(a) A person must use rated orders to obtain:

(1) Items which will be physically incorporated into other items to fill rated orders, including that portion of such items normally consumed, or converted into scrap or by-products, in the course of processing;

(2) Containers or other packaging materials required to make delivery of the finished items against rated orders;

(3) Services, other than contracts of employment, needed to fill rated orders; and

(4) MRO needed to produce the finished items to fill rated orders. However, for MRO, the priority rating used must contain the program identification symbol H7 along with the rating symbol contained on the customer's rated order. For example, a person in receipt of a rated order with a priority rating of DO-A3 rated order, who needs MRO, would place a rated order with a priority rating of DO-H7 rated order with the person's supplier.

(b) A person may use a rated order to replace inventoried items (including finished items) if such items were used to fill rated orders, as follows:

(1) The order must be placed within ninety (90) days of the date of use of the inventory.

(2) A DO rating symbol and the program identification symbol indicated on the customer's rated order must be used on the order. A DX rating symbol may not be used even if the inventory was used to fill a DX rated order.

(3) If the priority ratings on rated orders from one customer or several customers contain different program identification symbols, the rated orders may be combined. In this case, the program identification symbol H1 must be used (i.e., DO-H1).

(c) A person may combine DX and DO rated orders from one customer or several customers if the items covered by each level of priority are identified separately and clearly. If different program identification symbols are indicated on those rated orders of equal priority, the person must use the program identification symbol H1 (i.e., DO-H1 or DX-H1).

(d) Combining rated and unrated orders. (1) A person may combine rated and unrated order quantities on one purchase order provided that:

(i) The rated quantities are separately and clearly identified; and

(ii) The elements of a rated order, as required by § 700.12, are included on the order with the statement required in § 700.12(a)(4) modified to read in substance: “This purchase order contains rated order quantities certified for national defense use, and you are required to follow all the provisions of the Defense Priorities and Allocations System regulation (15 CFR part 700) as it pertains to the rated quantities.”

(2) A supplier must accept or reject the rated portion of the purchase order as provided in § 700.13 and give preferential treatment only to the rated quantities as required by this part. This part may not be used to give preferential treatment to the unrated portion of the order.

(3) Any supplier who believes that rated and unrated orders are being combined in a manner contrary to the intent of this regulation or in a fashion that causes undue or exceptional hardship may submit a request for adjustment or exception under § 700.80.

(e) A person may place a rated order for the minimum commercially procurable quantity even if the quantity needed to fill a rated order is less than that minimum. However, a person must combine rated orders as provided in paragraph (c) of this section, if possible, to obtain minimum procurable quantities.

(f) A person is not required to place a priority rating on an order for less than $125,000, or one half of the Simplified Acquisition Threshold (as established in the Federal Acquisition Regulation (FAR)) (see FAR section 2.101), whichever amount is greater, provided that delivery can be obtained in a timely fashion without the use of the priority rating.

[49 FR 30414, July 30, 1984. Redesignated at 54 FR 601, Jan. 9, 1989, as amended at 63 FR 31923, June 11, 1998; 79 FR 47566, Aug. 14, 2014; 89 FR 58972, July 22, 2024]
The 1 case that cites 15 C.F.R. § 700.17 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENArch Chemicals, Inc. v. United States, 64 Fed. Cl. 380 (Fed. Cl. 2005).
cites § 700.17 2×cited by 45 cases
Where it cites § 700.17
“3 (d); see also 15 C.F.R. § 700.17 . Failure to deliver rated orders on time can result in criminal penalties and fines.”
The case’s holding
The administrative record in a bid protest is limited to materials existing at the time of the challenged decision to prevent the use of post hoc rationalizations.
Later courts cite it for
“those created after-the-fact are suspect, as courts . . . recognize that they must reject 'post hoc rationalizations' as a basis for the agency action.” · 2 citing courts

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com