44.202-2 Considerations.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2014 1citing case
At a glance

Courts have cited this section in 1 opinion since 2014.

(a) The contracting officer responsible for consent must, at a minimum, review the request and supporting data and consider the following:

(1) Is the decision to subcontract consistent with the contractor's approved make-or-buy program, if any (see 15.407-2)?

(2) Is the subcontract for special test equipment, equipment or real property that are available from Government sources?

(3) Is the selection of the particular supplies, equipment, or services technically justified?

(4) Has the contractor complied with the prime contract requirements regarding—

(i) Small business subcontracting, including, if applicable, its plan for subcontracting with small, veteran-owned, service-disabled veteran-owned, HUBZone, small disadvantaged and women-owned small business concerns (see part 19); and

(ii) Purchase from nonprofit agencies designated by the Committee for Purchase From People Who Are Blind or Severely Disabled (41 U.S.C. 8504) (see part 8)?

(5) Was adequate price competition obtained or its absence properly justified?

(6) Did the contractor adequately assess and dispose of subcontractors' alternate proposals, if offered?

(7) Does the contractor have a sound basis for selecting and determining the responsibility of the particular subcontractor?

(8) Has the contractor performed adequate cost or price analysis or price comparisons and obtained certified cost or pricing data and data other than certified cost or pricing data?

(9) Is the proposed subcontract type appropriate for the risks involved and consistent with current policy?

(10) Has adequate consideration been obtained for any proposed subcontract that will involve the use of Government-provided equipment and real property?

(11) Has the contractor adequately and reasonably translated prime contract technical requirements into subcontract requirements?

(12) Does the prime contractor comply with applicable cost accounting standards for awarding the subcontract?

(13) Is the proposed subcontractor listed as excluded in the System for Award Management (see subpart 9.4)?

(b) Particularly careful and thorough consideration under paragraph (a) above is necessary when—

(1) The prime contractor's purchasing system or performance is inadequate;

(2) Close working relationships or ownership affiliations between the prime and subcontractor may preclude free competition or result in higher prices;

(3) Subcontracts are proposed for award on a non-competitive basis, at prices that appear unreasonable, or at prices higher than those offered to the Government in comparable circumstances; or

(4) Subcontracts are proposed on a cost-reimbursement, time-and-materials, or labor-hour basis.

[48 FR 42388, Sept. 19, 1983, as amended at 60 FR 33066, June 26, 1995; 60 FR 48264, Sept. 18, 1995; 62 FR 51271, Sept. 30, 1997; 63 FR 34060, June 22, 1998; 66 FR 65368, Dec. 18, 2001; 69 FR 76349, Dec. 20, 2004; 72 FR 27385, May 15, 2007; 73 FR 53995, Sept. 17, 2008; 75 FR 53149, Aug. 30, 2010; 78 FR 37680, June 21, 2013; 79 FR 24213, Apr. 29, 2014; 83 FR 48698, Sept. 26, 2018]
The 1 case that cites 48 C.F.R. § 44.202-2 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENUnited States v. Lockheed Martin Corp., 14 F. Supp. 3d 982 (S.D. Ohio 2014).
cites § 44.202-2 1×cited by 13 cases
Where it cites § 44.202-2
“48 C.F.R. § 44.202-2 (b). A Lockheed internal policy prohibited it from “retaining] the services of a retiree through a third party vendor within six months of the individual’s retirement” from Lockheed, (CSOF Ex.”
Later courts cite it for
“employment decisions are only materially adverse if they are reasonably likely to deter employees from engaging in activity protected by the false claims act.” · 2 citing courts

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com