30 C.F.R. § 585.601

When must I submit my plans to BOEM?

Read at: eCFRecfr.gov CornellLII GovInfogovinfo.gov CasesGoogle Scholar

(a) You may submit your SAP anytime; however, your SAP must be submitted to and approved by BOEM before you conduct activities requiring a SAP under § 585.600(a)(1).

(b) You must submit your COP by the end of the preliminary period of your commercial lease in accordance with § 585.235.

(1) Your COP must contain sufficient data and information for BOEM to complete its reviews and NEPA analysis.

(2) BOEM may need to conduct additional reviews of your COP, including environmental analysis under NEPA, if significant new information becomes available from your site assessment and characterization activities or if you substantially revise your COP. As a result of the additional reviews, BOEM may require that you revise your COP.

(c) You must submit your GAP by the end of the preliminary period for your limited lease in accordance with § 585.236, or the preliminary period for your grant in accordance with § 585.303.

Notes of Decisions
Cited in 2 cases, 2017–2018 · leading case: Fisheries Survival Fund v. Jewell, 236 F. Supp. 3d 332 (D.D.C. 2017).
Fisheries Survival Fund v. Jewell, 236 F. Supp. 3d 332 (D.D.C. 2017). · cites it 2× “30 C.F.R. §§ 585.601 , 585.605. BOEM must then approve the SAP, reject it, or approve it with modifications.”
Fisheries Survival Fund v. Jewell (D.D.C. 2018). “NYAR-0046753; 30 C.F.R. §§ 585.601 , 585.605. If BOEM approves the Plan, Statoil will have five years to engage in site assessment—including conducting surveys and using towers or buoys to evaluate wind resources—and propose a Construction and Operations Plan, 30 C.”
Annotations are extracted automatically from the opinions in the Syfert caselaw corpus and ranked by authority, recency, and treatment. Dots show Syfertize treatment of the citing case itself.