C.F.R. homeSearch C.F.R.
C.F.R.Title 40Chapter I—Environmental Protection AgencySubchapter D—Water ProgramsPart 130—Water Quality Planning and Management

40 C.F.R. § 130.5 (2026)

Continuing planning process

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2013–2015 3citing cases
At a glance

Courts have cited this section in 3 opinions since 2013.

(a) General. Each State shall establish and maintain a continuing planning process (CPP) as described under section 303(e)(3)(A)-(H) of the Act. Each State is responsible for managing its water quality program to implement the processes specified in the continuing planning process. EPA is responsible for periodically reviewing the adequacy of the State's CPP.

(b) Content. The State may determine the format of its CPP as long as the mininum requirements of the CWA and this regulation are met. The following processes must be described in each State CPP, and the State may include other processes at its discretion.

(1) The process for developing effluent limitations and schedules of compliance at least as stringent as those required by sections 301(b) (1) and (2), 306 and 307, and at least stringent as any requirements contained in applicable water quality standards in effect under authority of section 303 of the Act.

(2) The process for incorporating elements of any applicable areawide waste treatment plans under section 208, and applicable basin plans under section 209 of the Act.

(3) The process for developing total maximum daily loads (TMDLs) and individual water quality based effluent limitations for pollutants in accordance with section 303(d) of the Act and § 130.7(a) of this regulation.

(4) The process for updating and maintaining Water Quality Management (WQM) plans, including schedules for revision.

(5) The process for assuring adequate authority for intergovernmental cooperation in the implementation of the State WQM program.

(6) The process for establishing and assuring adequate implementation of new or revised water quality standards, including schedules of compliance, under section 303(c) of the Act.

(7) The process for assuring adequate controls over the disposition of all residual waste from any water treatment processing.

(8) The process for developing an inventory and ranking, in order of priority of needs for construction of waste treatment works required to meet the applicable requirements of sections 301 and 302 of the Act.

(9) The process for determining the priority of permit issuance.

(c) Regional Administrator review. The Regional Administrator shall review approved State CPPs from time to time to ensure that the planning processes are consistent with the Act and this regulation. The Regional Administrator shall not approve any permit program under Title IV of the Act for any State which does not have an approved continuing planning process.

The 3 cases that cite 40 C.F.R. § 130.5 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENOhio Valley Env't Coalition, Inc. v. McCarthy, 313 F.R.D. 10 (S.D. W. Va. 2015).
cites § 130.5 2×cited by 19 cases
Where it cites § 130.5
“§ 1313 (e) (plans for navigable waters include effluent limitations); see also 40 C.F.R. § 130.5 . . See W. Va. Code § 22-11-6 ("water quality standards themselves shall not be considered 'effluent standards or limitation' .”
Later courts cite it for
“require expending additional court resources without a corresponding benefit attainable only by intervention rather than amicus participation.” · 1 citing court
2
cites § 130.5 1×cited by 10 cases
Where it cites § 130.5
“40 C.F.R. § 130.5 (a). “In designating uses of a water body and the appropriate criteria for those uses, the State shall take into consideration the water quality standards of downstream waters and shall ensure that its water quality standards provide for the attainment and…”
3
NO FLAGEl Dorado Chem. Co. v. United States Env't Prot. Agency, 960 F. Supp. 2d 838 (W.D. Ark. 2013).
cites § 130.5 2×cited by 0 cases
Where it cites § 130.5
“40 C.F.R. § 130.5 (b)(6). The CPP, once established, must be reviewed and approved by EPA to ensure consistency with the CWA.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
201320142015

One bar per year. Tallest: 1 case in 2013. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
W.D. Ark.18th Cir.1S.D.W. Va1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com