18 C.F.R. § 2.24

Project decommissioning at relicensing

Read at: eCFRecfr.gov CornellLII GovInfogovinfo.gov CasesGoogle Scholar

The Commission issued a statement of policy on project decommissioning at relicensing in Docket No. RM93-23-000 on December 14, 1994.

[60 FR 347, Jan. 4, 1995]
Notes of Decisions
Cited in 1 case, 1997–1997 · leading case: State of Wisconsin v. Fed. Energy Regulatory Comm'n, Kimberly-Clark Corp. & N.E.W. Hydro, Inc., Intervenors, 104 F.3d 462 (D.C. Cir. 1997).
State of Wisconsin v. Fed. Energy Regulatory Comm'n, Kimberly-Clark Corp. & N.E.W. Hydro, Inc., Intervenors, 104 F.3d 462 (D.C. Cir. 1997). “l (1995) (referenced in 18 C.F.R. § 2.24 ). 3 . While Wisconsin also contends that FERC's decision approving the transfers is unsupported by the evidence, it focuses on its lack of opportunity to examine and challenge the evidence.”