40 C.F.R. § 60.60
Applicability and designation of affected facility
(a) The provisions of this subpart are applicable to the following affected facilities in portland cement plants: Kiln, clinker cooler, raw mill system, finish mill system, raw mill dryer, raw material storage, clinker storage, finished product storage, conveyor transfer points, bagging and bulk loading and unloading systems.
(b) Any facility under paragraph (a) of this section that commences construction or modification after August 17, 1971, is subject to the requirements of this subpart.
Notes of Decisions
Cited in 1
case, 1978–1978 · leading case: ASARCO Inc. v. Env't Prot. Agency, 578 F.2d 319 (D.C. Cir. 1978).
ASARCO Inc. v. Env't Prot. Agency, 578 F.2d 319 (D.C. Cir. 1978). “” 40 C.F.R. § 60.60 (1975). 9 The “bubble concept” appeared first in proposals from the nonferrous smelting industry and the Department of Commerce (DOC) beginning in December 1972.”
Annotations are extracted automatically from the opinions in the
Syfert caselaw corpus and ranked by authority, recency, and
treatment. Dots show Syfertize treatment of the citing case itself.