C.F.R.Title 40Chapter I—Environmental Protection AgencySubchapter D—Water ProgramsPart 122—Epa Administered Permit Programs: The National Pollutant Discharge Elimination SystemSubpart D—Transfer, Modification, Revocation and Reissuance, and Termination of Permits

40 C.F.R. § 122.64 (2026)

Termination of permits (applicable to State programs, see § 123.25)

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2010 1citing case
At a glance

Courts have cited this section in 1 opinion since 2010. The most litigated part is subsection (a) (1 case).

(a) The following are causes for terminating a permit during its term, or for denying a permit renewal application:

(1) Noncompliance by the permittee with any condition of the permit;

(2) The permittee's failure in the application or during the permit issuance process to disclose fully all relevant facts, or the permittee's misrepresentation of any relevant facts at any time;

(3) A determination that the permitted activity endangers human health or the environment and can only be regulated to acceptable levels by permit modification or termination; or

(4) A change in any condition that requires either a temporary or permanent reduction or elimination of any discharge or sludge use or disposal practice controlled by the permit (for example, plant closure or termination of discharge by connection to a POTW).

(b) The Director shall follow the applicable procedures in part 124 or part 22 of this chapter, as appropriate (or State procedures equivalent to part 124) in terminating any NPDES permit under this section, except that if the entire discharge is permanently terminated by elimination of the flow or by connection to a POTW (but not by land application or disposal into a well), the Director may terminate the permit by notice to the permittee. Termination by notice shall be effective 30 days after notice is sent, unless the permittee objects within that time. If the permittee objects during that period, the Director shall follow part 124 of this chapter or applicable State procedures for termination. Expedited permit termination procedures are not available to permittees that are subject to pending State and/or Federal enforcement actions including citizen suits brought under State or Federal law. If requesting expedited permit termination procedures, a permittee must certify that it is not subject to any pending State or Federal enforcement actions including citizen suits brought under State or Federal law. State-authorized NPDES programs are not required to use part 22 of this chapter procedures for NPDES permit terminations.

(c) Permittees that wish to terminate their permit must submit a Notice of Termination (NOT) to their permitting authority. If requesting expedited permit termination procedures, a permittee must certify in the NOT that it is not subject to any pending State or Federal enforcement actions including citizen suits brought under State or Federal law. As of December 21, 2025 or an EPA-approved alternative date (see 40 CFR 127.24(e) or (f)), all NOTs submitted by general permit covered facilities in compliance with this section must be submitted electronically by the permittee to the Director or initial recipient, as defined in 40 CFR 127.2(b), in compliance with this section and 40 CFR part 3 (including, in all cases, subpart D), § 122.22, and 40 CFR part 127. 40 CFR part 127 is not intended to undo existing requirements for electronic reporting. Prior to this date, and independent of 40 CFR part 127, the permittee may be required to report electronically if specified by a particular permit or if required to do so by State law.

[48 FR 14153, Apr. 1, 1983; 50 FR 6940, Feb. 19, 1985, as amended at 54 FR 18784, May 2, 1989; 65 FR 30909, May 15, 2000; 80 FR 64099, Oct. 22, 2015; 85 FR 69198, Nov. 2, 2020]
The 1 case that cites 40 C.F.R. § 122.64 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENMiccosukee Tribe of Indians of Florida v. United States, 706 F. Supp. 2d 1296 (S.D. Fla. 2010).
cites § 122.64 1×subsections: (a)cited by 1 case
Where it cites § 122.64
“[that] would have justified the application of different permit conditions” as a cause for “modification or termination”); see also 40 C.F.R. 122.64(a) (listing “causes for terminating a[n] [NPDES] permit during its term” and noting that an NPDES permit can be terminated if “the…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection
(a)1 case
Miccosukee Tribe of Indians of Florida v. United States, 706 F. Supp. 2d 1296 (S.D. Fla. 2010).“[that] would have justified the application of different permit conditions” as a cause for “modification or termination”); see also 40 C.F.R. 122.64(a) (listing “causes for terminating a[n] [NPDES] permit during its term” and noting that an NPDES permit can be terminated if “the…”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.