18 C.F.R. § 292.201
Scope
This subpart applies to the criteria for and manner of becoming a qualifying small power production facility and a qualifying cogeneration facility under sections 3(17)(C) and 3(18)(B), respectively, of the Federal Power Act, as amended by section 201 of the Public Utility Regulatory Policies Act of 1978 (PURPA).
Notes of Decisions
Cited in 9
cases (1 in the last 5 years), 1984–2024 · leading case: Californians For Renewable Energy v. Ca Puco, 922 F.3d 929 (9th Cir. 2019).
Californians For Renewable Energy v. Ca Puco, 922 F.3d 929 (9th Cir. 2019). “" 18 CFR §§ 292.201 & 292.203. FERC has authority to define the requirements for being a QF.”
Greensboro Lumber Co. v. Georgia Power Co., 643 F. Supp. 1345 (N.D. Ga. 1986). “"Quali *1372 tying facilities” are cogeneration and small power production facilities meeting the requirements of 18 C.F.R. §§ 292.201 through 292.207. 37 .”
Application of Wind Power Pac. Investors-Iii, 686 P.2d 831 (Haw. 1984). “1 The federal rules, 18 C.F.R. § 292.201 to § 292.207, implementing section 201 of the Public Utility Regulatory Policies Act of 1978, 16 U.”
Nassau Power Corp. v. Beard, 601 So. 2d 1175 (Fla. 1992). “See 18 C.F.R. § 292.201 -.211 (1991); Fla. Admin.”
Nassau Power Corp. v. Deason, 641 So. 2d 396 (Fla. 1994). “7 (citing 18 C.F.R. § 292.201 -.211 (1991); Fla.Admin.”
Vote Solar v. PSC, 2020 MT 213 (Mont. 2020). “18 C.F.R. §§ 292.201 , 292.203, 292.204. Small power QFs have a nameplate capacity of 80 megawatts (“MW”) or less and produce electric power from biomass, waste, or renewable resources such as wind, water, or solar energy.”
Vote Solar v. PSC (Mont. 2020). “18 C.F.R. §§ 292.201 , 292.203, 292.204. Small power QFs have a nameplate capacity of 80 megawatts (“MW”) or less and produce electric power from biomass, waste, or renewable resources such as wind, water, or solar energy.”
Bankston v. Alabama Pub. Serv. Comm'n (M.D. Ala. 2024). ““Qualifying facility means a cogeneration facility or a small power production facility that is a qualifying facility under” 18 C.F.R. §§ 292.201 through 292.211. 18 C.”
Entergy Texas, Inc.// Off. of Pub. Util. Couns. & Pub. Util. Comm'n of Texas v. Pub. Util. Comm'n of Texas & Texas Indus. Energy Consumers// Off. of Pub. Util. Couns. & Entergy Texas, Inc. (Tex. App. 2015). “13 Qualified Small Power Production Capacity shall be any capacity available from a small power production facility that qualifies under Subpart B of Part 292 of the FERC Regulations, 18 C.F.R. § 292.201 , et seq., as amended, or any successor provisions issued pursuant to…”