C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter B—Acquisition PlanningPart 11—Describing Agency NeedsSubpart 11.5—Liquidated Damages

48 C.F.R. § 11.502 (2026)

11.502 Procedures.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2015 1citing case
At a glance

Courts have cited this section in 1 opinion since 2015.

(a) Include the applicable liquidated damages clause and liquidated damages rates in solicitations when the contract will contain liquidated damages provisions.

(b) Construction contracts with liquidated damages provisions must describe the rate(s) of liquidated damages assessed per day of delay. The rate(s) should include the estimated daily cost of Government inspection and superintendence. The rate(s) should also include an amount for other expected expenses associated with delayed completion such as—

(1) Renting substitute property; or

(2) Paying additional allowance for living quarters.

The 1 case that cites 48 C.F.R. § 11.502 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENK-Con Bldg. Sys., Inc. v. United States, 778 F.3d 1000 (Fed. Cir. 2015).
cites § 11.502 1×cited by 145 cases
Where it cites § 11.502
“203-04 (contracting officer tabulating various costs); see also 48 C.F.R. § 11.502 (b) (requiring that rates in “[c]onstruetion contracts with liquidated damages provisions .”
The case’s holding
Jurisdiction under the Contract Disputes Act requires that a claim meeting specific requirements be submitted to the contracting officer and that the officer issue a final decision on that claim.
Later courts cite it for
“should treat requests as involving separate claims if they either request different remedies (whether monetary or non-monetary) or assert grounds that are materially different from each other factually or legally.” · 13 citing courts

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com