C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter C—Contracting Methods and Contract TypesPart 16—Types of ContractsSubpart 16.3—Cost-Reimbursement Contracts

48 C.F.R. § 16.305 (2026)

16.305 Cost-plus-award-fee contracts.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1997–2009 2citing cases
At a glance

Courts have cited this section in 2 opinions since 1997.

A cost-plus-award-fee contract is a cost-reimbursement contract that provides for a fee consisting of (a) a base amount (which may be zero) fixed at inception of the contract and (b) an award amount, based upon a judgmental evaluation by the Government, sufficient to provide motivation for excellence in contract performance. Cost-plus-award-fee contracts are covered in subpart 16.4, Incentive Contracts. See 16.401(e) for a more complete description and discussion of the application of these contracts. See 16.301-3 and 16.401(e)(5) for limitations.

[48 FR 42219, Sept. 19, 1983, as amended at 62 FR 12695, Mar. 17, 1997; 74 FR 52858, Oct. 14, 2009]
The 2 cases that cite 48 C.F.R. § 16.305 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENGlobal Comput. Enter., Inc. v. United States, 88 Fed. Cl. 350 (Fed. Cl. 2009).
cites § 16.305 1×cited by 46 cases
Where it cites § 16.305
“” 48 C.F.R. § 16.305 . . A time and materials contract "provides for acquiring supplies or services” based upon "(1) [djirect labor hours at specified fixed hourly rates that include wages, overhead, general and administrative expenses, and profit; and (2)[a]c-tual cost for…”
The case’s holding
The jurisdictional bar for bid protests applies to the issuance of a task order but does not extend to modifications of an existing task order.
Later courts cite it for
“although the protest in lbm, inc. concerned the underlying contracts . . ., the court nevertheless finds it instructive" because the protestor "did not challenge the issuance or proposed issuance of a task order under the existing contract.” · 2 citing courts
2
GREENDay & Zimmermann Servs. v. United States, 38 Fed. Cl. 591 (Fed. Cl. 1997).
cites § 16.305 1×cited by 47 cases
Where it cites § 16.305
“Federal Acquisition Regulation (FAR) 48 C.F.R. § 16.305 (1996). . The following abbreviations are used throughout this opinion: Tr.”
The case’s holding
An agency's discretion to decline discussions is not unfettered and must be reasonably based on the particular circumstances of the procurement.
Later courts cite it for
“it is clear that . . . a contracting agency retains discretion in determining whether or not to hold discussions in a particular procurement.” · 2 citing courts

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.