terms are defined in the FAR at 48 CFR 2.101).

(d) Multiple item acquisitions. (1) If at least 50% of the estimated contract value is composed of items that are manufactured by small business concerns, then a waiver of the nonmanufacturer rule is not required. There is no requirement that each and every item acquired in a multiple-item procurement be manufactured by a small business.

(2) If more than 50% of the estimated contract value is composed of items manufactured by other than small concerns, then a waiver is required. SBA may grant a contract specific waiver for one or more items in order to ensure that at least 50% of the value of the products to be supplied by the nonmanufacturer comes from domestic small business manufacturers or are subject to a waiver.

(3) If a small business is both a manufacturer of item(s) and a nonmanufacturer of other item(s), the manufacturer size standard should be applied.

(e) These requirements do not apply to small business concern subcontractors.

[61 FR 3286, Jan. 31, 1996; 61 FR 7986, Mar. 1, 1996, as amended at 65 FR 30863, May 15, 2000; 69 FR 29205, May 21, 2004; 76 FR 8252, Feb. 11, 2011; 78 FR 61132, Oct. 2, 2013; 81 FR 4469, Jan. 26, 2016; 81 FR 34259, May 31, 2016; 81 FR 48579, July 25, 2016; 83 FR 12851, Mar. 26, 2018; 84 FR 65661, Nov. 29, 2019; 85 FR 66182, Oct. 16, 2020; 88 FR 26201, Apr. 27, 2023]
The 10 cases that cite 13 C.F.R. § 121.406 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENRotech Healthcare Inc. v. United States, 71 Fed. Cl. 393 (Fed. Cl. 2006).
cites § 121.406 4×cited by 31 cases
Where it cites § 121.406
“(citing 13 C.F.R. § 121.406 (a-b)). Defendant points out that the procurement at issue in Empire Home Medical had been assigned a wholesale Standard Industrial Classification (SIC) code, which was used to describe both contracts for supplies and contracts for services, depending…”
The case’s holding
Under the non-manufacturer rule, a small business set-aside award may not be made to an offeror that will supply products made by large manufacturers when the procurement is for supplying manufactured products.
2
GREENRotech Healthcare Inc. v. United States, 118 Fed. Cl. 408 (Fed. Cl. 2014).
cites § 121.406 5×cited by 18 cases
Where it cites § 121.406
“However, after the 2006 Rotech holding, in 2011, the Small Business Administration (“SBA”) promulgated 13 C.F.R. § 121.406 , addressing the problem of mixed service and supply contracts.”
3
GREENFlexfab, L.L.C. v. United States, 424 F.3d 1254 (Fed. Cir. 2005).
cites § 121.406 1×cited by 174 cases
Where it cites § 121.406
“13 C.F.R. § 121.406 (b)(l)(iii) (2005). Flexfab apparently delivered all of the air-duct hose required under a contract awarded to Capital City for the supply of the hose.”
The case’s holding
A subcontractor is an intended third-party beneficiary only if the contract or the actions of an authorized contracting officer demonstrate an intent to benefit the subcontractor directly.
Later courts cite it for
“the intent of the parties to the contract is therefore the cornerstone of a claim for third-party beneficiary status.” · 8 citing courts
4
GREENColumbian Rope Co. v. West, Togo D., 142 F.3d 1313 (D.C. Cir. 1998).
cites § 121.406 2×cited by 38 cases
Where it cites § 121.406
“13 C.F.R. § 121.406 (b)(2) (1995). SBA revised its regulations in January 1996; the Manufacturer Rule can be found in its current form at 13 C.”
The case’s holding
A challenge to a contract award is moot when the contract is fully performed and neither injunctive nor declaratory relief can meaningfully affect the parties' rights.
Later courts cite it for
“a court declining to review an agency order on the ground of intervening mootness should vacate that order, at least when the mootness is a result of happenstance.” · 2 citing courts
5
GREENBlueStar Energy Servs., Inc. v. United States, 100 Fed. Cl. 607 (Fed. Cl. 2011).
cites § 121.406 4×cited by 3 cases
Where it cites § 121.406
“See 13 C.F.R. § 121.406 (b) (2011). Plaintiff challenged the manufacturing requirement in light of 13 C.”
6
GREENYork Telecom Corp. v. United States, 130 Fed. Cl. 186 (Fed. Cl. 2017).
cites § 121.406 3×cited by 2 cases
Where it cites § 121.406
“In addition, 13 C.F.R. § 121.406 (b) provides, in relevant part: (1) A firm may qualify as a small business concern for a requirement to provide manufactured products or other supply items as a nonmanufacturer if it: (i) Does not exceed 500 employees.”
cites § 121.406 1×cited by 3 cases
Where it cites § 121.406
“Southern Wipers may be able to comply with this element if it can satisfy the SBA's definition of “not dominant in field of operation” as set out in 13 C.F.R. § 121.406 (1994). 6 . The Trustee argues that Southern Wipers has failed to present evidence of its annual receipts.”
8
NO FLAGThird Coast Fresh Distrib., L.L.C., ASBCA No. 59696 (A.S.B.C.A. Apr. 6, 2016).
cites § 121.406 3×cited by 0 cases
Where it cites § 121.406
“The government terminated the contract for cause and appellant now seeks conversion to a termination for convenience, plus costs. The government has filed motions to dismiss the appeal for lack of jurisdiction and for failure to state a claim.”
9
NO FLAGDavinci Co. v. United States, No. 24-1238 (Fed. Cl. Aug. 7, 2025).
cites § 121.406 2×cited by 0 cases
Where it cites § 121.406
“So, on June 25, 2024, prior to issuing the Solicitation, the VA requested and then received a nonmanufacturing waiver from the SBA, thereby allowing the VA, under 13 C.F.R. § 121.406 (b)(7), to use a domestic reseller of foreign-origin Tamsulosin “without regard to the place of…”
10
NO FLAGRevelations Counseling & Consulting, LLC v. United States, No. 25-2169 (Fed. Cl. Apr. 17, 2026).
cites § 121.406 1×cited by 0 cases
Where it cites § 121.406
“677 , 689 (2023; see also 13 C.F.R. § 121.406 (b). Such a business concern is not disqualified from bidding on a small business set-aside contract so long as it “represent[s] that it will supply the product of a domestic small business manufacturer or processor, unless a waiver…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199420102026

One bar per year. Tallest: 1 case in 1994. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.6A.S.B.C.A.1D.C. Cir.1Fed. Cir.1Bankr. N.D. Ga.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com