48 C.F.R. § 42.1203 (2026)

42.1203 Processing agreements.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2008–2019 2citing cases
At a glance

Courts have cited this section in 2 opinions since 2008.

(a) If a contractor wishes the Government to recognize a successor in interest to its contracts or a name change, the contractor must submit a written request to the responsible contracting officer (see 42.1202). If the contractor received its contract under subpart 8.7 under 41 U.S.C. chapter 85, Committee for Purchase from People Who Are Blind or Severely Disabled, use the procedures at 8.716 instead.

(b) The responsible contracting officer shall—

(1) Identify and request that the contractor submit the information necessary to evaluate the proposed agreement for recognizing a successor in interest or a name change. This information should include the items identified in 42.1204 (e) and (f) or 42.1205(a), as applicable;

(2) Notify each contract administration office and contracting office affected by a proposed agreement for recognizing a successor in interest, and provide those offices with a list of all affected contracts; and

(3) Request submission of any comments or objections to the proposed transfer within 30 days after notification. Any submission should be accompanied by supporting documentation.

(c) Upon receipt of the necessary information, the responsible contracting officer shall determine whether or not it is in the Government's interest to recognize the proposed successor in interest on the basis of—

(1) The comments received from the affected contract administration offices and contracting offices;

(2) The proposed successor's responsibility under subpart 9.1, Responsible Prospective Contractors; and

(3) Any factor relating to the proposed successor's performance of contracts with the Government that the Government determines would impair the proposed successor's ability to perform the contract satisfactorily.

(d) The execution of a novation agreement does not preclude the use of any other method available to the contracting officer to resolve any other issues related to a transfer of contractor assets, including the treatment of costs.

(e) Any separate agreement between the transferor and transferee regarding the assumption of liabilities (e.g., long-term incentive compensation plans, cost accounting standards noncompliances, environmental cleanup costs, and final overhead costs) should be referenced specifically in the novation agreement.

(f) Before novation and change-of-name agreements are executed, the responsible contracting officer shall ensure that Government counsel has reviewed them for legal sufficiency.

(g) The responsible contracting officer shall (1) forward a signed copy of the executed novation or change-of-name agreement to the transferor and to the transferee and (2) retain a signed copy in the case file.

(h) Following distribution of the agreement, the responsible contracting officer shall—

(1) Prepare a Standard Form 30, Amendment of Solicitation/Modification of Contract, incorporating a summary of the agreement and attaching a complete list of contracts affected;

(2) Retain the original Standard Form 30 with the attached list in the case file;

(3) Send a signed copy of the Standard Form 30, with attached list to the transferor and to the transferee; and

(4) Send a copy of this Standard Form 30 with attached list to each contract administration office or contracting office involved, which shall be responsible for further appropriate distribution.

[48 FR 42370, Sept. 19, 1983, as amended at 62 FR 64934, Dec. 9, 1997; 63 FR 1533, Jan. 9, 1998; 64 FR 51834, Sept. 24, 1999; 79 FR 24213, Apr. 29, 2014]
The 2 cases that cite 48 C.F.R. § 42.1203 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENAlabama Aircraft Indus., Inc.-Birmingham v. United States, 83 Fed. Cl. 666 (Fed. Cl. 2008).
cites § 42.1203 1×cited by 25 cases
Where it cites § 42.1203
“The government's reliance on the provision of the FAR codified at 48 C.F.R. § 42.1203 , requiring notification of the contracting officer to approve a name change or a successor-in-interest, is misplaced, as its own brief recognizes: "[w]e acknowledge that this FAR provision is…”
The case’s holding
An agency must identify and mitigate organizational conflicts of interest that could impair objectivity or create an unfair competitive advantage through access to sensitive information.
Later courts cite it for
“access to 'the kind of specific, sensitive information that would create an oci,” · 3 citing courts
2
NO FLAGDcx-Chol Enter., Inc. v. United States, No. 18-395 (Fed. Cl. June 13, 2019).
cites § 42.1203 1×cited by 0 cases
Where it cites § 42.1203
“It primarily argues that plaintiff failed to allege that the request for the novation came from the contractor awarded the subject contracts, although that party’s participation is required under 48 C.F.R. § 42.1203 . Id. at 6 . The transferor of the contracts was identified in…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.