43.201 General.
Courts have cited this section in 2 opinions since 1993. The most litigated part is subsection (a) (1 case).
(a) Generally, Government contracts contain a changes clause that permits the contracting officer to make unilateral changes, in designated areas, within the general scope of the contract. These are accomplished by issuing written change orders on Standard Form 30, Amendment of Solicitation/Modification of Contract (SF 30), unless otherwise provided (see 43.301).
(b) The contractor must continue performance of the contract as changed, except that in cost-reimbursement or incrementally funded contracts the contractor is not obligated to continue performance or incur costs beyond the limits established in the Limitation of Cost or Limitation of Funds clause (see 32.706-2).
(c) The contracting officer may issue a change order by electronic means without a SF 30 under unusual or urgent circumstances, provided that the message contains substantially the information required by the SF 30 and immediate action is taken to issue the SF 30.
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.