52.236-27 Site Visit (Construction).

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2005 2citing cases
At a glance

Courts have cited this section in 2 opinions since 2005.

As prescribed in 36.523, insert a provision substantially the same as the following:

Site Visit (Construction) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigation and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting:

Name: Address: Telephone:
(End of provision)

Alternate I (FEB 1995). If an organized site visit will be conducted, substitute a paragraph substantially the same as the following for paragraph (b) of the basic provision:

(b) An organized site visit has been scheduled for—

[Insert date and time]

(c) Participants will meet at—

[Insert location]
(End of provision) [59 FR 67050, Dec. 28, 1994; 60 FR 14377, Mar. 17, 1995]
The 2 cases that cite 48 C.F.R. § 52.236-27 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENConner Bros. Constr. Co. v. United States, 65 Fed. Cl. 657 (Fed. Cl. 2005).
cites § 52.236-27 1×cited by 30 cases
Where it cites § 52.236-27
“236-27, Site Visit (Construction), see 48 C.F.R. § 52.236-27 (1995) (hereinafter site visit clause).”
The case’s holding
Work that a fixed-price contract unambiguously requires, even if more costly than anticipated, is not a compensable change entitling the contractor to an equitable adjustment under the changes clause.
Later courts cite it for
“the spirit and purpose of an equitable adjustment, such as that sought by plaintiff here, is to benefit the contractor and make it whole for changes ordered by the government.” · 2 citing courts
2
GREENS. Comfort Builders, Inc. v. United States, 67 Fed. Cl. 124 (Fed. Cl. 2005).
cites § 52.236-27 1×cited by 9 cases
Where it cites § 52.236-27
“1984) (incorporated by reference into the contract through 48 C.F.R. § 52.236-27 (Feb.1995)) states that: “The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com