C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter C—Contracting Methods and Contract TypesPart 15—Contracting By NegotiationSubpart 15.2—Solicitation and Receipt of Proposals and Information

48 C.F.R. § 15.209 (2026)

15.209 Solicitation provisions and contract clauses.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2006–2010 2citing cases
At a glance

Courts have cited this section in 2 opinions since 2006.

When contracting by negotiation—

(a) The contracting officer shall insert the provision at 52.215-1, Instructions to Offerors—Competitive Acquisition, in all competitive solicitations where the Government intends to award a contract without discussions.

(1) If the Government intends to make award after discussions with offerors within the competitive range, the contracting officer shall use the basic provision with its Alternate I.

(2) If the Government would be willing to accept alternate proposals, the contracting officer shall alter the basic clause to add a paragraph (c)(9) substantially the same as Alternate II.

(b)(1) Except as provided in paragraph (b)(2) of this section, the contracting officer shall insert the clause at 52.215-2, Audit and Records-Negotiation (10 U.S.C. 3841, 41 U.S.C. 4706, and Audit Requirements in the OMB Uniform Guidance at 2 CFR part 200, subpart F) , in solicitations and contracts except those for—

(i) Acquisitions not exceeding the simplified acquisition threshold;

(ii) The acquisition of utility services at rates not exceeding those established to apply uniformly to the general public, plus any applicable reasonable connection charge; or

(iii) The acquisition of commercial products or commercial services exempted under 15.403-1.

(2)(i) When using funds appropriated or otherwise made available by the American Recovery and Reinvestment Act of 2009 (Pub. L. 111-5)—

(A) The exceptions in paragraphs (b)(1)(i) through (b)(1)(iii) are not applicable; and

(B) Use the clause with its Alternate I.

(ii)(A) In the case of a bilateral contract modification that will use funds appropriated or otherwise made available by the American Recovery and Reinvestment Act of 2009, the contracting officer shall specify applicability of Alternate I to that modification.

(B) In the case of a task- or delivery-order contract in which not all orders will use funds appropriated or otherwise made available by the American Recovery and Reinvestment Act of 2009, the contracting officer shall specify the task or delivery orders to which Alternate I applies.

(3) For cost-reimbursement contracts with State and local Governments, educational institutions, and other nonprofit organizations, the contracting officer shall use the clause with its Alternate II.

(4) When the head of the agency has waived the examination of records by the Comptroller General in accordance with 25.1001, use the clause with its Alternate III.

(c) When issuing a solicitation for information or planning purposes, the contracting officer shall insert the provision at 52.215-3, Request for Information or Solicitation for Planning Purposes, and clearly mark on the face of the solicitation that it is for information or planning purposes.

(d) [Reserved]

(e) The contracting officer shall insert the provision at 52.215-5, Facsimile Proposals, in solicitations if facsimile proposals are authorized (see 15.203(d)).

(f) The contracting officer shall insert the provision at 52.215-6, Place of Performance, in solicitations unless the place of performance is specified by the Government.

(g) [Reserved]

(h) The contracting officer shall insert the clause at 52.215-8, Order of Precedence—Uniform Contract Format, in solicitations and contracts using the format at 15.204.

[62 FR 51230, Sept. 30, 1997, as amended at 63 FR 9055, Feb. 23, 1998; 63 FR 58589, Oct. 30, 1998; 64 FR 72418, Dec. 27, 1999; 69 FR 76346, Dec. 20, 2004; 72 FR 27384, May 15, 2007; 74 FR 14648, Mar. 31, 2009; 75 FR 34281, June 16, 2010; 79 FR 24201, Apr. 29, 2014; 81 FR 45852, July 14, 2016; 86 FR 3687, Jan. 14, 2021; 86 FR 61025, Nov. 4, 2021; 87 FR 73897, Dec. 1, 2022]
The 2 cases that cite 48 C.F.R. § 15.209 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENA & D Fire Prot., Inc. v. United States, 72 Fed. Cl. 126 (Fed. Cl. 2006).
cites § 15.209 1×cited by 272 cases
Where it cites § 15.209
“209(a), 48 C.F.R. § 15.209 (a) (2005), and FAR 15.”
The case’s holding
A bidder lacks standing to protest a procurement if its bid is nonresponsive due to the failure to submit a required bid bond.
Later courts cite it for
“whether, given all the disputed and undisputed facts, a party has met its burden of proof based on the evidence in the record.” · 177 citing courts
2
GREENBannum, Inc. v. United States, 96 Fed. Cl. 364 (Fed. Cl. 2010).
cites § 15.209 1×cited by 1 case
Where it cites § 15.209
“19 See 48 C.F.R. § 15.209 (a)(2) (“If the Government would be willing to accept alternate proposals, the contracting officer shall alter the basic clause to add a paragraph (e)(9)[.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com