22.407 Solicitation provision and contract clauses.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 ACTIVE · 1 IN 5Y cited 2020–2021 2citing cases
At a glance

Courts have cited this section in 2 opinions since 2020, 1 of them in the last five years.

(a) Insert the following clauses in solicitations and contracts in excess of $2,000 for construction within the United States:

(1) 52.222-6, Construction Wage Rate Requirements.

(2) 52.222-7, Withholding of Funds.

(3) 52.222-8, Payrolls and Basic Records.

(4) 52.222-9, Apprentices and Trainees.

(5) 52.222-10, Compliance with Copeland Act Requirements.

(6) 52.222-11, Subcontracts (Labor Standards).

(7) 52.222-12, Contract Termination—Debarment.

(8) 52.222-13, Compliance with Construction Wage Rate Requirements and Related Regulations.

(9) 52.222-14, Disputes Concerning Labor Standards.

(10) 52.222-15, Certification of Eligibility.

(b) Insert the clause at 52.222-16, Approval of Wage Rates, in solicitations and contracts in excess of $2,000 for cost-reimbursement construction to be performed within the United States, except for contracts with a State or political subdivision thereof.

(c) A contract that is not primarily for construction may contain a requirement for some construction work to be performed in the United States. If under 22.402(b) the requirements of this subpart apply to the construction work, insert in such solicitations and contracts the applicable construction labor standards clauses required in this section and identify the item or items of construction work to which the clauses apply.

(d) [Reserved]

(e) Insert the clause at 52.222-30, Construction Wage Rate Requirements—Price Adjustment (None or Separately Specified Pricing Method), in solicitations and contracts if the contract is expected to be—

(1) A fixed-price contract subject to the Construction Wage Rate Requirements statute that will contain option provisions by which the contracting officer may extend the term of the contract, and the contracting officer determines the most appropriate contract price adjustment method is the method at 22.404-12(c)(1) or (2); or

(2) A cost-reimbursable type contract subject to the Construction Wage Rate Requirements statute that will contain option provisions by which the contracting officer may extend the term of the contract.

(f) Insert the clause at 52.222-31, Construction Wage Rate Requirements—Price Adjustment (Percentage Method), in solicitations and contracts if the contract is expected to be a fixed-price contract subject to the Construction Wage Rate Requirements statute that will contain option provisions by which the contracting officer may extend the term of the contract, and the contracting officer determines the most appropriate contract price adjustment method is the method at 22.404-12(c)(3).

(g) Insert the clause at 52.222-32, Construction Wage Rate Requirements—Price Adjustment (Actual Method), in solicitations and contracts if the contract is expected to be a fixed-price contract subject to the Construction Wage Rate Requirements statute that will contain option provisions by which the contracting officer may extend the term of the contract, and the contracting officer determines the most appropriate method to establish contract price is the method at 22.404-12(c)(4).

(h) Insert the provision at 52.222-5, Construction Wage Rate Requirements—Secondary Site of the Work, in solicitations in excess of $2,000 for construction within the United States.

[53 FR 4935, Feb. 18, 1988, as amended at 66 FR 53481, Oct. 22, 2001; 70 FR 33667, June 8, 2005; 72 FR 27384, May 15, 2007; 79 FR 24205, Apr. 29, 2014]
The 2 cases that cite 48 C.F.R. § 22.407 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENUnited States v. Juan Carlos Bazantes, 978 F.3d 1227 (11th Cir. 2020).
cites § 22.407 1×cited by 9 cases
Where it cites § 22.407
“The second regulation is 48 C.F.R. § 22.407 , which provides that most federal construction contracts must include certain other mandatory terms.”
Later courts cite it for
“to the extent that an earlier decision is distinguishable from the case at hand, it may be a prior precedent, but it is not one that can dic- tate the result of the current case under the prior precedent rule.” · 3 citing courts
cites § 22.407 1×cited by 0 cases
Where it cites § 22.407
“16, 2021); see also 48 C.F.R. § 22.407 (e) (requiring a federal contracting officer to “[i]nsert the clause at 52.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com