C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter G—Contract ManagementPart 42—Contract Administration and Audit ServicesSubpart 42.7—Indirect Cost Rates

48 C.F.R. § 42.707 (2026)

42.707 Cost-sharing rates and limitations on indirect cost rates.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2016 1citing case
At a glance

Courts have cited this section in 1 opinion since 2016.

(a) Cost-sharing arrangements, when authorized, may call for the contractor to participate in the costs of the contract by accepting indirect cost rates lower than the anticipated actual rates. In such cases, a negotiated indirect cost rate ceiling may be incorporated into the contract for prospective application. For cost sharing under research and development contracts, see 35.003(b).

(b)(1) Other situations may make it prudent to provide a final indirect cost rate ceiling in a contract. Examples of such circumstances are when the proposed contractor—

(i) Is a new or recently reorganized company, and there is no past or recent record of incurred indirect costs;

(ii) Has a recent record of a rapidly increasing indirect cost rate due to a declining volume of sales without a commensurate decline in indirect expenses; or

(iii) Seeks to enhance its competitive position in a particular circumstance by basing its proposal on indirect cost rates lower than those that may reasonably be expected to occur during contract performance, thereby causing a cost overrun.

(2) In such cases, an equitable ceiling covering the final indirect cost rates may be negotiated and specified in the contract.

(c) When ceiling provisions are utilized, the contract shall also provide that (1) the Government will not be obligated to pay any additional amount should the final indirect cost rates exceed the negotiated ceiling rates and, (2) in the event the final indirect cost rates are less than the negotiated ceiling rates, the negotiated rates will be reduced to conform with the lower rates.

The 1 case that cites 48 C.F.R. § 42.707 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENScott Carlson v. DynCorp Int'l LLC, 657 F. App'x 168 (4th Cir. 2016).
cites § 42.707 1×cited by 21 casesunpublished
Where it cites § 42.707
“” 48 C.F.R. § 42.707 (b)(l)(iii). Carlson’s complaint does not contain “enough factual matter (taken as true) to suggest that” DynCorp made or was about to make' a false claim on the government.”
The case’s holding
Objecting to billing practices is not protected FCA activity unless the belief reflects a plausible false claim or fraudulent overbilling mechanism against the government; an unreasonable belief is unprotected.
Later courts cite it for
“motivated by an objectively reasonable belief that the employee's employer is violating, or soon will violate, the fca.” · 4 citing courts

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com