C.F.R.Title 47Chapter I—Federal Communications CommissionSubchapter A—GeneralPart 1—Practice and ProcedureSubpart J—Pole Attachment Complaint Procedures

47 C.F.R. § 1.1410 (2026)

Use of presumptions in calculating the space factor

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1993–2023 4citing cases
At a glance

Courts have cited this section in 4 opinions since 1993, 1 of them in the last five years.

With respect to the formulas referenced in § 1.1406(d)(1) and (d)(2), the space occupied by an attachment is presumed to be one foot. The amount of usable space is presumed to be 13.5 feet. The amount of unusable space is presumed to be 24 feet. The pole height is presumed to be 37.5 feet. These presumptions may be rebutted by either party.

[83 FR 44841, Sept. 4, 2018]
The 4 cases that cite 47 C.F.R. § 1.1410 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENAm. Elec. Power Serv. Corp. v. Fed. Commc'ns Comm'n, 708 F.3d 183 (D.C. Cir. 2013).
cites § 1.1410 2×cited by 8 cases
Where it cites § 1.1410
“” 47 C.F.R. § 1.1410 (a)(3). The Commission argues that petitioners have waived their challenge by failing to raise the issue before the agency, but under United Church of Christ v.”
Later courts cite it for
“means (within its domain) that a 'reasonable agency interpretation prevails.” · 2 citing courts
2
GREENGreater Media, Inc. v. Dep't of Pub. Utils., 614 N.E.2d 632 (Mass. 1993).
cites § 1.1410 1×cited by 16 cases
Where it cites § 1.1410
“” 47 C.F.R. § 1.1410 (c) (1991). 18 Greater Media contends that, since the department is required to “determine and enforce reasonable rates,” 19 it should have granted refunds back to 1984 when the rates were first applied.”
3
GREENPub. Serv. Co. v. Fed. Commc'ns Comm'n, 328 F.3d 675 (D.C. Cir. 2003).
cites § 1.1410 1×cited by 1 case
Where it cites § 1.1410
“It simply decided that an agreement’s rate (unauthorized attachment charges), term (application to drop poles), and condition (concerning credits for overpayments) were unjust and unreasonable, and authorized modifications pursuant to 47 C.F.R. § 1.1410 . 3 Moreover, if there…”
4
NO FLAGVerizon PA LLC v. PA PUC, No. 521 & 530 C.D. 2021 (Pa. Commw. Ct. Sept. 21, 2023).
cites § 1.1410 4×cited by 0 cases
Where it cites § 1.1410
“4 (a) (incorporating 47 C.F.R. §1.1410 ). The PUC incorrectly rejected FirstEnergy’s evidence rebutting the presumptive inputs for calculating the New Telecom Rate simply because the evidence was prepared for litigation.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199320082023

One bar per year. Tallest: 1 case in 1993. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.C. Cir.2Mass.1Pa. Commw. Ct.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com