30 C.F.R. § 707.11
Applicability
(a) Coal extraction which is an incidental part of government-financed construction is exempt from the Act and this chapter.
(b) Any person who conducts or intends to conduct coal extraction which does not satisfy paragraph (a) of this section shall not proceed until a permit has been obtained from the regulatory authority under a State, Federal or Federal lands program.
Notes of Decisions
Cited in 1
case, 1986–1986 · leading case: Darty Dev. Co. v. Off. of Surface Mining Reclamation & Enf't, 632 F. Supp. 627 (N.D. Ala. 1986).
Darty Dev. Co. v. Off. of Surface Mining Reclamation & Enf't, 632 F. Supp. 627 (N.D. Ala. 1986). “The parallel federal regulation provides that “[c]oal extraction which is an incidental part of government-financed construction is exempt from the Act____” 30 C.F.R. § 707.11 (a) (1985). It defines “government-financed construction” as .”
Annotations are extracted automatically from the opinions in the
Syfert caselaw corpus and ranked by authority, recency, and
treatment. Dots show Syfertize treatment of the citing case itself.