33 C.F.R. § 114.45

Applications, extensions of time

Read at: eCFRecfr.gov CornellLII GovInfogovinfo.gov CasesGoogle Scholar

Extensions of time to commence or complete construction of a bridge or remove a bridge that has been replaced as an element of a permitted bridge project must be submitted to, and received by the District Commander at least 30 days before the existing permit expires to allow the permit to remain in effect until the final agency action is taken.

(33 U.S.C. 401, 491, 525, 535; 49 CFR 1.46(c) (8), (9), (10), (q)) [CGD 76-144, 42 FR 28882, June 6, 1977]
Notes of Decisions
Cited in 1 case, 1985–1985 · leading case: Cianbro Corp. v. Jacksonville Transp. Auth., 473 So. 2d 209 (Fla. 1st DCA 1985).
Cianbro Corp. v. Jacksonville Transp. Auth., 473 So. 2d 209 (Fla. 1st DCA 1985). “Indeed, the Authority states only that "such an extension would likely be premature at this point," and that "any such extension request would likely result in extended administrative hearings and, perhaps, additional litigation.”
Annotations are extracted automatically from the opinions in the Syfert caselaw corpus and ranked by authority, recency, and treatment. Dots show Syfertize treatment of the citing case itself.