48 C.F.R. § 49.207

49.207 Limitation on settlements.

Read at: eCFRecfr.gov CornellLII GovInfogovinfo.gov CasesGoogle Scholar

The total amount payable to the contractor for a settlement, before deducting disposal or other credits and exclusive of settlement costs, must not exceed the contract price less payments otherwise made or to be made under the contract.

Notes of Decisions
Cited in 1 case, 2002–2002 · leading case: White Buffalo Constr., Inc. v. United States, 52 Fed. Cl. 1 (Fed. Cl. 2002).
White Buffalo Constr., Inc. v. United States, 52 Fed. Cl. 1 (Fed. Cl. 2002). · cites it 3× “48 C.F.R. § 49.207 (2001) (emphasis added); see also 48 C.”
Annotations are extracted automatically from the opinions in the Syfert caselaw corpus and ranked by authority, recency, and treatment. Dots show Syfertize treatment of the citing case itself.