49.404 Surety-takeover agreements.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2000–2019 3citing cases
At a glance

Courts have cited this section in 3 opinions since 2000.

(a) The procedures in this section apply primarily, but not solely, to fixed-price construction contracts terminated for default.

(b) Since the surety is liable for damages resulting from the contractor's default, the surety has certain rights and interests in the completion of the contract work and application of any undisbursed funds. Therefore, the contracting officer must consider carefully the surety's proposals for completing the contract. The contracting officer must take action on the basis of the Government's interest, including the possible effect upon the Government's rights against the surety.

(c) The contracting officer should permit surety offers to complete the contract, unless the contracting officer believes that the persons or firms proposed by the surety to complete the work are not competent and qualified or the proposal is not in the best interest of the Government.

(d) There may be conflicting demands for the defaulting contractor's assets, including unpaid prior earnings (retained percentages and unpaid progress estimates). Therefore, the surety may include a “takeover” agreement in its proposal, fixing the surety's rights to payment from those funds. The contracting officer may (but not before the effective date of termination) enter into a written agreement with the surety. The contracting officer should consider using a tripartite agreement among the Government, the surety, and the defaulting contractor to resolve the defaulting contractor's residual rights, including assertions to unpaid prior earnings.

(e) Any takeover agreement must require the surety to complete the contract and the Government to pay the surety's costs and expenses up to the balance of the contract price unpaid at the time of default, subject to the following conditions:

(1) Any unpaid earnings of the defaulting contractor, including retained percentages and progress estimates for work accomplished before termination, must be subject to debts due the Government by the contractor, except to the extent that the unpaid earnings may be used to pay the completing surety its actual costs and expenses incurred in the completion of the work, but not including its payments and obligations under the payment bond given in connection with the contract.

(2) The surety is bound by contract terms governing liquidated damages for delays in completion of the work, unless the delays are excusable under the contract.

(3) If the contract proceeds have been assigned to a financing institution, the surety must not be paid from unpaid earnings, unless the assignee provides written consent.

(4) The contracting officer must not pay the surety more than the amount it expended completing the work and discharging its liabilities under the defaulting contractor's payment bond. Payments to the surety to reimburse it for discharging its liabilities under the payment bond of the defaulting contractor must be only on authority of—

(i) Mutual agreement among the Government, the defaulting contractor, and the surety;

(ii) Determination of the Comptroller General as to payee and amount; or

(iii) Order of a court of competent jurisdiction.

[65 FR 46067, July 26, 2000]
The 3 cases that cite 48 C.F.R. § 49.404 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENHome Ins. v. United States, 46 Fed. Cl. 160 (Fed. Cl. 2000).
cites § 49.404 3×cited by 5 cases
Where it cites § 49.404
“” This language was lifted from 48 C.F.R. § 49.404 (e), which controls takeover agreements in construction contracts prompted by contractor default.”
2
NO FLAGLiberty Mut. Ins. Co. v. Int'l Fid. Ins. Co, No. 18-1455 (8th Cir. Apr. 12, 2019).
cites § 49.404 1×cited by 0 cases
Where it cites § 49.404
“See 48 C.F.R. § 49.404 . -5- When a general contractor’s surety takes over completion of a federal government construction project and “steps in the shoes” of its principal, the purposes of the Miller Act and the FAR regulations to protect the government are served if the surety…”
3
NO FLAGUnited States v. Liberty Mut. Ins. Co., 921 F.3d 744 (8th Cir. 2019).
cites § 49.404 1×cited by 0 cases
Where it cites § 49.404
“See 48 C.F.R. § 49.404 . When a general contractor's surety takes over completion of a federal government construction project and "steps in the shoes" of its principal, the purposes of the Miller Act and the FAR regulations to protect the government are served if the surety is…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
200020092019

One bar per year. Tallest: 2 cases in 2019. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
8th Cir.2Fed. Cl.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com