41 C.F.R. § 50-201.1 (2026)
The Walsh-Healey Public Contracts Act
Edition and currency
Other sources
Courts have cited this section in 2 opinions since 1973.
The Walsh-Healey Public Contracts Act, as amended (41 U.S.C. 35-45), hereinafter referred to as the Act, was enacted “to provide conditions for the purchase of supplies and the making of contracts by the United States.” It is not an act of general applicability to industry. The Supreme Court has described it as an instruction by the Government to its agents who were selected and granted final authority to fix the terms and conditions under which the Government will permit goods to be sold to it. Its purpose, according to the Supreme Court “was to impose obligations upon those favored with Government business and to obviate the possibility that any part of our tremendous national expenditures would go to forces tending to depress wages and purchasing power and offending fair social standards of employment.” (“Perkins v. Lukens Steel Co.,” 310 U.S. 113, 128 (1940); “Endicott Johnson Corp. v. Perkins,” 317 U.S. 501 (1943).) To this end, the Act requires those who enter into contracts to perform Government work subject to its terms to adhere to specifically prescribed representations and stipulations as set forth in 41 CFR 50-201.1 pertaining to qualifications of contractors, minimum wages, overtime pay, safe and sanitary working conditions of workers employed on the contract, the use of child labor or convict labor on the contract work, and the enforcement of such provisions. Except as otherwise specifically provided, these representations and stipulations are required to be included in every contract “for the manufacture or furnishing of materials, supplies, articles, and equipment in any amount exceeding $10,000” which is made and entered into by an agency of the United States or other entity as designated in section 1 of the Act, hereinafter referred to as “contracting agency.” Contractors performing work subject to the Act thus “enter into competition to obtain Government business on terms of which they are fairly forwarned by inclusion in the contract.” (“Endicott Johnson Corp. v. Perkins, supra,” 317 U.S. at 507.) The Act also provides for enforcement of the required representations and stipulations by various methods. Certain exemptions from the application of the Act are provided in section 9 of the statute. Other exemptions, variations, and tolerances may be provided under section 6 of the statute by the Secretary of Labor or the President.
- Where it cites § 50-201.1
- “§§ 35-45 (1970), and the regulations issued thereunder by the Secretary of Labor, 41 C.F.R. §§ 50-201.1 to 50-210.1 (1977), and that these violations amounted to negligence per se.”
- Where it cites § 50-201.1
- “§ 35; 41 CFR § 50-201.1 . Deliveries under the contract were to be made in 55 gallon steel drums from the Beaumont plant.”
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.