C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter C—Contracting Methods and Contract TypesPart 15—Contracting By NegotiationSubpart 15.4—Contract Pricing

48 C.F.R. § 15.405 (2026)

15.405 Price negotiation.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 ACTIVE · 1 IN 5Y cited 2012–2021 3citing cases
At a glance

Courts have cited this section in 3 opinions since 2012, 1 of them in the last five years. The most litigated part is subsection (a) (1 case).

(a) The purpose of performing cost or price analysis is to develop a negotiation position that permits the contracting officer and the offeror an opportunity to reach agreement on a fair and reasonable price. A fair and reasonable price does not require that agreement be reached on every element of cost, nor is it mandatory that the agreed price be within the contracting officer's initial negotiation position. Taking into consideration the advisory recommendations, reports of contributing specialists, and the current status of the contractor's purchasing system, the contracting officer is responsible for exercising the requisite judgment needed to reach a negotiated settlement with the offeror and is solely responsible for the final price agreement. However, when significant audit or other specialist recommendations are not adopted, the contracting officer should provide rationale that supports the negotiation result in the price negotiation documentation.

(b) The contracting officer's primary concern is the overall price the Government will actually pay. The contracting officer's objective is to negotiate a contract of a type and with a price providing the contractor the greatest incentive for efficient and economical performance. The negotiation of a contract type and a price are related and should be considered together with the issues of risk and uncertainty to the contractor and the Government. Therefore, the contracting officer should not become preoccupied with any single element and should balance the contract type, cost, and profit or fee negotiated to achieve a total result—a price that is fair and reasonable to both the Government and the contractor.

(c) The Government's cost objective and proposed pricing arrangement directly affect the profit or fee objective. Because profit or fee is only one of several interrelated variables, the contracting officer shall not agree on profit or fee without concurrent agreement on cost and type of contract.

(d) If, however, the contractor insists on a price or demands a profit or fee that the contracting officer considers unreasonable, and the contracting officer has taken all authorized actions (including determining the feasibility of developing an alternative source) without success, the contracting officer shall refer the contract action to a level above the contracting officer. Disposition of the action should be documented.

The 3 cases that cite 48 C.F.R. § 15.405 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENCBY Design Builders v. United States, 105 Fed. Cl. 303 (Fed. Cl. 2012).
cites § 15.405 1×cited by 85 cases
Where it cites § 15.405
“” 48 C.F.R. § 15.405 (b)(2011). The Federal Circuit has recognized that “[p]rice (or cost) must always be a ‘factor in an agency’s decision to award a contract,” and that in a tradeoff analysis the importance of price “must not be discounted to such a degree that it effectively…”
The case’s holding
The level of deference applied under the arbitrary and capricious standard of review remains unchanged when an agency implements a recommendation from the Government Accountability Office.
Later courts cite it for
“since the amount of deference given to an agency decision under the 'arbitrary and capricious' standard of review does not change when gao denies a protest of the decision, or when gao sustains a protest but its recommendation is not followed, it is hard to see how this deference would be altered by an agency's decision to follow a gao recommendation.” · 1 citing court
2
GREENUnited States ex rel. Thomas v. Siemens AG, 991 F. Supp. 2d 540 (E.D. Pa. 2014).
cites § 15.405 2×cited by 10 cases
Where it cites § 15.405
“” 48 C.F.R. § 15.405 (a), (b). The contracting officer’s objective is to get prices and discounts that are “comparable” to the vendor’s best price.”
3
NO FLAGSilbersher v. Janssen Biotech Inc., No. 2:19-cv-12107 (D.N.J. Dec. 17, 2021).
cites § 15.405 1×subsections: (a)cited by 0 casesunknown
Where it cites § 15.405
“804 (a)(5); 48 C.F.R. 15.405(a)-(b). Representing that the price of Zytiga is fair and reasonable was mandated as part of Defendants’ participation in GSA’s Federal Supply Schedule, HHS’s Medicaid Drug Rebate Program, and HHS’s Section 340B Drug Pricing Program, all of which…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
201220162021

One bar per year. Tallest: 1 case in 2012. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.N.J.1E.D. Pa.1Fed. Cl.1
By subsection
(a)1 case
Silbersher v. Janssen Biotech Inc., No. 2:19-cv-12107 (D.N.J. Dec. 17, 2021).“804 (a)(5); 48 C.F.R. 15.405(a)-(b). Representing that the price of Zytiga is fair and reasonable was mandated as part of Defendants’ participation in GSA’s Federal Supply Schedule, HHS’s Medicaid Drug Rebate Program, and HHS’s Section 340B Drug Pricing Program, all of which…”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com