252.243-7002 Requests for Equitable Adjustment.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 ACTIVE · 3 IN 5Y cited 2003–2023 7citing cases
At a glance

Courts have cited this section in 7 opinions since 2003, 3 of them in the last five years.

As prescribed in 243.205-71, use the following clause:

Requests for Equitable Adjustment (DEC 2022)

(a) The amount of any request for equitable adjustment to contract terms shall accurately reflect the contract adjustment for which the Contractor believes the Government is liable. The request shall include only costs for performing the change, and shall not include any costs that already have been reimbursed or that have been separately claimed. All indirect costs included in the request shall be properly allocable to the change in accordance with applicable acquisition regulations.

(b) In accordance with 10 U.S.C. 3862(a), any request for equitable adjustment to contract terms that exceeds the simplified acquisition threshold shall bear, at the time of submission, the following certificate executed by an individual authorized to certify the request on behalf of the Contractor:

I certify that the request is made in good faith, and that the supporting data are accurate and complete to the best of my knowledge and belief.

(Official's Name) (Title)

(c) The certification in paragraph (b) of this clause requires full disclosure of all relevant facts, including—

(1) Certified cost or pricing data if required in accordance with subsection 15.403-4 of the Federal Acquisition Regulation (FAR); and

(2) Data other than certified cost or pricing data, in accordance with subsection 15.403-3 of the FAR, including actual cost data and data to support any estimated costs, even if certified cost or pricing data are not required.

(d) The certification requirement in paragraph (b) of this clause does not apply to—

(1) Requests for routine contract payments; for example, requests for payment for accepted supplies and services, routine vouchers under a cost-reimbursement type contract, or progress payment invoices; or

(2) Final adjustment under an incentive provision of the contract.

(End of clause) [63 FR 11549, Mar. 9, 1998, as amended at 66 FR 49865, Oct. 1, 2001; 77 FR 76941, Dec. 31, 2012; 87 FR 76998, Dec. 16, 2022]
The 7 cases that cite 48 C.F.R. § 252.243-7002 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENZafer Constr. Co. v. United States, 40 F.4th 1365 (Fed. Cir. 2022).
cites § 252.243-7002 2×cited by 6 cases
Where it cites § 252.243-7002
“§ 7103 (b)(1), going be- yond what is required by 48 C.F.R. § 252.243-7002 (b) to certify mere requests for equitable adjustment.”
2
GREENLakeshore Eng'g Servs., Inc. v. United States, 748 F.3d 1341 (Fed. Cir. 2014).
cites § 252.243-7002 1×cited by 44 cases
Where it cites § 252.243-7002
“Lakeshore argues that the incorporation of the Department of Defense FAR Supplement provision at 48 C.F.R. § 252.243-7002 (a procedural provision for requests for equitable adjustments) and the inclusion of a price-adjustment provision in the contract support a broader…”
The case’s holding
In a firm fixed-price contract, the contractor assumes the risk of unexpected costs including pricing inaccuracies and inflation.
Later courts cite it for
“the essence of a firm fixed-price contract is that the contractor, not the government, assumes the risk of unexpected costs.” · 9 citing courts
3
GREENJohnson v. Advanced Eng'g & Plan. Corp., 292 F. Supp. 2d 846 (E.D. Va. 2003).
cites § 252.243-7002 1×cited by 3 cases
Where it cites § 252.243-7002
“” 48 C.F.R. § 252.243-7002 (b). 13 . In this respect, the Board also made note of the following to bolster its conclusion: In this regard, DFARS 243.”
4
GREENJ.P. Donovan Constr., Inc. v. Mabus, 469 F. App'x 903 (Fed. Cir. 2012).
cites § 252.243-7002 1×cited by 2 casesunpublished
Where it cites § 252.243-7002
“48 C.F.R. § 252.243-7002 (1998). In October 2002, Donovan subcontracted with Costello Industries, Inc.”
5
NO FLAGMidatlantic Constr. & Design Assocs., Inc. v. United States, No. 22-447 (Fed. Cl. May 5, 2023).
cites § 252.243-7002 2×cited by 0 casesunpublished
Where it cites § 252.243-7002
“4th at 1367 (citing 48 C.F.R. § 252.243-7002 (b)). 6In this case, by letter dated July 6, 2017, the contracting officer timely notified MCDA of the contractor’s failure to certify the May 8, 2017 REA.”
6
NO FLAGH&M Assocs., LLC. v. United States, No. 22-110 (Fed. Cl. Mar. 31, 2023).
cites § 252.243-7002 1×cited by 0 cases
Summary
No passage or summary on file for this case yet.
7
NO FLAGTherapure Biopharma, Inc. v. DynPort Vaccine Co., No. 1:19-cv-02092 (D. Md. June 5, 2020).
cites § 252.243-7002 1×cited by 0 casesunknown
Where it cites § 252.243-7002
“) Moreover, DVC concedes that “Therapure may be entitled to some equitable adjustment as a result of the stop work orders, as generally provided for in 48 C.F.R. § 252.243-7002 .” (Defendant’s Mot.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
200320132023

One bar per year. Tallest: 2 cases in 2023. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cir.3Fed. Cl.2D. Md.1E.D. Va.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com