24 C.F.R. § 58.46

Time delays for exceptional circumstances

Read at: eCFRecfr.gov CornellLII GovInfogovinfo.gov CasesGoogle Scholar

The responsible entity must make the FONSI available for public comments for 30 days before the recipient files the RROF when:

(a) There is a considerable interest or controversy concerning the project;

(b) The proposed project is similar to other projects that normally require the preparation of an EIS; or

(c) The project is unique and without precedent.

Notes of Decisions
Cited in 1 case, 2000–2000 · leading case: Soc'y Hill Towers Owners' Assn. v. Rendell, 210 F.3d 168 (3rd Cir. 2000).
Soc'y Hill Towers Owners' Assn. v. Rendell, 210 F.3d 168 (3rd Cir. 2000). · cites it 3× “24 C.F.R. § 58.46 . While NEPA does not specifically address the EA process, the Council on Environmental Quality (“CEQ”) promulgated regulations for implementing NEPA that address this process and establish requirements for public participation.”