43.201 General.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1993–2004 2citing cases
At a glance

Courts have cited this section in 2 opinions since 1993. The most litigated part is subsection (a) (1 case).

(a) Generally, Government contracts contain a changes clause that permits the contracting officer to make unilateral changes, in designated areas, within the general scope of the contract. These are accomplished by issuing written change orders on Standard Form 30, Amendment of Solicitation/Modification of Contract (SF 30), unless otherwise provided (see 43.301).

(b) The contractor must continue performance of the contract as changed, except that in cost-reimbursement or incrementally funded contracts the contractor is not obligated to continue performance or incur costs beyond the limits established in the Limitation of Cost or Limitation of Funds clause (see 32.706-2).

(c) The contracting officer may issue a change order by electronic means without a SF 30 under unusual or urgent circumstances, provided that the message contains substantially the information required by the SF 30 and immediate action is taken to issue the SF 30.

[48 FR 42386, Sept. 19, 1983, as amended at 78 FR 37689, June 21, 2013; 81 FR 83099, Nov. 18, 2016]
The 2 cases that cite 48 C.F.R. § 43.201 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENFirst Enter. v. United States, 61 Fed. Cl. 109 (Fed. Cl. 2004).
cites § 43.201 1×cited by 22 cases
Where it cites § 43.201
“” 48 C.F.R. § 43.201 (a). Plaintiff claims that a contracting officer can also issue a “negative” change order which “decreases the scope of work or the cost of the total project.”
Later courts cite it for
“an agency has virtually a carte blanche right to decide the amount of funding it will spend on a given project.” · 2 citing courts
2
NO FLAGUSA for u v., No. 93-1541 (1st Cir. Nov. 29, 1993).
cites § 43.201 2×subsections: (a)cited by 0 cases
Where it cites § 43.201
“Despite Sun Engineering's contention to the contrary, 48 C.F.R. 43.201 (1992) does not impose such a requirement.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection
(a)1 case
USA for u v., No. 93-1541 (1st Cir. Nov. 29, 1993).“Despite Sun Engineering's contention to the contrary, 48 C.F.R. 43.201 (1992) does not impose such a requirement.”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com